HomeMy WebLinkAbout#21 Easton Village Park Additional Cost Approval Request 09062016MAYOR AND COUNCIL COMMUNICATION DATE: 09/06/2016 CONSENT ITEM #: 21 AGENDA ITEM: Easton Village Additional Cost Approval Request SUBMITTED BY: Emily Becker, City Planner THROUGH: Kristina Handt, City Administrator REVIEWED BY: Stephen Wensman, Planning Director BACKGROUND: At the April 5, 2016 City Council meeting, the Council directed Staff to coordinate with Easton Village developer to grade the park pad and to install concrete curbing while Easton Village crews on site, to purchase proposed large park amenities and have amenities installed this summer. The estimated cost for this project was $75,000, which included installation, rubber mulch, curbing, and grading. The actual cost of the playground equipment, including rubber mulch and installation, came in to be $71,927.52. The staff report from the April 5, 2016 City Council meeting stated the estimated cost of installation of concrete curbing would be $2970. On August 3, 2016, the Easton Village developer met with Staff to discuss the poor drainage underneath the swings of the playground area and the need for draintile. Public Works Staff suggested that the developer install the draintile along with the concrete curbing. The developer was asked to provide a quote for the draintile so the cost could be approved by Council. A few weeks later, Staff was made aware that draintile had been installed without a Council approved quote. Staff contacted the developer regarding the installation, and the developer communicated that it was felt that the lack of drainage was creating a safety issue, so their contractor was directed to install the draintile (the concrete curbing has not yet been installed). The developer then provided a quote of $7241.50 for the installation of concrete curbing and $3475.00 for the draintile, totaling $10,716.50. It should be noted that the quote does not include site surveying/staking, soil conditionaing, testing, bonds, permits or turf restoration. ISSUE BEFORE COUNCIL: The Council is requested to approve the additional cost for the installation of draintile for Easton Village Park. With the installation of the playground equipment, the revised, total cost of the project will be closer to $82,644.02, as compared to the $75,000 budgeted for this project. PROPOSAL DETAILS/ANALYSIS: City Council Meeting 09/06/2016 Consent Agenda Item #22 Page 2 The first attached photo shows what the playground had looked like without the draintile. The water had nowhere to drain, and the playground could not be safely utilized as a result. The second photo shows that the draintile properly drained the playground area. Staff asked the developer why the quote for the concrete curbing was so much more than what was quoted in the April 5, 2016 City Council Staff Report, and the developer replied that he believes that quote was for the plastic curbing, which Staff did not recommend installing due to its inferior durability. Staff has confirmed that the quote provided for concrete curbing, though higher than the cost estimate provided at the April 5, 2016 Council meeting, is reasonable; the seemingly high per square foot cost could be attributable to the smaller size of the park’s perimeter. FISCAL IMPACT: The total cost of the playground will be $82,644.02, $7644.02 more than what was budgeted for the park. OPTIONS:  Approve reimbursement of draintile cost and increased cost estimate for concrete curbing.  Deny reimbursement of draintile cost and increased cost estimate for concrete curbing.  Approve reimbursement of draintile and direct Staff to gather bids for concrete curbing.  Approve reimbursement of draintile and direct that the developer install plastic curbing, decreasing the cost. RECOMMENDATION: Staff recommends that Council approve, as part of tonight’s consent agenda, the additional cost for installation of concrete curbing and draintile in Easton Village Park. The base bid given for the installation of draintile and concrete curbing is $10,716.50. If the Council chooses to remove this item from the Consent Agenda, the recommended action can be take through the following motion: “Move to approve reimbursement of $10,716.50, plus possible necessary excluded costs listed on the bid, to Easton Village developer for the installation of draintile and concrete curb once all work on the aforementioned is complete.” ATTACHMENTS:  Quote from Easton Village  Photos of playground before and after draintile was installed.  Easton Village playground equipment invoice City Council Meeting 09/06/2016 Consent Agenda Item #22 Page 3 Photos of Easton Village Park Without Draintile Installed City Council Meeting 09/06/2016 Consent Agenda Item #22 Page 4 Photos of Easton Village Park With Draintile Installed City Council Meeting 09/06/2016 Consent Agenda Item #22 Page 5 PROPOSAL FRIEDGES, INC. Landscaping · Excavating Contractors 9380 202nd Street West, Lakeville, MN 55044 (952) 469-2996 · Fax: (952) 469-1755 Job: Lake Elmo Playground Date 8/19/16 STREET CITY, STATE and ZIP CODE Lake Elmo, MN JOB LOCATION ARCHITECT DATE OF PLANS JOB PHONE We Propose hereby to furnish material and labor – complete in accordance with specifications below, for the sum of: * * * See Below * * * All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard practices. Any alteration or deviation from specifications below involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate. All agreements contingent upon strikes, accidents or delays beyond our control. Owner to carry fire, tornado, and other necessary insurance. Our workers are fully covered by Workman's Compensation Insurance. Authorized Signature ______ Note: This proposal may be withdrawn by us if not accepted within 30 (thirty) days. Work for Playground We hereby submit the following:  350LF of Playground Curb Furnished and Installed @ $20.69/LF Total: 7,241.50 Includes base work  Core Drill Drain Tile into existing Structure and 316LF of 4” Drain Tile, Fabric and Rock running from structure to city’s specified location @ $3,475.00 Grand Total: $10,716.50 Excludes: *Site Survey/ Staking *Soil Conditioning/ Testing *Bonds *Permits *Turf Restoration PLEASE CALL IF YOU HAVE ANY QUESTIONS Acceptance of Proposal – The above prices; specifications and conditions are satisfactory and are hereby accepted. You are authorized to do the work as specified. Payment will be made as outlined above. By signing you have read and are familiar with the Minnesota Mechanic's Lien Law. Signature ________________ Date ________