MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: September 20, 2016
CONSENT
ITEM # 9
AGENDA ITEM: 2016 Street, Drainage, and Utility Improvements – Change Order No. 2
SUBMITTED BY: Chad Isakson, Project Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer
Cathy Bendel, Finance Director
SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: $22,187.40.
This change order increases the contract amount for the project by $22,157.40 bringing the
revised construction contract to $1,244,774.28. With these change order items the project
remains within the authorized project budget and contingenc y amount.
SUMMARY AND ACTION REQUESTED: The City Council is respectfully requested to
consider approving Change Order No. 2 for the 2016 Street, Drainage, and Utility Improvements
project.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION: This change order is being
processed at the request of the City to address additional construction items needing to be
completed as part of the street and drainage improvements to maintain the integrity of the
infrastructure being built.
1. Additional costs in the amount of $11,445 was needed to replace three catch basin
structures along Highland Trail that were discovered in the field to be structurally
City Council Meeting [Consent Agenda Item 9]
September 20, 2016
-- page 2 --
damaged. If they had not been replaced they would have eventually failed structurally
which would have resulted in early pavement failure to the newly constructed street.
2. Additional costs in the amount of $9,303.50 was needed to install 155 linear feet of
draintile to address subsurface water that was discovered upon excavation of the street in
several locations in the Stonegate neighborhood. The saturated conditions needed to be
drained to prevent undermining of the street subgrade.
3. A 6%-unit price deduct was accepted for the installation of material meeting Class 5
aggregate base specifications instead of Class 6 aggregate base specifications. This
resulted in a contract deduct in the amount of $1,061.10 for the Kirkwood Avenue
neighborhood.
4. Additional costs in the amount of $2,500 was needed to complete a full depth patch to a
section of roadway along Jamley Avenue to replace poor subgrade material that was
causing pavement to breakup and crack.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the
Consent Agenda, Change Order No. 2 for the 2016 Street, Drainage, and Utility Improvements
project. If removed from the consent agenda, the recommended motion for the action is as
follows:
“Move to approve Change Order No. 2 for the 2016 Street, Drainage, and Utility
Improvements thereby increasing the contract amount by $22,187.40.”
ATTACHMENT(S):
1. Change Order No. 2.
CONTRACT CHANGE ORDER FORM
CHANGE ORDER NO. DATE:
TO:
UNIT
Amount of Original Contract $
Sum of Additions/Deductions approved to date (CO Nos. 1 ) $
Contract Amount to date $
Amount of this Change Order (ADD) (DEDUCT) (NO CHANGE)$
Revised Contract Amount $
The Contract Period for Completion will be (UNCHANGED) (INCREASED) (DECREASED)days
APPROVED BY ENGINEER: FOCUS Engineering, inc. APPROVED BY CONTRACTOR
DATE DATE
APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA
DATE DATE
0
This Document will become a supplement to the Contract and all provisions will apply hereto. The Contract Documents are
modified as follows upon execution of this Change Order.
BYENGINEER
1,189,610.33
32,976.55
1,222,586.88
22,187.40
1,244,774.28
INCREASE/(DECREASE)
HARDRIVES, INC. 14475 QUIRAM DRIVE ROGERS, MN 55374
2016 STREET, DRAINAGE AND UTILITY IMPROVEMENTS
PROJECT NO. 2015.129
2 September 12, 2016
ITEM
$22,187.40
NET CONTRACT CHANGE $22,187.40
CITY OF LAKE ELMO, MINNESOTA
BYBY
CHANGE ORDER DESCRIPTION / JUSTIFICATION:
This change order is being processed to amend the Contract for the following reasons:
1) Items CO2‐1 and CO2‐2: Replacement of three catch basins on Highlands Trail that were discovered to be damaged and would cause future
pavement failure if left in place.
2) Items CO2‐3 to CO2‐8: Installation of draintile, cleanouts, and connection of the draintile to existing storm sewer to drain a saturated
subgrade between storm sewer structures 111 and 108 on Jasmine Avenue.
3) Items CO2‐9 to CO2‐10): 6% unit price deduct for the installation of material meeting Class 5 gravel specifications instead of Class 6 along
Kirkwood Avenue.
4) Item CO2‐11: Complete a full depth patch on Jamley Avenue due to poor subgrade material causing pavement to breakup and crack.
Attachments (list documents supporting change):Itemization of Materials
DESCRIPTION OF PAY ITEM QTY UNIT PRICE
**See attached itemization
9/12/2016
FOCUS Engineering, inc.CHANGE ORDER FORM
CHANGE ORDER NO. 2
2016 STREET, DRAINAGE AND UTILITY IMPROVEMENTS
CITY OF LAKE ELMO, MINNESOTA
PROJECT NO. 2015.129
QUANTITY UNIT PRICE AMOUNT
CO2‐1 EA 3.0 $715.00 $2,145.00
CO2‐2 EA 3.0 $3,100.00 $9,300.00
CO2‐3 LF 155.0 $22.50 $3,487.50
CO2‐4 TN 13.0 $125.00 $1,625.00
CO2‐5 EA 2.0 $825.00 $1,650.00
CO2‐6 LS 1.0 $1,200.00 $1,200.00
CO2‐7 HR 3.0 $245.00 $735.00
CO2‐8 HR 6.0 $101.00 $606.00
CO2‐9 CY ‐655.0 $27.03 ‐$17,704.65
CO2‐10 CY 655.0 $25.41 $16,643.55
CO2‐11 LS 1.0 $2,500.00 $2,500.00
TOTALS ‐ CHANGE ORDER NO. 2 $22,187.40
ITEM DESCRIPTION OF PAY ITEM UNIT
CHANGE ORDER
TYPE SP 9.5 BITUMINOUS WEAR COURSE FOR PATCHING
REMOVE EXISTING CATCH BASIN
2'X3' CATCH BASIN WITH INVERTS
4" PVC PERFORATED EDGE DRAIN WITH BACKFILL & WRAP
EXPLORATORY DIGGING (STROM SEWER STRUCTURE 111)
CLASS 5 AGGREGATE BASE (CV) (P)
CLASS 6 AGGREGATE BASE (CV) (P)
This change order is being processed to amend the Contract for the
following reasons:
1) Items CO2‐1 and CO2‐2: Replacement of three catch basins on
Highlands Trail that were discovered to be damaged and would cause
future pavement failure if left in place.
2) Items CO2‐3 to CO2‐8: Installation of draintile, cleanouts, and
connection of the draintile to existing storm sewer to drain a saturated
subgrade between storm sewer structures 111 and 108 on Jasmine
Avenue.
3) Items CO2‐9 to CO2‐10): 6% unit price deduct for the installation of
material meeting Class 5 gravel specifications instead of Class 6 along
Kirkwood Avenue.
4) Item CO2‐11: Complete a full depth patch on Jamley Avenue due to
poor subgrade material causing pavement to breakup and crack.
DESCRIPTION / JUSTIFICATION
YARD GRADING
FULL DEPTH PATCH
CONNECT TO EXISTING STORM SEWER STRUCTURE
MOBILIZATION