HomeMy WebLinkAboutItem 4b THE CITY OF PLANNING COMMISSION
LAKE ELMO DATE: 7/25/16
AGENDA ITEM: 4Ir PUBLIC HEAR ITEM
CASE#2016-24
ITEM: Rezoning/PUD Amendment—Boulder Ponds
SUBMITTED BY: Stephen Wensman, Planning Director
REVIEWED BY: Emily Becker, City Planner
SUMMARY AND ACTION REQUESTED:
OP4 Boulder Ponds LLC is requesting approval of a rezoning/PUD amendment to the Boulder Ponds
PUD to rezone Outlots B (PID#34.029.21.33.0023) and C (PID# 34.029.21.33.0024), Boulder
Ponds from Commercial PUD and MDR-PUD, respectively to HDR-PUD.
GENERAL INFORMATION
Applicant: OP4 Boulder Ponds LLC
Property Owners: OP4 Boulder Ponds LLC
Location: Jade Trail North, South of 5th Street
Request: rezoning/PUD amendment to the Boulder Ponds PUD to rezone Outlots B and
C, Boulder Ponds from Commercial PUD and MDR-PUD, respectively to
HDR-PUD
Existing Land Use and Zoning: Undeveloped outlots - Commercial PUD/MDR PUD
Surrounding Land Use and Zoning: LDR to the north,vacant- Commercial PUD outlot to the east,
BP to the west, vacant Commercial PUD outlot to the south
Comprehensive Plan: MDR/Commercial
History: Boulder Ponds Preliminary Plat was approved on 7/28/14. The subject parcels were
rezoned from RT to Commercial PUD/MDR PUD on 4/21/15.
Deadline forAction: Application Complete—6/27/16
60 Day Deadline—8/26/16
Extension Letter Mailed—N/A
120 Day Deadline—N/A
Applicable Regulations: Article XVI, Chapter 154, Sections 750-760, PUD Regulations
Article X—Urban Residential Districts
Planning Commission Meeting 7125116 Page 2
REQUEST DETAILS:
OP4 Boulder Ponds is requesting a Rezoning/PUD Amendment of two parcels, Outlot B and C, from
Commerical/PUD and MDR/PUD respectively,to HDR/PUD in order to better market the parcels for
a future Senior Housing Development.
Outlot B is presently zoned for Commercial/PUD and is 1.44 acres in size. Outlot C is presently
zoned for MDR/PUD and is 2.24 acres in size. The applicant would like to rezone both parcels to
HDR/PUD and market them together for a proposed senior housing project.
REVIEW AND ANALYSIS:
According to Article XVI, Chapter 15, Section 757, Subd C of the Planned Unit Development Code,
PUD Amendments shall be authorized by an amendment of the final development plan under the
procedures for zoning amendment in Article III of the City Code of Ordinances.
The rationale for the housing density in the MDR portion of Boulder Ponds was described in the
12/09/13 Planning Report for the Boulder Ponds PUD Concept Plan:
The medium density area,which is approximately 10.1 acres, contains 81 residential units (17
single family, 64 multi-family),resulting in a gross density of 7.98 units per acre. It should be
noted that this density figure is slightly higher than what is guided by the Comprehensive Plan.
However, given that the proposed development is a PUD, and that the amount of land guided
for medium density residential development on these parcels by the Comprehensive Plan is
much greater, Staff has determined that the proposed Concept Plan meets the spirit and intent
of the Comprehensive Plan. To explain Staff s reasoning for this determination in another
way,the proposed Concept Plan decreases the amount of total land guided for medium density
development by over 20 acres by moving the collector road south. The slight increase in
density above the allowed range per the Comp Plan is balanced by the significant reduction in
the amount of land guided medium density. To put it in simple terms,by using the low end of
gross density ranges in the Comp Plan,these parcels were guided to have 195 total residential
units (not accounting for road right-of-way),whereas the proposed PUD Concept Plan includes
157 total units. Overall,the proposed PUD Concept Plan is consistent with the intent of the
land use and density requirements as guided by the City's Comprehensive Plan.
The rationale for the density is sound,however,when it recommending subsequent zoning for the
sites, Staff had recommended LDR/PUD for the single family cul-de-sac,Jade Circle North, and
MDR/PUD for the senior housing parcel (Outlot Q. Outlot B was zoned Commercial PUD. The
LDR/PUD zoning is the correct zoning for the single family housing on Jade Circle North just
south of 5th Street,but the remaining 2.240 acre parcel (Outlot C)was zoned MDR/PUD for a
planned 64 unit Senior Housing project. The zoning code, Section 154.453, Subdivision A,
allows:
Averaging of Lot Area. When lots are clustered within a development to provide common
open space,the open space may be used to calculate an average density per lot to
determine compliance with the individual lot area requirements.
To determine the allowed density for Outlot C,A 64-unit project on a 2.240 acres site (and 0.23
acres of corresponding open space) would have a density of 25.91 units per acre, exceeding the 7-
unit per acres allowed by the underlying MDR zoning, or 8.4-units per acre if 20% density bonus
PUBLIC HEARING ITEM 4b—ACTION ITEM
Planning Commission Meeting 7125116 Page 3
was applied through the PUD. The HDR zoning would provide a 15-units per acre base density, or
18-units per acre if 20% density bonus was applied through the PUD. Even with HDR/PUD
zoning,the 64-unit project would exceed the density allowable on the 2.47 acre site (.23 acres of
open space). Therefore, OP4 Boulder Ponds LLC is proposing to rezone Outlot B (1.44 acres)
from Commercial/PUD to HDR/PUD to add to the Senior Housing project area. With the addition
of Outlot B, the 64-unit senior housing project be 4.18 acres (3.68 acres outlot area+ .5 acres of
open space) in size with a density of 15-units per acre. HDR/PUD is the appropriate zoning
district for the proposed use on Outlots B and C combined.
Senior housing(congregate housing) is a conditional use in both the Commercial and HDR Zoning
Districts, so although the request is for a rezoning from Commercial/PUD to HDR/PUD, the
proposed underlying land use remains essentially the same.
In order to proceed with a senior housing project on the Oulots B and C the following would be
required:
• Final PUD Plans and Final Plat(combining the two outlots into a single lot)
• Conditional Use Permit
DRAFT FINDINGS:
In order to approve a rezoning,the Planning Commission shall consider findings are shall submit the
same with its recommendation to the City Council. Staff suggests the following findings:
1. The Rezoning/PUD Amendment is consistent with the Comprehensive Plan designation for
the subject property.
2. The proposed land use, Senior Housing, is a conditional use in both the Commercial and
HDR zoning districts, so the underlying land use will remain unchanged.
3. The proposed HDR/PUD zoning is appropriate for the proposed senior housing density.
4. The proposed PUD/Amendment is consistent with the Boulder Ponds PUD Concept Plan and
Preliminary PUD Plans.
RECOMMENDATION:
Staff recommends approval of the Rezoning/PUD Amendment for Outlots B and C, Boulder Ponds,
rezoning from Commercial/PUD and MDR/PUD,respectively,to HDR/PUD with the following
motion:
"Move to recommend approval of the Rezoning/PUD Amendment for Outlots B and C,Boulder
Ponds from Commercial/PUD and MDR/PUD, respectively, to HDR/PUD with the following
motion based on the findings in the Staff report."
ATTACHMENTS:
PUBLIC HEARING ITEM 4b—ACTION ITEM
Planning Commission Meeting 7125116 Page 4
• Application and Narrative
• Planning Commission Report—Boulder Ponds PUD—Concept Plan 12/09/16
• Housing Density Analysis (from 12/09/16 Concept Plan)
ORDER OF BUSINESS:
- Introduction........................................................................................Planning Staff
- Report by Staff...................................................................................Planning Staff
- Questions from the Commission............................Chair&Commission Members
- Open the Public Hearing..................................................................................Chair
- Close the Public Hearing..................................................................................Chair
- Discussion by the Commission..............................Chair&Commission Members
- Action by the Commission.....................................Chair&Commission Members
PUBLIC HEARING ITEM —ACTION ITEM
Date Received: THE CITY of 651-747-3900
Received By: LAKE ELMO 3800 Laverne Avenue North
Permit#.- Lake Elmo, MN 55042
LAND USE APPLICATION
❑ Comprehensive Plan ® Zoning District Amend ❑ Zoning Text Amend ❑ Variance'(see below) ❑ Zoning Appeal
❑ Conditional Use Permit(C.U.P.) ❑ Flood Plain C.U.P. ❑ Interim Use Permit(I.U.P.) ❑ Excavating/Grading
❑ Lot Line Adjustment ❑ Minor Subdivision ❑ Residential Subdivision Sketch/Concept Plan
❑ PUD Concept Plan ❑ PUD Preliminary Plan ❑ PUD Final Plan
Applicant: ON Boulder Ponds, LLC (Contact: Deb Ridgeway)
Address: 1660 Highway 100 S, Suite 400, St. Louis Park, MN 55416
Phone# 952.525.3223
Email Address: deb.rid geway(@_Excels iorLLC.corn
Fee owner: Same as Applicant
Address:
Phone#
Email Address:
Property Location(Address and Complete(long)Legal Description:
xxxx Jade Trail
Outlots B & C, Boulder Ponds
Detailed Reason for Request: Rezone Outlots B & C from Commercial PUD and MDR-PUD, respectively
to HDR - PUD. Please refer to project narrative for a detailed explanation.
*Variance Requests: As outlined in Section 301.060 C.of the Lake Elmo Municipal Code,the applicant must demonstrate
practical difficulties before a variance can be granted. The practical difficulties related to this application are as follows:
In signing this application, I hereby acknowledge that I have read and fully understand the applicable provisions of the Zoning
ordinance and current administrative procedures. I further acknowledge the fee explanation as outlined in the application
procedures and hereby agree to pay all statements received from the City pertaining to additional application expense.
OP4 B_ou Ponds, LLC
Signature of applicant:BY Date: 6/24/16
ON Borrf ,r Ponder i��
Signature of fee owner:B --qua= 6/24/16
tf(der
St
Zoning Amendment&Preliminary PUD Amendment
Project Representatives and Contact Information.
LANDOWNER/ OP4 Boulder Ponds, LLC
DEVELOPER c/o The Excelsior Group, LLC
1660 Highway 100 South, Suite 400
St. Louis Park, MN 55416
Ben Schmidt,Vice President
952.525.3225
Ben.Schmidt@ExcelsiroLLC.com
Deb Ridgeway,Asset Manager
952.525.3223
Deb.Ridgeway@ExelsiorLLC.com
Property Address,Zoning, Parcel Size, PID and Legal Description
Outlot B,Boulder Ponds Outlot C,Boulder Ponds
ADDRESS XXXX Hudson Blvd XXXX Hudson Blvd
CURRENT Commercial- PUD MDR-PUD
ZONING
PARCEL SIZE
Acres 1.72 2.46
S .Ft 2,591,320.2 6,098.4
PIDs 34-029-21-33-0023 34-029-21-33-0024
Boulder Ponds Preliminary PUD Amendment&Zoning Amendment Application
1
Boulder Ponds is a Planned Unit Development that was approved to include a
variety of land uses, including single family residential,multifamily residential and
commercial. The first phase of street and utility installation is complete to serve 20
Villa lots, 27 single family lots and 10 acres of commercial and multifamily.
During the preliminary plat process,the 2.42 multifamily site (Outlot C) was
presented as a 64-unit multifamily building. Based on the current zoning of medium
density residential (7 units per acre), Outlot C is allowed only 15.4 units,which is
inconsistent with the PUD approval. In addition to remedying this inconsistency,
there is a desire to rezone Outlot B to allow multifamily on the entire 4.18 acres.
Therefore, this application requests approval to amend the zoning of Outlots B &C,
Boulders Ponds from Commercial and MDR-PUD to HDR-PUD and allow for a
maximum 112 multifamily units. This is based on the analysis of the current
approved plan with 98 units versus the 210.4 units that could be allowed per the
zoning code. The accompanying plan further illustrates this. There is no proposed
layout at this time, but when a plan is created, Final Plat, Final PUD and Conditional
Use Permit approvals will be required providing adequate oversight of the specific
site plans.
In conclusion, Boulder Ponds offers a uniquely planned mixed-use neighborhood
where the land uses provide a seamless transition from commercial to low density
residential. The high density use between the commercial and lower density homes
creates a complementary buffer and generally a more desirable and overall more
viable neighborhood for Lake Elmo.
Boulder Ponds Preliminary PUDAmendment&7.oning Amendment Application
2
PROPOSED ZONING EXHIBIT FOR:
BOULDER PONDS
OWNER/DEVELOPER PARK
OP4 BOULDER PONDS,LLC
11455 VIKING DRIVE
SUITE 350
EDEN PRAIRIE,MN 55344
Low Density Residential
78 Units Approved
4 Units per Acre allowed
28.95 Acres
28.95 Ac x 4 DUA-115.8 Units allowed
57H 8lifff
-Lpw Density Residential SUMMARY OF ALLOWED UNITS
20 Units Approved
4 Units per Acre allowed 115.80
7.98 Acres
7.98 Ac x 4 DUA 31.9 Units allowed 31.90
+62.70
210.40 Total Allowed Units
- 98 Platted Units
112.4 Proposed Units on MF site(Outlots a&C)
Medium Density Residential
64 Units Approved(Outlol C)
PROPOSED YICINRYMAP
High Density Residential p JZT CF SEC 34 TWP 29 QKG z
15 Units per Acre allowed
4.18 Acres(Outlots 8&C) s
4.18 Ac x 15 DUA-62.7 '
UU MOT F
Commercial(Outlot B)
Multifamily Residential allowed
OUTIATA .- Y
WAS NGTCN COINTY.MNJPSOTA
01M-0T E NO SCAI.M
M�ecweolmr
(CIISI.q lrnwpy�M�.D)
{!IIS, INC. NORTH
',45e"Professlonal Land Surveyors NOT TO SCALE
,.....a 6776 Lake Drive NE,Suite 110
Lino Lakes,MN 55014
Tel.(651)361.8200 Fox(651)361-8701
a(der
YC S
Zoning Amendment&Preliminary PUD Amendment
Project Representatives and Contact Information.
LANDOWNER/ OP4 Boulder Ponds, LLC
DEVELOPER c/o The Excelsior Group, LLC
1660 Highway 100 South, Suite 400
St. Louis Park, MN 55416
Ben Schmidt,Vice President
952.525.3225
Ben.Schmidt@)ExcelsiroLLC.com
Deb Ridgeway,Asset Manager
952.525.3223
Deb.Ridgeway@)ExelsiorLLC.com
Property Address,Zoning, Parcel Size,PID and Legal Description
Outlot B,Boulder Ponds Outlot C,Boulder Ponds
ADDRESS XXXX Hudson Blvd XXXX Hudson Blvd
CURRENT Commercial-PUD MDR-PUD
ZONING
PARCEL SIZE
Acres 1.72 2.46
S .Ft 2,591,320.2 6,098.4
PIDs 34-029-21-33-0023 34-029-21-33-0024
Boulder Ponds Preliminary PUD Amendment&Zoning Amendment Application
1
Boulder Ponds is a Planned Unit Development that was approved to include a
variety of land uses, including single family residential, multifamily residential and
commercial. The first phase of street and utility installation is complete to serve 20
Villa lots, 27 single family lots and 10 acres of commercial and multifamily.
During the preliminary plat process,the 2.42 multifamily site (Outlot C) was
presented as a 64-unit multifamily building. Based on the current zoning of medium
density residential (7 units per acre), Outlot C is allowed only 15.4 units,which is
inconsistent with the PUD approval. In addition to remedying this inconsistency,
there is a desire to rezone Outlot B to allow multifamily on the entire 4.18 acres.
Therefore, this application requests approval to amend the zoning of Outlots B & C,
Boulders Ponds from Commercial and MDR-PUD to HDR-PUD and allow for a
maximum 112 multifamily units. This is based on the analysis of the current
approved plan with 98 units versus the 210.4 units that could be allowed per the
zoning code. The accompanying plan further illustrates this. There is no proposed
layout at this time, but when a plan is created, Final Plat, Final PUD and Conditional
Use Permit approvals will be required providing adequate oversight of the specific
site plans.
In conclusion, Boulder Ponds offers a uniquely planned mixed-use neighborhood
where the land uses provide a seamless transition from commercial to low density
residential. The high density use between the commercial and lower density homes
creates a complementary buffer and generally a more desirable and overall more
viable neighborhood for Lake Elmo.
Boulder Ponds Preliminary PUD Amendment&Zoning Amendment Application
2
TI IF CITY OI' PLANNING COMMISSION
LAKE ELMO DATE: 12/09/13
AGENDA ITEM: 4A—PUBLIC HEARING
CASE#2013-29
ITEM: Boulder Ponds Planned Unit Development (PUD)—Concept Plan
SUBMITTED BY: Nick Johnson,City Planner
REVIEWED BY: Kyle KIatt, Community Development Director
Jack Griffin, City Engineer
Mike Bouthilet, Public Works Superintendent
Greg Malmquist,Fire Chief
Rick Chase,Building Official
Matt Moore, South Washington Watershed District
SUMMARY AND ACTION REQUESTED:
The Planning Commission is being asked to hold a public hearing for a request from Amaris
Company LLC for a residential Planned Unit Development Concept Plan with 93 single family
residential homes and a 64-unit multifamily dwelling to be located on approximately 58 acres
immediately east of the Eagle Point Business Park and within the City's 1-94 Corridor Planning Area.
Staff is recommending approval of the PUD Concept Plan with 11 conditions of approval as listed in
the Staff Report.
GENERAL INFORMATION
Applicant: Amaris Company, LLC, P.O. Box 10811,White Bear Lake, MN 55110
Property Owners: Louis Damian Trust, c/o Security Bank&Trust Co., William C. Kuhlmann,
2202 11'll Street East,Glencoe, MN 55336
Tim Montgomery, 6211 Upper 5 1" Street North, Oakdale, MN 55128
Location: Part of Section 34 in Lake Elmo,north of I-94 and Hudson Boulevard, south of
Stonegate residential subdivision, and east of Eagle Point Business Park. PINs:
34.029.21.33.0001; 34.029.21.32.0001; 34.029.21.33.0002.
Request: Application for Concept Plan approval of a Planned Unit Development (PUD)
containing 93 single family homes and a 64-unit senior housing multi-family
residential building to be named Boulder Ponds of Lake Elmo.
Existing Land Use and Zoning: Agricultural land with one single family home (9120 Hudson
Blvd. N.). Current Zoning: RT—Rural Transitional Zoning
District;Proposed Zoning: LDR and MDR PUD
Surrounding Land Use and Zoning: North: Residential Estates subdivision(Stonegate)—RE zoning
and Park(Stonegate Park)—PF zoning;
West: Offices (Eagle Point Town Office Park)—BP zoning;
PUBLIC HEARING ITEM 4A—ACTION ITEM
2
South: Retail Trade(Lampert Lumber)—C zoning and Sales
and Storage Lots(Cranky Ape)—C zoning; and
East: future proposed Lennar urban low density residential
subdivision(Savona)—current zoning: RT, future zoning: LDR.
Comprehensive Plan: Urban Low Density Residential(2.5—4 units per acre),Urban
Medium Density Residential (4.5—7 units per acre), and
Commercial.
History: Applicants are participating in the Section 34 Utility Project under a Statute 429 area-
wide assessment. The utility project is expected to be completed in December of
2013.
Deadline for Action: Application Complete— 11/7/13
60 Day Deadline— 1/6/14
Extension Letter Mailed—No
120 Day Deadline—3/7/13
Applicable Regulations: Chapter 153—Subdivision Regulations
Article 10—Urban Residential Districts Q 154.450)
Article 16—Planned Unit Development(§154.800)
REQUEST DETAILS
The City of Lake Elmo has received an application from Amaris Company, LLC for a Planned Unit
Development (PUD)Concept Plan on approximately 58 acres of land located within the I-94
Corridor Planning Area. The Concept Plan includes 93 single family homes on the northern and
central portion of the site, as well as a proposed 64-unit senior housing multi-family residential
building. In addition,the Concept Plan includes vacant land along the Hudson Blvd that is planned
for future Commercial land uses per the City's Comprehensive Plan. It is the applicant's intention to
plat the Commercial areas as outlots until Commercial users are identified. The proposed PUD,to be
called Boulder Ponds of Lake Elmo,would be located on property currently owned by the Louis
Damiani Trust,currently managed by Security Bank&Trust Co., and Mr.Tim Montgomery.
The Concept Plan has been developed in response to the City's adopted Comprehensive Plan for the
I-94 Corridor,which guide the applicant's land as a mix of Urban Low Density Residential—LDR,
Urban Medium Density Residential—MDR and Commercial. The plan incorporates 93 single family
lots,most of which are designed with a width of approximately 65 feet. The majority(76)of the
single family lots are located north of the future minor collector road, 51h Street,whereas 17 single
family lots are located south of the minor collector. In addition,the 64-unit senior housing multi-
family building is also located south of the minor collector road adjacent to the areas that are guided
for future Commercial land uses.
As opposed to following the City's normal subdivision procedures, the applicants have determined
that a planned development approach offers the best method to achieve their development vision for
their property. The purpose of the City's PUD ordinance is to provide flexibility in development and
zoning standards for large parcels under unified control with the goal of achieving higher quality
development. More specifically,the General Concept Plan phase of the PUD procedure allows the
applicant to submit a general plan to the City demonstrating his or her basic intent of the
development,including general density ranges,location of residential and nonresidential land uses,
and location of streets,paths and open space. The purpose of approving the Concept Plan is to
PUBLIC HEARING ITEM 4A —ACTION ITEM
3
provide the applicant with conceptual approval related to the requested flexibilities or variations from
the City Zoning and Subdivision Ordinances, or other City standards,before incurring substantial
costs related to submitting a full Preliminary Plat application. In terms of procedure,the planned
development path is similar to the normal subdivision process in that Preliminary and Final PUD
Plan approvals must follow parallel track to Preliminary and Final Plat. However,one critical
difference between the planned development process and standard subdivision process is that the
PUD Concept Plan phase requires a public hearing and the approval of the City Council.
Alternatively,the Sketch Plan review phase, the first step in the standard subdivision process, does
not require a public hearing and City approval. The reason that the PUD Concept Plan requires a
public hearing and City approval is due to the requested flexibility and variation from the City's
standard zoning and subdivision procedures. Regarding variation from the City's Zoning Ordinance
and Comprehensive Plan,the applicants have requested minor flexibility in a couple of areas, hence
justifying the planned development approach. The requested variances or flexibilities will be further
discussed and analyzed in the Planning and Zoning section of the Staff Report.
The Boulder Ponds Concept Plan also includes a significant portion of the proposed 51h Street minor
collector road as planned in the City's Transportation Plan. Once completed,the minor collector
road will serve as the primary access for the Boulder Ponds planned development. The segment of
the minor collector road included in the Concept Plan is part of the I`phase of the 5`i' Street collector
road,from Inwood Avenue(CSAH 13)to Keats Avenue(CSAH I9).Eventually, the 5`h Street minor
collector road is planned to serve the entire I-94 Corridor from west to east(Inwood Ave. to Manning
Ave.). As shown in the Concept Plan, the design of the minor collector road as part of the Boulder
Ponds development is consistent with the City's specifications for this roadway segment. The
applicant has provided for a 120-foot wide right-of-way,which will provide sufficient room for the
construction of a parkway with turning lanes, 10-foot bituminous trail, sidewalk,trees, lighting, and
other design elements as planned by the City. It should also be noted that the applicants and other
interested landowners in the area have recently met with City staff to discuss the possibility of
petitioning the City for a 429 area-wide assessment project to complete the 5`h Street minor collector
road from Keats Ave. (CSAH 19) to the western boundary of the Boulder Pond project next year.
Finally,to achieve the desired vision of development for their project, as well as address difficult
grade issues on the site,the applicants are proposing to move the alignment of the minor collector
road to the south. The applicants are currently working with the adjacent property owners to the east,
US Homes Corp. (Lennar Homes)and DPS-Lake Elmo LLC(Dale Properties), to come to terms on
an agreed alignment of the 51h Street minor collector road. The proposed alignment of the minor
collector road will be further discussed in the Review and Analysis section of the Staff Report.
In terms of utilities,the applicants are currently participating in the Section 34 Utility Project, which
is extending sewer and water throughout Stage 1 of the 1-94 Corridor Planning Area. With the
improvements associated with the Section 34 project,the applicants will have access to both sewer
and water from the south(Hudson Blvd.)and west(Eagle Point Business Park). Currently, sewer and
water service are being provided by the City of Oakdale via a Joint Services Agreement. There is
currently enough capacity in the Oakdale system to provide sewer and water service to the Boulder
Ponds development. As the build-out of the Stage 1 Area of the 1-94 Corridor progresses,the City
will need to transition water services to the Lake Elmo municipal water system via the Inwood Ave
Trunk Watermain Extension Project, as well as transition sewer flows to the Met Council W.O.N.E
interceptor station along Hudson Blvd. The City will work with the applicants to plan for adequate
utility infrastructure with the submission of the PUD Preliminary Plan and Preliminary Plat.
Other major features of the proposed planned development include outlot areas that will provide for
open space,trails, and storm water management throughout the development area. The development
PUBLIC HEARING ITEM 4A—ACTION ITEM
4
also incorporates a buffer/greenway area along the northern boundary of the plat adjacent to an
existing RE—Residential Estates subdivision as required in the City's Comprehensive Plan. All
outlots that are planned for park land or storm water use will be deeded to the City, while the future
home owner's association will retain ownership of the remaining outlots.
Regarding next steps,the applicant is proposing to bring forward a Preliminary Plan and Preliminary
Plat application upon approval of the Concept Plan. Per the PUD Ordinance,the final approval of the
proposed planned unit development will result in a zoning change to a specific PUD zoning district,
with specific requirements and standards that are specific to the development. If the application
moves forward,the change in the base zoning(LDR,MDR, C) of the property would occur at the
time of Preliminary Plan approval, and the final PUD zoning with approved flexibility that is specific
to the development would be established at Final Plan approval.
PLANNING AND ZONING ISSUES
The Boulder Ponds site is guided for Urban Low Density Residential,Urban Medium Density
Residential and Commercial land uses in the City's Comprehensive Plan. The Density Analysis
sheet within the Boulder Ponds Concept Plan delineates the low density,medium density and
commercial areas respectively within the proposed planned development. The realignment of the 5`h
Street minor collector road to the south allows the applicant to maximize the single family residential
area to the north,creating a larger distinct single family neighborhood as opposed to having the
parcels bisected in half by the collector road.
Regarding the design of the planned development,the single family residential area to the north of
the minor collector street is defined by one curvilinear residential through street that allows for ease
of travel through the neighborhood. The remaining portions of the single family neighborhood are
served by three cut-de-sacs,none exceeding 500 feet in length. Also,the applicants are proposing to
include several landscaped medians and islands within the proposed City streets,the highlights of
which are three medians in the middle of the single family neighborhood. In relation to the lots and
blocks,the arrangement follow a curvilinear pattern,which allows the vast majority of the lots to
back up to common open space of some form. The northern portion of the single family area north of
the minor collector street also contains the 100' greenbelt buffer between the new growth areas and
the Stonegate residential estates subdivision as guided by the City's Comprehensive Plan. The
greenbelt buffer contains a trail that connects to the trail provided by the Lennar urban low density
subdivision to the east and connects with the trail within the 5"Street corridor to the west. This area
is also the location of a power line easement owned by XceI Energy. On the southern half of the
minor collector road, a local street connects the medium density residential commercial areas from
5th Street to Hudson Boulevard. South of the collector road,the plan include one small area of 17
single family lots, as well as a 64-unit multi-family building intended for senior housing. Regarding
the commercial areas(approximately 9 acres)to the south of the medium density residential area, it is
the applicant's intention to plat these areas as outlots until prospective users are identified.
For pedestrian circulation and recreation, sidewalks and trails are planned throughout the Boulder
Ponds planned development. Consistent with City Design Standards, the applicants have included
sidewalks to be installed on at least one side of all streets. Also,the greenbelt buffer trail included on
the northern portion of the site is consistent with the guidance of the Comprehensive Plan. In
addition to the internal trails and sidewalks that are proposed by the developer,the 5th Street Corridor
include a 10-foot bituminous trail on the north side of the road and a six-foot sidewalk on the south
PUBLIC HEARING ITEM 4A—ACTION ITEM
5
side. The internal trails and sidewalks provide good circulation to the 50' Street trail,which is
intended to provide a regional transportation and recreation purpose.
Regarding the single family lots within the Boulder Ponds Concept Plan,the vast majority of the lots
meet the minimum size requirements for the City's Urban Low Density Residential—LDR zoning
district. The minimum lot size per the City's LDR zoning district is 8,000 square feet, and the
minimum lot width at building setback line is 60'. Of the 93 single family lots, all but five lots(Lot
59, 69, 72, 73 and 75)meet or exceed the minimum lot size of 8,000 square feet as required under
LDR zoning. Overall,the average single family lot size in the planned development is approximately
10,495 square feet. In addition,the vast majority of the single family lots meet or exceed the
minimum 60' lot width.The applicants have noted that allowing for minor flexibility in lot area and
width is one of the key reasons for proceeding with a planned development. Also pertaining to the
single family residential lots, the applicants are requesting that the City consider reduced side yard
and front yard setbacks to accommodate the unique design of the single family residential portion of
the planned development. Reduced setbacks allow for greater clustering,which promotes high levels
of open space.According to §154.802.E-F,planned developments may allow for reduced setbacks
and reductions in area and width of individual lots. It is Staff's understanding that the applicants are
seeking to allow 5' side yard setbacks on both sides of the principal structure.In addition,the
applicants may be seeking reduced front yard setbacks. Any reductions in front yard setback must be
approved with the understanding that adequate separation is provided between parking areas
(driveways) and sidewalks,so that any potential obstacles, such as parked vehicles or trailers, do not
encroach on residential sidewalks. Overall, reductions in all residential lot sizes and setbacks must be
clearly identified, reviewed and approved at time of PUD Preliminary Plan phase.
Also related to single family lots,the applicants have included five residential lots that are partially
or almost entirely on a small triangular piece of property owned by Dale Properties. The applicants
are proposing to acquire this land from Dale Properties in order to facilitate the platting of these five
additional lots and realign the minor collector road to the south. Dale Properties has submitted a
letter(Attachment#5)indicating that general agreement has been reached on the land acquisition.
For the purposes of the Concept Plan,the applicants have"ghost platted"the five lots,Lots 14-18 on
the PUD Lot Areas sheet,with the intention of acquiring the land prior to Preliminary Plat
submission. If these lots are to be included in the PUD Preliminary Plan and Preliminary Plat,the
applicants must submit evidence demonstrating control or consent of this area being included in the
plat. If this is not possible,plans must be revised accordingly.
Regarding the proposed multi-family residential building,the applicant has noted that it is likely
intended for a senior living facility. Given that the application is currently at Concept Plan phase, it
is not required that significant detail be provided. However, it should be noted that within the Urban
Medium Density Residential—MDR zoning district,multi-family dwellings are considered a
conditional use. At the time of Final Plat and PUD Final Plan approval for the phase that includes
the 64-unit multi-family dwelling,the applicant will be required to apply for a Conditional Use
Permit(CUP). Further review of the multi-family dwelling should occur at the time of review for the
required CUP.
On the topic of housing density, the applicants have submitted a density analysis worksheet to
present the gross densities associated with the low density and medium density areas. Due to the fact
that the minor collector road has been moved to the south, the proposed Boulder Ponds planned
development would include more single family residential development than is currently planned for
in the Comprehensive Plan. However, it is important to note that per the Comp Plan,the 5`n Street
PUBLIC HEARING ITEM 4A —ACTION ITEM
6
minor collector road serves as the boundary between low density and medium density areas in the
Stage 1 Area(Inwood Ave. to Keats Ave.)of the I-94 Corridor. The gross density of the single
family area to the north of the collector road,which is approximately 28.5 acres, is calculated to be
2.66 units per acre. The medium density area,which is approximately 10.1 acres, contains 81
residential units(17 single family, 64 multi-family),resulting in a gross density of 7.98 units per
acre. It should be noted that this density figure is slightly higher than what is guided by the
Comprehensive Plan. However, given that the proposed development is a PUD, and that the amount
of land guided for medium density residential development on these parcels by the Comprehensive
Plan is much greater, Staff has determined that the proposed Concept Plan meets the spirit and intent
of the Comprehensive Plan. To explain Staffs reasoning for this determination in another way, the
proposed Concept Plan decreases the amount of total land guided for medium density development
by over 20 acres by moving the collector road south.The slight increase in density above the allowed
range per the Comp Plan is balanced by the significant reduction in the amount of land guided
medium density. To put it in simple terms,by using the low end of gross density ranges in the Comp
Plan,these parcels were guided to have 195 total residential units(not accounting for road right-of-
way), whereas the proposed PUD Concept Plan includes 157 total units. Overall,the proposed PUD
Concept Plan is consistent with the intent of the land use and density requirements as guided by the
City's Comprehensive Plan.
In terms of parkland dedication requirements,the Subdivision Ordinance requires that 10%of the
land in urban residential districts to be dedicated for park purposes. Alternatively, fees may be
submitted to the City in lieu of land dedication at a rate equal to the market value of the land. It is at
the discretion of the City Council how parkland/fees are accepted to meet this requirement. The
Boulder Ponds site is approximately 58 acres in size. Therefore,under the approach of a pure land
dedication,the applicants would be required to dedicate approximately 5.8 acres of land for parkland
purposes. In the application narrative, the applicants note that within the proposed Plan Concept
Plan, 11.8 acres are devoted as park space. However, it must be noted that to be accepted as parkland
for dedication purposes,the land must be able to serve an active recreation purpose. In addition, if
linear land dedications are accepted, a trail that provides effective connectivity in the community
must be provided and constructed. Also, it should be noted that the City cannot accept land that is
subject to private easement for public parkland dedication. This consideration relates to the location
of the Xcel Energy power line easement in the greenbelt buffer area in the northern portion of the
site. It is the recommendation of Staff that further discussions be had with the applicants regarding
which areas are eligible for parkland dedication. Greater clarity regarding parkland dedication
requirements and eligibility should be reached in advance of Preliminary Plat.
Regarding available or future park facilities,the applicants are proposing to continue the
greenbelt/buffer trail along the northern portion of the property. This trail provides connections to
the 51h Street regional trail and Stonegate Park from the east. Given it proximity,it makes logical
sense that Stonegate Park,in addition to other City parks,will serve the future residents of the
Boulder Ponds planned development. It is recommended by Staff that the City works with the
applicants and property owners to the west of Stonegate Park, Azure Properties, to investigate
possible expansions or improvements to Stonegate Park. In addition Staff will work with the Park
Commission to evaluate if any additional facilities or programs should be offered at Stonegate Park.
Evaluating the facilities and programing of Stonegate Park should inform future planning or
expansion efforts.
REVIEW AND ANALYSIS
PUBLIC HEARING ITEM 4A—ACTION ITEM
City Staff has reviewed the proposed Boulder Ponds PUD Concept PIan,which has gone through
multiple iterations in advance of the formal application being accepted as complete by the City.
During the course of these reviews, several of the issues and concerns that were previously raised by
Staff have been addressed by the applicant with updated submission documents. However, it is
important to note that there are other elements of the plan that still require additional attention in
advance of a PUD Preliminary Plan and Preliminary Plat submittal. In general,the proposed plan
will meet all applicable City requirements for PUD Concept Plan approval, and any deficiencies or
additional work that is needed is noted for the purpose of inclusion in the review record. In addition
there are several things happening in and around the Boulder Ponds planned development that will
have an impact on the project,including the possible petition for a 429 area-wide assessment project
to construct the 5`h Street minor collector road, as well as the final alignment of said road. Given that
some of these efforts are still underway, Staff recognizes that some minor modifications may be
necessary from PUD Concept Plan phase to PUD Preliminary Plan phase.
The City has received a detailed list of comments from the City Engineer, in addition to general
comments by the South Washington Watershed District, all of which are attached for consideration
by the Commission.
In addition to the general comments that have been provided in the preceding sections of this report,
Staff would like the Planning Commission to consider the issues and comments related to the
following discussion areas as well:
• Comprehensive Plan. The proposed subdivision is consistent with the Lake Elmo
Comprehensive Plan for this area and with the densities that were approved as part of this
plan. The gross densities for the development generally are consistent with the ranges
allowed for the urban low density and urban medium density land use categories. Other
aspects of the Comprehensive Plan relate to the Boulder Ponds PUD Concept Plan as
follows:
o Transportation. The City's transportation plan calls for the construction of a minor
collector road that will connect the eastern and western portions of the I-94 Corridor.
Staff views this road as a critical piece of the transportation infrastructure that is
needed to serve the densities that have been planned for this area. The applicant has
incorporated the right-of-way at the width necessary to construct the minor collector
as part of its PUD Concept Plan.
o Parks. The greenbelt trail provided on the northern portion of the site is consistent
with the City's Land Use Plan in the Comprehensive Plan. In addition,the City's
Park Plan in the Comprehensive Plan does not identify this area as a future location
of a neighborhood park due to its proximity to Stonegate Park.
o Water. Water will eventually be provided to this area via a future extension of the
municipal system along Inwood Avenue. The Boulder Ponds planned development
will be able to be served under the City's current agreement with the City of Oakdale
until the Inwood watermain extension is completed.
o Sanitary Sewer. The Boulder Ponds planned development will be required to
connect to the sewer main being constructed as part of the Section 34 area wide
assessment project. In this case, all of the property owners that are planned to be
served by sanitary sewer have petitioned the City to construct the required sewer and
water mains to serve the area.
PUBLIC HEARING ITEM 4A—ACTION ITEM
8
o Phasing. The Boulder Ponds planned development is located within the Stage 1
phasing area for the I-94 Corridor and therefore the proposed development is
consistent with the City's anticipated phasing of growth.
• Zoning. The proposed base zoning for the Boulder Ponds site will be split between the
Urban Low Density Residential—LDR,the Urban Medium Density Residential—MDR, and
Commercial—C zoning districts. However, approval of PUD Final Plan will result in a
zoning change to a specific PUD Zoning District,recording all of the permitted variations,
such as minimum lot size and setbacks, from the Zoning requirements of the base zoning
district.
• Subdivision Requirements. The City's Subdivision Ordinance includes a fairly lengthy list
of standards that must be met by all new subdivisions, and include requirements for blocks,
lots, easements,erosion and sediment control,drainage systems,monuments, sanitary sewer
and water facilities, streets, and other aspects of the plans. The City will work with the
applicant to ensure that all standards specified in the Subdivision Ordinance are met, or that
the appropriate variation is requested through the PUD Preliminary Plan.
• Concept Phasing. The applicants have also submitted a Concept Phasing Plan, indicating
how they intend to proceed with construction and build-out of the proposed planned
development. As proposed by the applicants,the Phasing Plan indicates that Phase I includes
construction of the access road to Hudson Blvd. and the southern portion of the northern
single family residential area. Phase II includes construction of the medium density
residential area. Finally, Phase III includes the construction of the remaining single family
area in the northern portion of the site, as well the 5`h Street minor collector road. Staff is
recommending that the Phasing Plan be revised so that all public infrastructure is constructed
adjacent to any areas being platted. More specifically,the minor collector road should be
constructed adjacent to any areas of residential homes that are being platted. It is critical that
the city ensures that all public improvements needed to serve development in the I-94
Corridor are installed as growth occurs.
• Infrastructure. The developer will be required to construct all streets, sewer,water, storm
water ponds, and other infrastructure necessary to serve the development. Storm water
facilities should be platted as outlots and deeded to the city for maintenance purposes.
Adequate access to storm water facilities must be provided.
• Tree Preservation and Protection. Based upon the existing tree cover of the site,it is
possible that the applicant may not be required to complete a Tree Preservation Plan. If the
applicant can demonstrate that significant trees on the site will not be negatively impacted by
development activity,they would be allowed to submit a Woodland Evaluation Report in lieu
of a Tree Preservation Plan.
• Green Belt/Buffer. The Comprehensive Plan identifies an area north of the Boulder Ponds
planned development and south of the Stonegate subdivision as a green belt/buffer space with
a minimum width of 100 feet. In the case of the subject property, this area is also the location
for a significant power line easement held by Xcel Energy. As proposed in the PUD Concept
Plan,the applicant is utilizing this space for the continuation of trail corridor from the east.
Design of the greenbelt trail is consistent with City planning efforts to date. Staff believes
that that green belt(buffer requirements of the Comprehensive Plan have been met by the
applicant.
PUBLIC HEARING ITEM 4A—ACTION ITEM
9
• Streets and Transportation. The proposed street system has been designed to comply with
all applicable subdivision requirements and City engineering standards,with the exception of
the requested variance as noted in the City Engineer's report. Staff does have some concerns
related to the landscape medians and island in term of acceptable turning radii, emergency
vehicle access, snow removal, general maintenance,and safe turning movements. More
specifically,the central intersection of the northern single family area contains three large
medians/island that present difficult turning movements and safety concerns related to
limited turning radii,potential limited visibility due to plantings, and,in multiple instances,
direct driveway access that intersects with this unique central intersection. The applicant will
be directed to provide significant geometric detail of these areas and work with staff to
ensure that all islands and medians allows for safe travel movements and efficient
maintenance. Finally, further clarification must be provided regarding proposed plantings in
these medians/islands, as well as the responsible party for the maintenance of these plantings.
• 5"Street Alignment and Design. Staff has the following comments regarding the proposed
alignment of the P Street minor collector road and design:
o The applicants have proposed to relocate the alignment of the 51h Street minor
collector road to the south in order to maximize the potential for a single family
neighborhood to the north, as well as mitigate difficult grade issues that exist on the
site. From meeting with the applicants on multiple occasions regarding the proposed
alignment of the minor collector road, staff has found the existing grade challenges to
be accurate, and the alignment proposed in the Concept Plan to work in the context of
meeting Municipal State Aid(MSA)road design requirements. To make the
proposed alignment feasible,the applicants are working with the property owners to
the east, Lennar and Dale Properties,to negotiate realigning the road to the south. All
indications that the City has received indicate that general agreement has been
reached, and the realignment will move forward. Evidence of these negotiations is
documented in Attachment#5, a letter from Mr. Alan Dale of Dale Properties.
o In addition to the eastern alignment,the applicants have also been working with
Bremer Bank regarding the alignment of the minor collector road in the northwestern
portion of the site. As proposed,the 5'Street right-of-way would encroach on the
Bremer Bank property, and the road would encroach ever so slightly on the very
northeast corner of the Bremer property. It is the City's understanding that
discussion regarding the alignment of the collector in the northwest corner are
moving forward in a positive direction. As a condition of seeking PUD Preliminary
Plan and Preliminary Plat approval, Staff is recommending that both alignment areas,
the northwestern and eastern alignments, are resolved or agreed upon by all interested
parties in advance of future application submittals.
o Regarding the proposed alignment of the collector road, as well as the alignment of
the local access road connecting Hudson Blvd.,the properties to the south and east
(Cranky Ape and Lampert Lumber)of the subject property do not currently have
access provided. It is Staffs recommendation that right-of-way be platted to these
adjacent parcels in a location that is acceptable to the City Engineer.
o Finally, as part of the PUD Preliminary Plan and Preliminary Plat application
submission, Staff is requesting that the plans for 51h Street include all design elements
as requested by the City, including the street trees,landscaping, lighting,median
plantings, and other elements as proposed by the Damon Farber design work.
PUBLIC HEARING ITEM 4A—ACTION ITEM
10
• Sidewalks and Trails As noted in the City Engineer's report,there are several instances
where sidewalks and trails are located within either private outlots or on individual
residential single family lots. The Subdivision Ordinance requires that all front property lines
include 10' drainage and utility easements. The placement of sidewalks within these
easements would impact the City's ability to use these easements for utility or maintenance
purposes. In addition,having the sidewalks located on private property hinders the City's
ability to maintain these public improvements. Also, it is important to maintain appropriate
clear zones for all sidewalks and trails. Staff is recommending that all sidewalks and trails be
located in City right-of-way.
• City Engineer Review. The City Engineer has provided the Planning Department with a
detailed comment letter dated November 20,2013 as a summary of his PUD Concept Plan
review. Staff has incorporated the more significant issues identified by the Engineer as part
of the recommended conditions of approval, and has also included a general condition that all
issues identified by the City Engineer must be addressed by the applicant prior to approval of
a the PUD Preliminary Plan and Preliminary Plat. The Engineer does note that the proposed
Concept Plan complies with the City's standards, with one exception related to base material
of City streets.
• Watershed Districts. The project area lies within the South Washington Watershed District.
Comments have been provided(Attachment#4)by the SWWD Engineer,Matt Moore.
• Environmental Review. Based upon the proposed scope of the Concept Plan, the City does
not believe that the planned development will individually trigger further environmental
review.
Based on the above Staff Report and analysis, Staff is recommending approval of the Boulder Ponds
PUD Concept Plan with multiple conditions intended to address future considerations related to the
submission of a PUD Preliminary Plan and Preliminary Plat application.The recommended
conditions are as follows:
Recommended Conditions of Approval.
I) The applicant must obtain permission and consent from the adjoining property owner,
Bremer Bank,related to the right-of-way and alignment of the 5'h Street minor collector road
in the northwest corner of the site. The final alignment must be determined prior to the
submittal of PUD Preliminary Plan and Preliminary Plat applications.
2) The applicant must resolve the alignment of the P Street minor collector road in the
southeast portion of the site with adjoining property owners, specifically Lennar and Dale
Properties. The final alignment must be determined prior to the submittal of PUD Preliminary
Plan and Preliminary Plat applications.
3) Access must be provided to the adjacent parcels owned by Star River Holdings LLC(Cranky
Ape) and Lampert Yards Inc(Lampert Lumber)via either the Sth Street minor collector road
or the access road to Hudson Boulevard. The access location must meet the approval of the
City Engineer.
4) The applicant must acquire additional Iand in the eastern portion of the site to plat single
family residential Lots 14-18 as part of the Preliminary Plat application, or revise their plan
accordingly.
PUBLIC HEARING ITEM 4A — ACTION ITEM
11
5) Request for flexibilities related to lot size, width, setbacks and all other requirements per the
City's Zoning Ordinance or Design Standards must be clarified and documented as part of
the PUD Preliminary Plan and Preliminary Plat submission.
6) The applicant must revise the Phasing Plan to accommodate the construction of all public
infrastructure adjacent to any proposed areas to be platted within said phase per the City
Engineer's report dated November 20, 2013.
7) All street and median geometrics must accommodate emergency vehicle access and
maintenance. Applicants must demonstrate acceptable turning radii for all uniquely shaped
landscape medians and cul-de-sacs.
8) All sidewalks must be located in dedicated public right-of-way. All trails must be located
within dedicated right-of-way, City parkland, or a 30-foot wide dedicated easement at a
minimum.
9) The developer shall follow all of the rules and regulations spelled out in the Wetland
Conservation Act, and shall acquire the needed permits from the appropriate watershed
district prior to the commencement of any grading or development activity on the site.
10) Any land under which public trails are located will be accepted as park land provided the
developer constructs said trails as part of the public improvements for the subdivision, and
the land is located outside of any restrictive easements.
11)The applicant shall observe all comments and recommendations from the City Engineer
documented on the Engineer's report dated November 20, 2013.
DRAFT FINDINGS
Staff is recommending that the Planning Commission consider the following findings with regards to
the proposed Boulder Ponds Concept Plan:
I) That the Boulder Ponds PUD Concept Plan is consistent with the Lake Elmo Comprehensive
Plan and the Future Land Use Map for this area.
2) That the Boulder Ponds PUD Concept Plan complies with the general intent of the City's
Urban Low Density Residential and Urban Medium Density Residential zoning districts.
3) That the Boulder Ponds PUD Concept Plan complies with the City's Subdivision Ordinance.
4) That the Boulder Ponds PUD complies with the City's PUD Ordinance.
5) That the Boulder Ponds PUD Concept Plan is consistent with the City's engineering
standards with one exception as noted by the City Engineer in his review comments to the
City dated November 20, 2013.
RECCOMENDATION:
Staff recommends that the Planning Commission recommend approval of the Boulder Ponds PUD
Concept Plan with the I 1 conditions of approval as listed in the Staff Report. Suggested motion:
"Move to recommend approval of the Boulder Ponds PUD Concept Plan with the findings of fact
and conditions of approval as drafted in the Staff Report."
PUBLIC HEARING ITEM 4A—ACTION ITEM
Density Analysis
t =80 feet
241.453.69 SO FT
.66 Ul.,r r A
Medium Densft,,L;
442,007-85 Sty FT
er Acre
z4 LAkd VrAc.YAm
Total Number of lots 93
Average Lot Size 10,489 sq ft
7 01 Units F
wi I
Minimum lot Site 7,200 sq(I
"RT entar
ugly A..01.1.