HomeMy WebLinkAbout5-2017 Streets Project SchedulePROJECT SCHEDULE  CITY OF LAKE ELMO    2017 STREET IMPROVEMENTS  PROJECT NO. 2016.135  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.   651.300.4261 Jack Griffin, P.E.                651.300.4264  Ryan Stempski, P.E.  651.300.4267  Chad Isakson, P.E.  651.300.4283  AUGUST 2016                  OCTOBER 4, 2016  Council authorizes Feasibility Report.      DECEMBER 6, 2016  Presentation  of  Feasibility  Report.  Council  accepts  Report  and  calls  Hearing.  Authorizes Design Survey.      JANUARY 17, 2017  Public  Improvement  Hearing.  Council  Orders  the Improvement and orders the  preparation of Plans and Specifications (Requires 4/5th vote).       APRIL 4, 2017    Council approves Plans and Specifications and orders Advertisement for Bids.      MAY 4, 2017    Receive Contractor Bids.      MAY 16, 2017   Council accepts Bids and awards Contract.      JUNE 12, 2017  Conduct Pre‐Construction Meeting and issue Notice to Proceed.   SEPTEMEBER 22, 2017  Substantial Completion.   OCTOBER 27, 2017   Final Completion.