OCTOBER 4, 2016 Council authorizes Feasibility Report.
DECEMBER 6, 2016 Presentation of Feasibility Report. Council accepts Report and calls Hearing.
Authorizes Design Survey.
JANUARY 17, 2017 Public Improvement Hearing. Council Orders the Improvement and orders the
preparation of Plans and Specifications (Requires 4/5th vote).
APRIL 4, 2017 Council approves Plans and Specifications and orders Advertisement for Bids.
MAY 4, 2017 Receive Contractor Bids.
MAY 16, 2017 Council accepts Bids and awards Contract.
JUNE 12, 2017 Conduct Pre‐Construction Meeting and issue Notice to Proceed.
SEPTEMEBER 22, 2017 Substantial Completion.
OCTOBER 27, 2017 Final Completion.