Loading...
HomeMy WebLinkAboutInwood Tower No. 4 - Pay Request No 7 PROJECT PAY FORM PARTIAL PAY ESTIMATE NO. 7 FOCUS ENGINEERING, inc. INWOOD WATER TOWER NO.4 PERIOD OF ESTIMATE PROJECT NO.2015.130 FROM 11/1/2016 TO 11/30/2016 PROJECT OWNER: CONTRACTOR: CITY OF LAKE ELMO CB&I Inc. 3800 LAVERNE AVENUE NORTH 14109 S. ROUTE 59 LAKE ELMO, MN 55042 PLAINFIELD, IL 60544 ATTN:JACK GRIFFIN,CITY ENGINEER ATTN: MICHAEL ALLISON CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY No. Approval Amount 1. Original Contract Amount $2,395,000.00 Date Additions Deductions 2. Net Change Order Sum $8,744.00 1 5/3/2016 $0.00 $0.00 3. Revised Contract (1+2) $2,403,744.00 2 9/20/2016 $8,744.00 $0.00 4. *Work Completed $1,420,273.50 5. *Stored Materials $0.00 6. Subtotal (4+5) $1,420,273.50 7. Retainage* 5.0% $71,013.68 8. Previous Payments $1,153,198.83 TOTALS $8,744'00 $0.00 9.Amount Due (6-7-8) $196,061.00 NET CHANGE $8,744.00 *Detailed Breakdown Attached CONTRACT TIME START DATE: 4/7/2016 ORIGINAL DAYS 574 ON SCHEDULE SUBSTANTIAL COMPLETION: 9/28/2017 REVISED DAYS 0 YES FX FINAL COMPLETION: 11/2/2017 REMAINING 337 NO ENGINEER'S CERTIFICATION: SEH The undersigned certifies that the work has been reviewed and to the best of their knowledge and belief,the quantities shown in this estimate are correct and the work has been performed in accordance ENGINEER with the contract documents. 12/9/2016 DATE CONTRACTOR'S CERTIFICATION: CONTRACTOR The undersigned Contractor certifies that to the best of their knowledge,information and belief the work covered by this payment estimate has been completed in accordance with the contract BY 12/12/16 documents,that all amounts have been paid by the contractor for work for which previous payment estimates was issued and payments DATE received from the owner,and that current payment shown herein is now due. APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA BY BY DATE DATE FOCUS Engineering,inc. PROJECT PAYMENT FORM PARTIAL PAY ESTIMATE NO. 7 r C INWOOD WATER TOWER NO.4 FOCUS ENGINEERING, Inc. CITY OF LAKE ELMO,MINNESOTA PROJECT NO.2015.130 CONTRACT THIS PERIOD TOTAL TO DATE ITEM DESCRIPTION OF PAY ITEM UNIT QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT DIVISION 1-SITE&UTILITY WORK 1 MOBILIZATION LS 1 $16,000.00 $16,000.00 $0.00 1.00 $16,000.00 2 ROCK CONSTRUCTION ENTRANCE EA 1 $3,822.00 $3,822.00 $0.00 1.00 $3,822.00 3 TRAFFIC CONTROL LS 1 $2,068.00 $2,068.00 $0.00 0.50 $1,034.00 4 SUBGRADE EXCAVATION CY 120 $10.00 $1,200.00 $0.00 60.00 $600.00 5 GEOTEXTILE FABRICTYPE V SY 200 $6.00 $1,200.00 $0.00 0.00 $0.00 6 ORGANICTOPSOIL BORROW CY 100 $30.00 $3,000.00 $0.00 0.00 $0.00 7 SELECT GRANULAR BORROW CY 150 $16.00 $2,400.00 $0.00 0.00 $0.00 8 AGGREGATE BASE,CLASS 6 TON 1,250 $22.00 $27,500.00 $0.00 0.00 $0.00 9 BIT WEARING COURSE MIX(WEA240B) TON 65 $99.00 $6,435.00 $0.00 0.00 $0.00 10 BIT NON-WEARING COURSE MIX(WEB240B) TON 65 $99.00 $6,435.00 $0.00 0.00 $0.00 11 TACK COAT GAL 35 $10.00 $350.00 $0.00 0.00 $0.00 12 8"CONCRETE APRON SF 350 $25.00 $8,750.00 $0.00 0.00 $0.00 13 4"CONCRETE WALK SF 100 $20.00 $2,000.00 $0.00 0.00 $0.00 14 CONNECT TO EXISTING WATERMAIN EA 1 $2,300.00 $2,300.00 $0.00 0.00 $0.00 15 6"DIP WATER MAIN PIPE,CL.52 LF 10 $110.00 $1,100.00 $0.00 0.00 $0.00 16 16"DIP WATER MAIN PIPE,CL.52 LF 120 $140.00 $16,800.00 $0.00 0.00 $0.00 17 6"GATE VALVE&BOX EA 1 $1,980.00 $1,980.00 $0.00 0.00 $0.00 18 HYDRANT EA 1 $4,864.00 $4,864.00 $0.00 0.00 $0.00 19 DIP FITTINGS LB 700 $2.50 $1,750.00 $0.00 0.00 $0.00 20 POLYETHYLENE ENCASEMENT LF 140 $2.00 $280.00 $0.00 0.00 $0.00 21 4'X 4'CATCH BASIN WITH GRATING EA 1 $2,618.00 $2,618.00 $0.00 0.00 $0.00 22 1.5"CLEAR TOCK CY 16 $76.00 $1,216.00 $0.00 0.00 $0.00 23 GEOTEXTILE FABRIC TYPE I SY 30 $6.00 $180.00 $0.00 0.00 $0.00 24 18"RCP STORM SEWER PIPE,CL.V LF 90 $68.00 $6,120.00 $0.00 0.00 $0.00 25 18"APRON W/TRASH GUARD EA 1 $1,700.00 $1,700.00 $0.00 0.00 $0.00 26 HAND PLACED RIP RAP,CL.III CY 10 $92.00 $920.00 $0.00 0.00 $0.00 27 GEOTEXTILE FABRIC TYPE IV SY 37 $3.00 $111.00 $0.00 0.00 $0.00 28 PREASSEMBLED SILT FENCE LF 500 $2.25 $1,125.00 $0.00 250.00 $562.50 29 STRAW BIOROLL LF 1,000 $2.00 $2,000.00 $0.00 0.00 $0.00 30 TEMPORARY SEEDING(MIX 22-111 WITH TYPE I MULCH) AC 1.5 $4,000.00 $6,000.00 $0.00 0.00 $0.00 31 SEEDING(MIX 25-131 WITH FERTILIZER&HYDROMULCH) AC 1.5 $3,500.00 $5,250.00 $0.00 0.00 $0.00 SUBTOTAL-DIVISION 1 $137,474.00 $0.00 $22,018.50 DIVISION 2-ELEVATED STORAGE TANK 1 INSURANCE AND BONDS LS 1 $47,900.00 $47,900.00 $0.00 1.00 $47,900.00 2 ENGINEERING&APPROVAL LS 1 $239,500.00 $239,500.00 $0.00 0.98 $234,710.00 3 TANK MATERIALS LS 1 $316,100.00 $316,100.00 $0.00 1.00 $316,100.00 4 TANK FABRICATION&SHIP LS 1 $287,700.00 $287,700.00 0.20 $57,540.00 0.25 $71,925.00 5 FOUNDATION CONSTRUCTION LS 1 $413,400.00 $413,400.00 $0.00 0.95 $392,730.00 6 CONCRETE SHAFT CONSTRUCTION LS 1 $372,100.00 $372,100.00 0.40 $148,840.00 0.90 $334,890.00 7 TANK ERECTION(ON GROUND) LS 1 $214,600.00 $214,600.00 $0.00 0.00 $0.00 8 TANK PAINT(ON GROUND) LS 1 $142,300.00 $142,300.00 $0.00 0.00 $0.00 9 HOISTTANK LS 1 $43,450.00 $43,450.00 $0.00 0.00 $0.00 10 TANK PAINT(IN AIR) LS 1 $74,200.00 $74,200.00 $0.00 0.00 $0.00 11 STERILIZE AND TEST LS 1 $976.00 $976.00 $0.00 0.00 $0.00 12 ELECTRICAL LS 1 $89,800.00 $89,800.00 $0.00 0.00 $0.00 13 WATER TOWER CONTROL PANEL AND RTU LS 1 $15,500.00 $15,500.00 $0.00 0.00 $0.00 SUBTOTAL-DIVISION 2 $2,257,526.00 $206,380.00 $1,398,255.00 TOTALS-BASE CONTRACT $2,395,000.00 $206,380.00 $1,420,273.50 TOTAL CHANGE ORDER NO.1 0 1 $0.00 $0.00 $0.00 0.00 $0.00 TOTAL CHANGE ORDER NO.2 0 1 $8,744.00 $8,744.00 $0.00 0.00 $0.00 TOTALS-REVISED CONTRACT $2,403,744.00 $206,380.00 $1,420,273.50