HomeMy WebLinkAbout#16 - I-94 Lift Station and Sanitary Sewer Improvements STAFF REPORT DATE: October 17, 2017 CONSENT Item #: 16 AGENDA ITEM: I-94 Lift Station (No. 1) and Sanitary Sewer Improvements - Change Order No. 2 SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Rob Weldon, Public Works Director Chad Isakson, Project Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 2 for the I-94 Lift Station (No. 1) and Sanitary Sewer Improvements? BACKGROUND: RL Larson Excavating, Inc. was awarded a construction contract to complete the I-94 Lift Station (No. 1) and Sanitary Sewer Improvements on May 2, 2017. Construction is in progress. PROPOSAL DETAILS/ANALYSIS: RL Larson Excavating, Inc. has submitted a change order to revise the substantial completion date from October 6, 2017 to November 17, 2017 and revise the final completion date from November 3, 2017 to December 15, 2017. The extended contract completion period is needed to allow for the delay in ordering and delivery of the revised lift station pumps previously approved by the City as Change Order No. 1. Change Order No. 1 was approved by the City at the June 20, 2017 meeting, 7-weeks after the contract was awarded, to revise the lift station pump design to meet new Met Council discharge requirements. The change in pump design resulted in delays in ordering the pumps. FISCAL IMPACT: None. This change order does not change the contract amount. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 2 for the I-94 Lift Station (No. 1) and Sanitary Sewer Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 2 for the I-94 Lift Station (No. 1) and Sanitary Sewer Improvements, thereby revising the substantial completion date from October 6, 2017 to November 17, 2017 and revising the final completion date from November 3, 2017 to December 15, 2017”. ATTACHMENTS: 1. Change Order No. 2. CONTRACT CHANGE ORDER FORM CHANGE ORDER NO. DATE: TO: UNIT Amount of Original Contract $ Sum of Additions/Deductions approved to date (CO No.   1) $ Contract Amount to date $ Amount of this Change Order   (ADD)   (DEDUCT)   (NO CHANGE)$ Revised Contract Amount $ The Contract Period for Completion will be   (UNCHANGED)  (INCREASED)  (DECREASED)days APPROVED BY ENGINEER:  FOCUS ENGINEERING APPROVED BY CONTRACTOR DATE DATE APPROVED BY OWNER:  CITY OF LAKE ELMO, MINNESOTA DATE DATE $0.00 CITY OF LAKE ELMO, MINNESOTA BYBY CHANGE ORDER DESCRIPTION / JUSTIFICATION: This Change Order revises the substantial completion date from October 6, 2017 to November 17, 2017 and revises the final  completion date from November 3, 2017 to December 15, 2017. Change Order No. 1 for revising the 3 lift station pumps was approved at the June 20, 2017 City Council Meeting (7‐weeks  after award of the contract). The Contractor ordered the pumps after receiving approved shop drawings from the Engineer.  Based on the availability of the pumps, the Contractor was unable to start and complete the project within the specified  completion date.  Attachments  (list documents supporting change):None DESCRIPTION OF PAY ITEM QTY UNITE PRICE NET CONTRACT CHANGE ITEM RL Larson Excavating, Inc., 2255 12th Street SE, St. Cloud, MN 56304 I‐94 LIFT STATION (NO. 1) AND SANITARY SEWER IMPROVEMENTS PROJECT NO. 2016.134 2 October 10, 2017 42 This Document will become a supplement to the Contract and all provisions will apply hereto. The Contract Documents are  modified as follows upon execution of this Change Order.  BYENGINEER 809,129.70 17,853.72 826,983.42 0.00 826,983.42 INCREASE/(DECREASE) 10/10/2017 FOCUS Engineering, inc.CHANGE ORDER FORM