HomeMy WebLinkAbout#05 Eagle Point Blvd - CCO#4 STAFF REPORT DATE: February 7, 2017 REGULAR ITEM #: 5 AGENDA ITEM: Eagle Point Boulevard Street and Utility Improvements – Compensating Change Order No. 4 SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Cathy Bendel, Finance Director Ryan Stempski, Project Engineer BACKGROUND: Miller Excavating, Inc. was awarded a construction contract on July 7, 2015 to complete the Eagle Point Boulevard Street and Utility Improvements. The contractor has completed the work in accordance with the contract, plans and specifications; and with approval of this change order the contract amount will be adjusted to reflect quantities actually installed as a part of the project. ISSUE BEFORE COUNCIL: Should the City Council approve Compensating Change Order No. 4 for the Eagle Point Boulevard Street and Utility Improvements? PROPOSAL DETAILS/ANALYSIS: Compensating Change Order No. 4 would reconcile the estimated and actual quantities installed on the project. FISCAL IMPACT: $62,184.72 decrease to the final construction contract amount. The final construction contract amount is $1,158,809.37 or 7.25% under the original construction contract award amount of $1,249,949.09. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Compensating Change Order No. 4 for the Eagle Point Boulevard Street and Utility Improvements project thereby decreasing the final contract amount by $62,184.72. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Compensating Change Order No. 4 for the Eagle Point Boulevard Street and Utility Improvements, thereby the final contract amount by $62,184.72”. ATTACHMENTS: 1. Compensating Change Order No. 4. 1/24/2017