Loading...
HomeMy WebLinkAbout#06 Eagle Pt Blvd Street Imp - Pay Request No 7 (Final) STAFF REPORT DATE: February 7, 2017 REGULAR ITEM #: 6 AGENDA ITEM: Eagle Point Boulevard Street and Utility Improvements – Pay Request No. 7 (Final) SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Cathy Bendel, Finance Director Ryan Stempski, Project Engineer BACKGROUND: Miller Excavating, Inc. was awarded a construction contract on July 7, 2015 to complete the Eagle Point Boulevard Street and Utility Improvements. The contractor has completed the work in accordance with the contract, plans and specifications. ISSUE BEFORE COUNCIL: Should the City Council accept the improvements and approve Pay Request No. 7 (Final)? PROPOSAL DETAILS/ANALYSIS: The Eagle Point Boulevard Street and Utility Improvements have been reviewed by the Engineer and have been found to be fully completed in accordance with the Contract, Plans and Specifications and Change Orders. The Project Engineer has prepared a Certificate of Completion indicating that all work is completed including all punchlist items and is recommending the acceptance of the improvements and release of final retainage. Project acceptance will initiate the one-year warranty period for the improvements. The one-year warranty will begin on February 7, 2017 and will extend through February 7, 2018. FISCAL IMPACT: Final payment is proposed in accordance with the Contract for the project. The Project was completed within the authorized scope and budget. The final total construction costs for the project is $1,158,809.37 which is 7.25% under the original contract amount of $1,249,494.09. A breakdown of the project costs compared with the previously approved budget is shown below. Eagle Point Boulevard Street and Utility Improvements – Final Project Cost Summary Final Project Costs Authorized Project Costs Total Project Costs: $1,343,809.37 $1,485,800 Breakdown: Construction: $1,158,809.37 $1,249,494.09 Contingency: $0 $34,005.91 Engineering (Report, Design, Construction, Right of Way Services) $140,000 $155,300 Geotechnical Engineering: $14,000 $16,000 Budget for Legal, Fiscal, and Administration: $31,000 $31,000 RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, accepting the Eagle Point Boulevard Street and Utility Improvements and approving Pay Request No. 7 (Final) in the amount of $57,940.47. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to accept the improvements and approve Pay Request No. 7 (final) to Miller Excavating, Inc. in the amount of $57,940.47 for the Eagle Point Boulevard Street and Utility Improvements”. ATTACHMENTS: 1. Partial Pay Estimate No. 7 (Final). 2. Certificate of Completion. 1/24/2017 CITY OF LAKE ELMO, MN EAGLE POINT BOULEVARD STREET AND UTILITY IMPROVEMENTS PROJECT NO. 2015.120 CERTIFICATE OF COMPLETION DATE OF ISSUANCE: February 7, 2017 OWNER: CITY OF LAKE ELMO, MN CONTRACTOR: MILLER EXCAVATING, INC. PROJECT NAME: EAGLE POINT BLVD. STREET AND UTILITY IMPROVEMENTS PROJECT NO.: 2015.120 This Certification of Completion applies to all work under the Contract Documents This Certification of Completion applies to the following specified parts of the Contract Documents I do hereby certify that the work to which this Certificate applies has been constructed in accordance with the Contract dated July 31, 2015. The above-mentioned improvement is hereby declared to be complete and acceptance of this work is recommended. DATE OF COMPLETION: February 7, 2017 Ryan Stempski Reg. No. 45395 FOCUS Engineering, inc. THE WARRANTY PERIOD BEGINS February 7, 2017 AND ENDS February 7, 2018