HomeMy WebLinkAbout#06 Old Village Phase 3-Approve PS AGENDA ITEM STAFF REPORT
DATE: April 4, 2017
CONSENT
ITEM #: 6
AGENDA ITEM: Old Village Phase 3 Street, Drainage, and Utility Improvements – Resolution
Approving Plans and Specifications and Ordering Advertisement for Bids
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Rob Weldon, Public Works Director
Chad Isakson, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve the plans and specifications and order
advertisement for bids for the Old Village Phase 3 Street, Drainage, and Utility Improvements?
BACKGROUND: On December 20, 2016, following a Public Improvement Hearing, the City council
ordered the improvements and preparation of the plans and specifications for the Old Village Phase 3 Street,
Drainage, and Utility Improvements. The improvements include the extension of sanitary sewer to the Lake
Elmo Elementary School, City Hall and the Brookman II Building (3825 Lake Elmo Avenue) as well as
extending sanitary sewer along Laverne Avenue, from 39th Street North to CSAH 14; 31st Street North,
from CSAH 17 to the east end; Laverne Court North, from 31st Street North to south cul-de-sac; and Layton
Court North, from 31st Street North to south cul-de-sac.
The improvements include the reconstruction of the existing streets with concrete curb and gutter,
installation and repair of storm sewer, the replacement of the aged watermain, and a sanitary sewer service
stub extended to the property line for each benefitting property. The improvements also include the
construction of a sidewalk and trail along Laverne Avenue from 39th Street North to CSAH 14 as part of
the Downtown Master Plan. The watermain along Laverne Avenue will be upsized to a trunk 16-inch
diameter main as the final connection for the intermediate/low pressure zone relocation to the Union Pacific
Railroad and watermain is proposed to be extended to the Brookman II building at the property owner’s
request.
The scope of improvements is consistent with the approved feasibility report which was adopted by the
City Council on November 15, 2016. The feasibility report was prepared in response to the receipt of
petitions for sanitary sewer service from the Lake Elmo Elementary School (Independent School District
#834) at 11030 Stillwater Boulevard, and from the property owners along 31st Street North, from CSAH
17 to the east end, Laverne Court North, from 31st Street North to south cul-de-sac, and Layton Court
North, from 31st Street North to south cul-de-sac.
PROPOSAL DETAILS/ANALYSIS: The plans and specifications have been completed for the
improvements and are ready to be advertised for contractor bids. A bid date has been scheduled for May 4,
2017. Once received, bids will be reviewed by staff and if acceptable will be presented to council on May
16th to award a contract.
FISCAL IMPACT: The estimated total cost for the Old Village Phase 3 improvements is $2,498,000 with
the street, sidewalk and storm sewer improvements estimated at $1,191,300; the sanitary sewer
improvements estimated at $753,800; and the watermain improvements estimated at $552,900. The
improvements are proposed to be assessed against the benefitting properties consistent with the City’s
Special Assessment Policy and the Old Village Sewer Assessment Policy.
Approval of this motion does not commit the council to the project costs. Once contractor bids are received,
the actual construction costs will be known and the council will be asked to consider entering into a contract
to complete the work.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the consent
agenda, Resolution 2017-033 approving the plans and specifications and ordering the advertisement for
bids for the Old Village Phase 3 Street, Drainage, and Utility Improvements. If removed from the consent
agenda, the recommended motion for the action is as follows:
“Move to approve Resolution No. 2017–033, approving the plans and specifications and ordering the
advertisement for bids for the Old Village Phase 3 Street, Drainage, and Utility Improvements.”
ATTACHMENTS:
1. Resolution No. 2017-033 Approving the plans and specifications and ordering the advertisement
for bids for the Old Village Phase 3 Street, Drainage, and Utility Improvements.
2. Location Map.
3. Project Schedule.
4. Project Plans and Specifications available for review at City Hall.
1
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2017-033
A RESOLUTION APPROVING PLANS AND SPECIFICATIONS AND
ORDERING ADVERTISEMENT FOR BIDS FOR THE OLD VILLAGE
PHASE 3 STREET, DRAINAGE, AND UTILITY IMPROVEMENTS
WHEREAS, pursuant to a resolution passed by the City Council on the 20th day of December
2016, the City Engineer, together with SEH, Inc. has prepared plans and specifications for the Old Village
Phase 3 Street, Drainage and Utility Improvements and has presented such plans and specifications to the
Council for approval.
NOW, THEREFORE, BE IT RESOLVED,
1. Such plans and specifications, a copy of which is on file at Lake Elmo City Hall, and made a part
hereof, are hereby approved.
2. The City Clerk shall prepare and cause to be inserted in the official paper and posted online with
Quest Construction Data Network (QuestCDN.com) an advertisement for bids upon the making of
such improvements under such approved plans and specifications. The advertisement shall be
published for at least 21 days, shall specify the work to be done, and shall state that sealed bids
provided to the City Clerk prior to the specified bid date and time and accompanied by a bid bond
or cashier’s check made payable to the City of Lake Elmo in an amount not less than 5% of the
amount of such bid will be considered.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE FOURTH DAY OF APRIL, 2017.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
(Seal) Mayor
ATTEST:
________________________________
Julie Johnson
City Clerk
PROJECT SCHEDULE
CITY OF LAKE ELMO
OLD VILLAGE PHASE 3: STREET, DRAINAGE
AND UTILITY IMPROVEMENTS
PROJECT NO. 2016‐133
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
MARCH 2017
SEPTEMBER 20, 2016 Council authorizes the preparation of the Phase 3 Feasibility Report.
NOVEMBER 15, 2016 Presentation of Feasibility Report. Council accepts Report and calls Hearing.
DECEMBER 20, 2016 Public Improvement Hearing. Council Orders the Improvement and orders the
preparation of Plans and Specifications (Requires 4/5th vote).
APRIL 4, 2017 Council approves Plans and Specifications and orders Advertisement for Bids.
MAY 4, 2017 Receive Contractor Bids.
MAY 16, 2017 Council accepts Bids and awards Contract.
JUNE 5, 2017 Conduct Pre‐Construction Meeting and issue Notice to Proceed.
OCTOBER 27, 2016 Substantial Completion.
June 30, 2018 Final Completion.