HomeMy WebLinkAbout#09 2017 Seal Coat Accept Bids & Award Contract STAFF REPORT
DATE: May 16, 2017
CONSENT
ITEM #: 9
AGENDA ITEM: 2017 Seal Coat Project – Accept Bids and Award Contract
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Rob Weldon, Public Works Director
Ryan Stempski, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept bids and award a contract for the 2017
Seal Coat Project?
PROPOSAL DETAILS/ANALYSIS: Bids were received, publicly opened, and read aloud at City Hall
on Thursday, May 4, 2017. FOCUS Engineering, Inc. has prepared and attached the Tabulation of Bids
and a Letter of Recommendation for the award of the contract. The City received three (3) bids for this
project, with Allied Blacktop Company providing both the lowest base bid and lowest alternate bid. Staff
is recommending that Allied Blacktop Company be awarded the contract for the Alternate Bid in the
amount of $173,305.00 which includes the amount of $122,265.00 for the City of Lake Elmo and the
amount of $51,040 for West Lakeland Township. The Alternate Bid includes higher performing asphalt
(CRS-2P) to provide a better product and to reduce resident complaints.
Once again, the project will be completed jointly with West Lakeland Township with the Township
reimbursing Lake Elmo their portion of the construction cost in the bid award amount of $51,040.00
(29%). West Lakeland Township will also pay Lake Elmo $3,000 for engineering and administration fees
once the Lake Elmo City Council accepts the bids and awards the construction contract. Construction
observation services will be contracted directly by each jurisdiction for the work performed on their
streets.
FISCAL IMPACT: $122,265.00.
The post-bid construction estimate for Lake Elmo is $122,265.00 (71%). The total engineering design,
bidding and construction services is estimated to be $8,500 less $3,000 to be reimbursed by West
Lakeland Township. The Lake Elmo total post-bid project cost is therefore estimated to be $127,765.00
to be paid through the General Fund (Fund No. 101-430-3120-42250).
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the consent
agenda, Resolution No. 2017-055 accepting the bids and awarding a Contract to Allied Blacktop
Company. If removed from consent agenda, the recommended motion for this action is as follows:
“Move to approve Resolution No. 2017-055Accepting the Bids and Awarding a Contract to Allied
Blacktop Company in the Alternate Bid amount of $173,305.00 for the 2017 Seal Coat Project; which
includes $122,265.00 for the City of Lake Elmo and $51,040.00 for West Lakeland Township.”
ATTACHMENTS:
1. Resolution No. 2017-055 Accepting Bids and Awarding Contract.
2. Engineer’s Letter of Award Recommendation and Tabulation of Bids.
3. Project Schedule.
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2017-055
A RESOLUTION ACCEPTING THE BIDS AND AWARDING A
CONTRACT FOR THE 2017 SEAL COAT PROJECT
WHEREAS, pursuant to an advertisement for bids for the 2017 Seal Coat Project, bids were
received, opened, and tabulated according to law, and bids were received complying with the
advertisement; and
WHEREAS, bids were tabulated, checked and summarized to verify that all requirements of the
submittals were met; and
WHEREAS, the project engineer reviewed the bids and has provided a letter recommending the
award of the contract to the lowest responsible bidder, Allied Blacktop Company, for the Alternate
Bid in the amount of $173,305.00.
NOW, THEREFORE, IT IS HEREBY RESOLVED,
1. That the Mayor and City Clerk are hereby authorized and directed to enter into a Contract
in the accordance with the above ordered Project, in the amount of the Contractor’s
lowest responsible bid, and according to the plans and specifications thereof approved by
the City Council.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids, except that the deposits of the successful bidder and the
next two lowest bidders shall be retained until a contract has been signed.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE SIXTEENTH DAY OF
MAY 2017.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
Mayor
(Seal)
ATTEST:
________________________________
Julie Johnson
City Clerk
May 5, 2016
Jack Griffin, P.E.
City Engineer
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, Minnesota 55042
2017 Seal Coat Project
City of Lake Elmo, Minnesota
Project No. 2017.118
Dear Mr. Griffin,
Attached is a complete tabulation of Bids for the 2017 Seal Coat Project. Bids were received at City Hall at
3:00 PM on Thursday, May 4, 2017.
Contractor Base Bid Alternate Bid
Allied Blacktop Company
City of Lake Elmo $119,047.50 $122,265.00
West Lakeland Township $49,720.00 $51,040.00
TOTAL: $168,767.50 $173,305.00
Astech Corporation
City of Lake Elmo $120,120.00 $126,555.00
West Lakeland Township $49,280.00 $51,920.00
TOTAL: $169,400.00 $178,475.00
Pearson Bros, Inc.
City of Lake Elmo $124,410.00 $130,845.00
West Lakeland Township $52,360.00 $55,440.00
TOTAL: $176,770.00 $186,285.00
We recommend that you award the Contract to the lowest responsible bidder for the Alternate Bid to Allied
Blacktop Company in the total amount of $173,305.00. This includes the amount of $122,265.00 for the City
of Lake Elmo and the amount of $51,040.00 for West Lakeland Township. The Alternate Bid includes the
higher grade CRS‐2P emulsified asphalt for a superior product.
Please contact me with any questions you may have.
Sincerely,
Ryan W. Stempski, P.E.
Project Engineer
Enclosure
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
TABULATION OF BIDS
2017 SEAL COAT PROJECT
CITY OF LAKE ELMO & WEST LAKELAND TWP
PROJECT NO. 2017.118
BIDS OPENED: MAY 4, 2017, AT 3:00 PM
BASE BID (CRS‐2 EMULSIFIED ASPHALT)
ITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
CITY OF LAKE ELMO
1 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK 107,250 SY 1.23$ 131,917.50$ 1.11$ 119,047.50$ 1.12$ 120,120.00$ 1.16$ 124,410.00$
CITY OF WEST LAKELAND
2 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK 44,000 SY 1.23$ 54,120.00$ 1.13$ 49,720.00$ 1.12$ 49,280.00$ 1.19$ 52,360.00$
TOTAL 186,037.50$ 168,767.50$ 169,400.00$ 176,770.00$
ALTERNATE BID NO. 1 (CRS‐2P EMULSIFIED ASPHALT)
ITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
CITY OF LAKE ELMO
1 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK 107,250 SY 1.33$ 142,642.50$ 1.14$ 122,265.00$ 1.18$ 126,555.00$ 1.22$ 130,845.00$
CITY OF WEST LAKELAND
2 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK 44,000 SY 1.33$ 58,520.00$ 1.16$ 51,040.00$ 1.18$ 51,920.00$ 1.26$ 55,440.00$
TOTAL 201,162.50$ 173,305.00$ 178,475.00$ 186,285.00$
ENGINEER'S ESTIMATE Allied Blacktop Company Astech Corporation
ENGINEER'S ESTIMATE Allied Blacktop Company Astech Corporation Pearson Bros, Inc.
Pearson Bros, Inc.
PROJECT SCHEDULE
CITY OF LAKE ELMO
2017 SEAL COAT PROJECT
PROJECT NO. 2017.118
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
APRIL 6, 2017 Placement of Advertisement for Bids.
–Oakdale‐Lake Elmo Review. Publication on April 12
– Quest CDN. Publication on April 12
MAY 4, 2017 Receive Contractor bids.
MAY 16, 2017 Council accepts bids and awards Contract.
JUNE 14, 2017 Conduct Pre‐construction meeting and Issue Notice to Proceed.
JUNE 15, 2017 Contractor begins Work.
JULY 14, 2017 Substantial Completion of Work; including sweeping of excess aggregate.
AUGUST 31, 2017 Final Completion of Work; including punchlist and final documentation.