HomeMy WebLinkAbout08 - Inwood Water Tower (No. 4) - Payment Request No. 11 STAFF REPORT
DATE: July 18, 2017
CONSENT
ITEM #: 8
AGENDA ITEM: Inwood Water Tower (No. 4) – Pay Request No. 11
SUBMITTED BY: Chad Isakson, Project Engineer
REVIEWED BY: Krintina Handt, City Administrator
Jack Griffin, City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 11?
BACKGROUND: CB&I, Inc. was awarded a construction contract on March 15, 2016 to complete the
Inwood Water Tower (No. 4) project. The substantial completion date for the project is September 28,
2017.
PROPOSAL DETAILS/ANALYSIS: CB&I, Inc., has submitted Partial Pay Request No. 11 in the
amount of $60,914.00. The request has been reviewed and payment is recommended in the amount
requested. In accordance with the contract documents, the City has retained 5% of the total work
completed. The amount retained is $105,446.43.
FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project.
Payment remains within the authorized scope and budget.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent
Agenda, Pay Request No. 11 for the Inwood Water Tower (No. 4) project. If removed from the consent
agenda, the recommended motion for the action is as follows:
“Move to approve Pay Request No. 11 to CB&I, Inc. in the amount of $60,914.00 for the Inwood
Water Tower (No. 4)”.
ATTACHMENTS:
1. Partial Pay Estimate No. 11.