HomeMy WebLinkAbout# 03 - Old Village Ph3 Street and Utility Improvements STAFF REPORT
DATE: July 5, 2017
CONSENT
ITEM #: 3
AGENDA ITEM: Old Village Phase 3 Street, Drainage, and Utility Improvements - Change
Order No. 1
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator
Rob Weldon, Public Works Director
Chad Isakson, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 1 for the Old Village
Phase 3 Street, Drainage, and Utility Improvements?
BACKGROUND: Douglas-Kerr Underground, LLC was awarded a construction contract to complete the
Old Village Phase 3 Street, Drainage, and Utility Improvements on May 16, 2017. The project is in
construction with an anticipated substantial completion date of October 27, 2017.
PROPOSAL DETAILS/ANALYSIS: Douglas-Kerr Underground, LLC has submitted a change order to
address two design changes requested by the City as follows:
1. Remove the storm sewer piping and a stormwater treatment basin from the City Hall property.
The stormwater treatment basin is no longer required after the City obtained a variance to the
Valley Branch Watershed District rules. The variance was obtained after bids for the project were
received.
2. The sanitary sewer main and service pipe was redesigned for the properties located at 11200 and
11240 Stillwater Boulevard to accommodate easement constraints and address separation
requirements from existing water service lines. An 8-inch sewer main (in lieu 3 6-inch sewer
services) was extended across the property of 11200 Stillwater Blvd using watermain pressure
grade pipe. Separation from drinking water facilities caused a watermain grade pipe material to
be necessary which was not included in the original bid.
FISCAL IMPACT: This change order will decrease the contract in the amount of $16,586.70 bringing
the revised construction contract to $1,559,452.45. With this change order the project remains within the
authorized project budget and contingencies.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent
Agenda, Change Order No. 1 for the Old Village Phase 3 Street, Drainage, and Utility Improvements. If
removed from the consent agenda, the recommended motion for the action is as follows:
“Move to approve Change Order No. 1 for the Old Village Phase 3 Street, Drainage, and Utility
Improvements, thereby decreasing the contract amount by $16,586.70”.
ATTACHMENTS:
1. Change Order No. 1.