HomeMy WebLinkAbout# 13 - 2017 Street Improvements - Pay Request No. 3 STAFF REPORT
DATE: September 19, 2017
CONSENT
AGENDA ITEM: 2017 Street Improvements – Pay Request No. 3
SUBMITTED BY: Chad Isakson, Project Engineer
REVIEWED BY: Kristina Handt, City Administrator
Jack Griffin, City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 3 for the 2017 Street
Improvements?
BACKGROUND: Hardrives, Inc. was awarded a construction contract on May 16, 2017 to complete the
2017 Street Improvements project. The substantial completion date for the project is September 22, 2017.
PROPOSAL DETAILS/ANALYSIS: Hardrives, Inc., has submitted Partial Pay Request No. 3 in the
amount of $435,391.28. The request has been reviewed and payment is recommended in the amount
requested. In accordance with the contract documents, the City has retained 5% of the total work
completed. The amount retained is $36,614.11.
FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project.
Payment remains within the authorized scope and budget.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent
Agenda, Pay Request No. 3 for the 2017 Street Improvements. If removed from the consent agenda, the
recommended motion for the action is as follows:
“Move to approve Pay Request No. 3 to Hardrives, Inc. in the amount of $435,391.28 for the 2017
Street Improvements project”.
ATTACHMENTS:
1. Partial Pay Estimate No. 3.
PROJECT PAY FORM
PARTIAL PAY ESTIMATE NO.
PERIOD OF ESTIMATE
TO
PROJECT OWNER: CONTRACTOR:
1. Original Contract Amount
2. Net Change Order Sum
3. Revised Contract (1+2)
4. *Work Completed
5. *Stored Materials
6. Subtotal (4+5)
7. Retainage*
8. Previous Payments
9. Amount Due (6‐7‐8)
*Detailed Breakdown Attached
START DATE:ON SCHEDULE
SUBSTANTIAL COMPLETION:X
FINAL COMPLETION:
ENGINEER'S CERTIFICATION: FOCUS Engineering, inc.
DATE
CONTRACTOR'S CERTIFICATION: CONTRACTOR
DATE
APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA
DATE DATE
No.Approval
Date
Amount $1,038,206.14
Additions Deductions $15,742.25
$732,282.24
1 8/1/2017 $15,742.25 $1,053,948.39
$732,282.24
$0.00
$260,276.85
$36,614.115.0%
CONTRACT TIME
TOTALS $15,742.25 $0.00 $435,391.28
NET CHANGE $15,742.25
CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY
3
8/31/20178/1/2017FROM
2017 STREET IMPROVEMENTS
PROJECT NO. 2016.135
CITY OF LAKE ELMO
3800 LAVERNE AVENUE NORTH
LAKE ELMO, MN 55042
ATTN: JACK GRIFFIN, CITY ENGINEER
HARDRIVES, INC.
14475 QUIRAM DRIVE
ROGERS, MN 55374
ATTN: NATHAN LINDBERG, PROJECT MANAGER
6/12/2017
10/27/2017
REVISED DAYS
REMAINING
137
0
57
9/22/2017
ORIGINAL DAYS
BY
BY
YES
NO
The undersigned Contractor certifies that to the best of their
knowledge, information and belief the work covered by this payment
estimate has been completed in accordance with the contract
documents, that all amounts have been paid by the contractor for
work for which previous payment estimates was issued and payments
received from the owner, and that current payment shown herein is
now due.
The undersigned certifies that the work has been reviewed and to the
best of their knowledge and belief, the quantities shown in this
estimate are correct and the work has been performed in accordance
with the contract documents.
ENGINEER
BY
9/11/2017
FOCUS Engineering, inc.PROJECT PAYMENT FORM
PARTIAL PAY ESTIMATE NO. 3
2017 STREET IMPROVEMENTS
CITY OF LAKE ELMO, MINNESOTA
PROJECT NO. 2016.135
QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
1 LS 1
$4,226.26 $4,226.26 0.00 $0.00 1.00 $4,226.26
2 LS 1
$1,890.12 $1,890.12 0.00 $0.00 1.00 $1,890.12
3 LF 180
$2.63 $473.40 220.00 $578.60 220.00 $578.60
4 EA 39
$90.00 $3,510.00 23.50 $2,115.00 36.00 $3,240.00
5 EA 11
$231.01 $2,541.11 0.00 $0.00 15.00 $3,465.15
6 EA 11
$126.01 $1,386.11 0.00 $0.00 15.00 $1,890.15
7 CY 2,080
$10.00 $20,800.00 0.00 $0.00 0.00 $0.00
8 SY 10,330
$4.40 $45,452.00 0.00 $0.00 0.00 $0.00
9 SY 2,140
$1.95 $4,173.00 0.00 $0.00 0.00 $0.00
10 EA 10
$472.53 $4,725.30 0.00 $0.00 0.00 $0.00
$89,177.30 $2,693.60 $15,290.28
1 LF 281
$5.25 $1,475.25 0.00 $0.00 273.00 $1,433.25
2 EA 12
$420.02 $5,040.24 0.00 $0.00 13.00 $5,460.26
3 EA 1
$420.02 $420.02 0.00 $0.00 1.00 $420.02
4 EA 13
$159.82 $2,077.66 13.00 $2,077.66 13.00 $2,077.66
5 EA 13
$659.11 $8,568.43 13.00 $8,568.43 13.00 $8,568.43
6 LF 66
$31.50 $2,079.00 0.00 $0.00 98.00 $3,087.00
7 LF 1,773
$32.55 $57,711.15 0.00 $0.00 1,772.00 $57,678.60
8 LF 20
$60.90 $1,218.00 0.00 $0.00 16.00 $974.40
9 EA 5
$945.06 $4,725.30 0.00 $0.00 4.00 $3,780.24
10 EA 1
$2,205.12 $2,205.12 0.00 $0.00 1.00 $2,205.12
11 EA 4
$1,732.60 $6,930.40 0.00 $0.00 6.00 $10,395.60
12 EA 17
$2,058.11 $34,987.87 0.00 $0.00 18.00 $37,045.98
13 CY 39
$89.25 $3,480.75 0.00 $0.00 38.30 $3,418.28
14 LF 220
$17.85 $3,927.00 0.00 $0.00 285.00 $5,087.25
$134,846.19 $10,646.09 $141,632.09
1 LF 310
$1.00 $310.00 0.00 $0.00 310.00 $310.00
2 LF 130
$1.65 $214.50 0.00 $0.00 161.00 $265.65
3 SY 680
$4.12 $2,801.60 0.00 $0.00 630.00 $2,595.60
4 SY 220
$7.49 $1,647.80 0.00 $0.00 196.00 $1,468.04
5 SY 41,776
$1.35 $56,397.60 0.00 $0.00 41,776.00 $56,397.60
6 CY 4,062
$9.47 $38,467.14 659.00 $6,240.73 3,721.00 $35,237.87
7 LF 3,174
$1.01 $3,205.74 0.00 $0.00 0.00 $0.00
8 CY 370
$0.01 $3.70 349.00 $3.49 349.00 $3.49
9 RS 121
$250.00 $30,250.00 121.00 $30,250.00 121.00 $30,250.00
10 SY 893
$18.00 $16,074.00 0.00 $0.00 0.00 $0.00
11 TN 4,380
$48.75 $213,525.00 3,739.96 $182,323.05 3,739.96 $182,323.05
12 TN 3,290
$51.45 $169,270.50 0.00 $0.00 0.00 $0.00
13 GAL 2,020
$1.25 $2,525.00 200.00 $250.00 200.00 $250.00
14 LF 9,560
$2.60 $24,856.00 0.00 $0.00 0.00 $0.00
15 LF 20,997
$10.25 $215,219.25 20,939.00 $214,624.75 20,939.00 $214,624.75
16 EA 3
$523.98 $1,571.94 0.00 $0.00 0.00 $0.00
17 SY 220
$50.61 $11,134.20 222.78 $11,274.90 222.78 $11,274.90
18 LF 2,000
$9.60 $19,200.00 0.00 $0.00 1,830.00 $17,568.00
19 EA 20
$230.00 $4,600.00 0.00 $0.00 18.00 $4,140.00
20 EA 2
$1,454.34 $2,908.68 0.00 $0.00 2.00 $2,908.68
$814,182.65 $444,966.92 $559,617.63
TOTALS ‐ BASE CONTRACT $1,038,206.14 $458,306.61 $716,539.99
CHANGE ORDER NO. 1
CO1‐1 LS 1.0 $2,400.00 $2,400.00 0.00 $0.00 1.0 $2,400.00
CO1‐2 LF 54.0 $5.25 $283.50 0.00 $0.00 54.0 $283.50
CO1‐3 LF 54.0 $60.90 $3,288.60 0.00 $0.00 54.0 $3,288.60
CO1‐4 EA 1.0 $2,205.15 $2,205.15 0.00 $0.00 1.0 $2,205.15
CO1‐5 EA 1.0 $700.00 $700.00 0.00 $0.00 1.0 $700.00
CO1‐6 LS 1.0 $3,150.00 $3,150.00 0.00 $0.00 1.0 $3,150.00
CO1‐7 LS 1.0 $3,715.00 $3,715.00 0.00 $0.00 1.0 $3,715.00
GRADE TO DRAIN
BITUMINOUS MATERIAL FOR TACK COAT
REMOVE & DISPOSE OF EXISTING CONCRETE CURB AND GUTTER, ALL TYPES
REMOVE & DISPOSE OF EXISTING BITUMINOUS PAVEMENT (DRIVEWAY)
SUBTOTAL ‐ DIVISION 2
REMOVE & DISPOSE OF EXISTING CONCRETE PAVEMENT (DRIVEWAY)
RECLAIM EXISTING BITUMINOUS AND BASE MATERIALS (8" DEPTH INCL. BIT. CURB) (P)
DIVISION 3 ‐ STREET IMPROVEMENTS
SAWCUT BITUMINOUS OR CONCRETE
HAUL OUT EXCESS RECLAIMED MATERIAL (LV)
2' AGGREGATE SHOULDERING
15" FLARED END SECTION
18" FLARED END SECTION
CATCH BASIN TYPE 404
CATCH BASIN/MANHOLE TYPE 406
RIP RAP INCL. GEOTEXTILE
ITEM DESCRIPTION OF PAY ITEM UNIT
CONTRACT THIS PERIOD TOTAL TO DATE
DIVISION 1 ‐ GENERAL
MOBILIZATION
REMOVE & DISPOSE OF ENERGY DISSIPATION STRUCTURE
REMOVE CATCH BASIN CASTING
R‐3067 CATCH BASIN CASTING
12" RCP STORM SEWER PIPE
15" RCP STORM SEWER PIPE
18" RCP STORM SEWER PIPE
TRAFFIC CONTROL
SILT FENCE
INLET PROTECTION
CLEAR TREE
GRUB TREE
IMPORT AND PLACE TOPSOIL BORROW
SODDING
SEED, MULCH, & FERTILIZER
REINSTALL PROPERTY CORNER
DIVISION 2 ‐ STORM SEWER IMPROVEMENTS
REMOVE & DISPOSE OF EXISTING STORM SEWER (ALL SIZES AND TYPES, INCL. END SECT
REMOVE & DISPOSE OF EXISTING STORM SEWER STRUCTURE
SUBTOTAL ‐ DIVISION 1
SUBTOTAL ‐ DIVISION 3
SUBGRADE CORRECTION
SUBGRADE PREPARATION OF RECLAIMED SURFACE (P)
BITUMINOUS DRIVEWAY PAVEMENT
MANHOLE UPPER SECTION REHABILITATION
SAW AND SEAL STREET (40' INTERVALS)
BITUMINOUS NON‐WEARING COURSE
BITUMINOUS WEARING COURSE
CONCRETE CURB AND GUTTER, ALL TYPES
6" CONCRETE FLUME (ALL TYPES)
6" CONCRETE DIRVEWAY PAVEMENT
4" PERFORATED PVC EDGE DRAIN
DRAINTILE CLEANOUT
MOBILIZATION
REMOVE STORM SEWER
18‐INCH RCP STORM SEWER
18‐INCH FES W/ TRASHGUARD
CONNECT TO EXISTING STRUCTURE
CULVERT 305‐1 EXTENSION
CULVERT 306‐1 EXTENSION
QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
ITEM DESCRIPTION OF PAY ITEM UNIT
CONTRACT THIS PERIOD TOTAL TO DATE
TOTALS ‐ CHANGE ORDER NO. 1 $15,742.25 $0.00 $15,742.25
TOTALS ‐ REVISED CONTRACT $1,053,948.39 $458,306.61 $732,282.24