MEMORANDUM
Date: February 17, 2019
To: Ken Roberts, Planning Director Re: Bentley Village
Cc: Chad Isakson, Assistant City Engineer Preliminary Plan Engineering Review
From: Jack Griffin, P.E., City Engineer
An engineering review has been completed for the Bentley Village Preliminary Plat/Plans. The submittal consisted
of the following documentation prepared by Alliant Engineering and received on January 31, 2019:
Preliminary Plat/Plans dated January 25, 2019.
Stormwater Management Plan dated January 25, 2019.
Phasing Plan dated January 25, 2019.
Drainage and Utility Vacation Exhibits dated January 25, 2019.
STATUS/FINDINGS: Engineering has prepared the following review comments:
PRELIMINARY PLAT AND PRELIMINARY SITE PLANS
Preliminary plat approval should be contingent upon all public improvements being designed and
constructed in accordance with the City Engineering Design Standards Manual.
Preliminary plat approval should also be contingent upon the preliminary plans being revised and
approved by the City prior to the City accepting an application for any phase of final plat.
All Outlots (A, B, C, D, E, F, G, H and I) should be shown as HOA owned. Outlot ownership should be
identified on the preliminary plat and on all construction plans.
Drainage and utility easements have been shown over all Outlots. These easements will allow for City
maintenance of the storm water BMPS and storm sewer system. However, the preliminary plans must be
revised to eliminate all encroachments (buildings, retaining walls, trees, small utility corridors) that result
in “effective” maintenance easement areas that are less than City minimum requirements.
The site plans and preliminary plans must be revised to show a dedicated 10‐foot utility corridor along all
public streets, including 5th Street North, without encroachment by other design elements (e.g. storm
sewer pipe, retaining walls, buildings, landscaping, storm water retention, etc.). The easements have been
provided as required but the corridors have not been reserved for the dedicated purpose.
All storm sewer pipe easements and effective maintenance areas must be a minimum 30‐feet in width.
Additional width may be required for deeper storm sewer. Significant plan revisions are needed to
provide the minimum 15‐feet of clearance from the pipe centerline. Storm sewer closer than 15‐feet from
plat boundaries will require off‐site easements over the adjacent property. Retaining walls are not
allowed to be constructed over storm sewer.
Written landowner permission must be submitted as part of the final plat applications for any off‐site
grading work and storm water discharges to adjacent properties. The proposed off‐site easements must
be shown on the preliminary site plans, grading plans, and utility plans.
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4285
PAGE 2 of 5
Typical Townhome Lot Detail. The typical Townhome Lot detail proposes a minimum setback of 25 feet
from the right‐of‐way to the garage door. Preliminary Plat approval should identify this requirement as a
condition of approval to ensure that vehicles parked in the driveway do not obstruct sidewalks.
Driveway connections to City Streets. The site plans and preliminary plans must be revised to show all
private driveways within the public right‐of‐way to be perpendicular to the street.
Once driveways are shown perpendicular to the street, a detailed street/boulevard plan must be
incorporated into the preliminary plans that specifically identifies each on‐street parking location,
dedicated areas for snow storage, hydrant placement, mail box locations, street light locations,
water/sewer service locations, and landscaping improvements. The proposed parking plan does not take
these conflicts into consideration.
Landscape Plans must be revised to avoid planting conflicts with utilities and pond maintenance access.
Tree plantings must remain outside of utility easements, including the 10‐foot small utility corridor along
all public roads, and clear from all storm water maintenance benches and access roads. Tree plantings
must be offset a minimum of 10 feet from watermains, hydrants, sanitary sewer mains, storm sewers, and
water/sewer services. Water/sewer services must be shown on the landscape plans.
All proposed retaining walls should be privately owned and maintained.
PHASING PLAN
The phasing plan includes the construction of Road G (North‐South Collector Roadway) as part of Phase 1.
This is beneficial to direct traffic away from 5th Street and to initiate both the east development and west
development from Road G rather than 5th Street.
The phasing plan must be included in the Final approved Preliminary Plan set.
The phasing plan should include the watermain, sanitary sewer and storm sewer infrastructure to be
completed with each phase of the development, including the storm water basin outfall piping.
Temporary cul‐de‐sacs per City standard details will be required with Phase 1 and 3 and should be shown
on the phasing plans.
TRANSPORTATION IMPROVEMENTS
5th Street North Right‐of‐Way Dedication. The existing collector street to the north of the site (5th Street
North) was constructed by Lennar within a permanent roadway easement. This easement area must be
dedicated to the City as public right‐of‐way as part of this development. Per the City design standards for
5th Street, a 10 ft. utility easement corridor along the south side of the 5th Street right‐of‐way must also
be reserved for small utilities with no encroachment from the development improvements.
Site Access from 5th Street North. The preliminary plans propose three new public street intersections
with 5th Street North; one at Junco Road North; one at Julianne Avenue North; and the construction of a
new north‐south collector street (Road G) that will eventually connect 5th Street North with Hudson
Boulevard. All proposed intersections are consistent with approved access configuration along 5th Street.
Additional Site Access. The new public streets proposed for this development will each have secondary
access to the new north‐south collector street (Road G) that will eventually connect 5th Street North with
Hudson Boulevard. Access spacing appears to be acceptable along the new collector street.
Road G (New North‐South Collector Street) Alignment. Road G is consistent with the City’s planning
efforts and the proposed street is shown in the approximate location as planned. However, there are
existing sanitary sewer and watermain utilities located in the corridor. The design for this new collector
street must therefore consider the existing location of these utilities and must be consistent with City
right‐of‐way and boulevard design standards.
Public Street Typical Sections. The preliminary plan typical sections must be updated to provide all
required information consistent with City design standard details. The 10‐foot utility corridors must be
shown on each side for all public streets to be preserved for small utility installation. Driveway grades
must be shown at 4% along boulevards, at 2% along the sidewalk, and can vary up to 10% once beyond
PAGE 3 of 5
the public right‐of‐way. Any proposed landscaping within the public right‐of‐way must be shown on the
typical sections for review by the City.
Road G Typical Section. The Typical Section of Road G (North‐South Collector Street) must be determined
by the City as the plat moves forward through the process, including required right‐of‐way width and lane
configuration. The preliminary plans propose a 40‐foot wide paved street to include two 12‐foot drive
lanes and one 12‐foot center turn lane, within a 100‐foot right‐of‐way. The right‐of‐way width may be
able to be reduced to 80‐feet through City staff evaluation. In addition, per City design standards, 10‐foot
utility easements must be provided along each side of the new R/W. An 8‐foot wide bituminous trail is
proposed on the east boulevard to connect to the future Hudson Boulevard trail corridor and a 6‐foot
sidewalk is proposed on the west boulevard.
5th Street North Turn Lanes. Eastbound right turn lanes (RTL) along 5th Street are in place at the
intersections of Road G and Junco Road but not at Julianna Avenue. A westbound left turn lane (LTL) along
5th Street is in place at the Road G intersection. Additional transportation review is necessary to evaluate
if additional turn lanes should be required including an eastbound right turn lane (RTL) at Julianna Avenue
and westbound left turn lanes (LTL) at Junco Road and/or Julianna Avenue.
Road G Turn Lanes Required at intersection with 5th Street. A northbound RLT and LTL is proposed at the
intersection of 5th Street North and Road G.
The proposed development will increase traffic movements at the intersections of CSAH‐19 and 5th Street
North and CSAH‐19 and Hudson Boulevard. A financial contribution to traffic signal and turn lane
improvements to one or both of these intersections should be considered.
RESIDENTIAL STREETS AND RIGHT‐OF‐WAYS
All streets are proposed to be publicly owned and maintained. Public streets are proposed to meet the
City’s Engineering Design Standard street width of 28‐feet with 45‐foot cul‐de‐sac radii. However, the
applicant is proposing a reduced right‐of‐way width from the City standard 60 feet to 53 feet. The
reduced width is adequate for the proposed design since boulevard trees are not proposed within the
right‐of‐way and the street section is not centered within the right‐of‐way. A six (6) foot sidewalk is
proposed along one side of all residential streets within a 28‐foot right‐of‐way from centerline and the
other side of the street is within a 25‐foot right‐of‐way from centerline with no sidewalk.
In addition to the 53‐foot right‐of‐way, a 10‐foot utility corridor must be preserved for small utility
installation along both sides of the street. A 10‐foot drainage and utility easement is provided through the
overall Outlot easements, however the preliminary plans must be revised to eliminate all encroachments
to the utility corridors. The site plans and preliminary plans must be revised to show on the plans the
dedicated 10‐foot utility corridors along all public streets, including the south boulevard of 5th Street.
The proposed internal street network is well interconnected creating multiple access routes into and out
of the development. Only one short cul‐de‐sac has been proposed.
The street plan proposes raised landscaped medians at all entrance points. Divided roadways must be a
minimum of 19 feet wide each way from back of curb to back of curb.
The City Standard boulevard must not exceed a 4% grade to the street. The driveway grades shown on the
street typical sections must be removed. Grades exceeding 4% may be used outside the right‐of‐way.
Coordinated landscape plans. The boulevard layout does not accommodate boulevard trees within the
public right‐of‐way. No boulevard trees can be placed within the 10‐foot utility easements. Landscaping
requirements/plans must be planned accordingly.
The south leg of Road E, at the intersection with Road D, must be revised to provide a minimum 50‐foot
tangent prior to the start of the horizontal curve. All street intersections must be at 90 degrees and
maintain 50 feet of tangent with maximum slopes of 2.5%. Streets must also meet City standards for
horizontal and vertical curvature. The City standard minimum horizontal curve radius is 90.
Residential maximum longitudinal grade is 8% with no sidewalks, 6% where there are sidewalks. These
requirements have been met with the proposed plans.
PAGE 4 of 5
Surmountable concrete curb and gutter shall be installed along areas with future driveways and B618
curb installed along entrance roadways and roadway stretches with no lots. The plans must be revised to
incorporate the B style curb where appropriate.
GRADING PLAN, STORMWATER MANAGEMENT AND STORM SEWER SYSTEM
The site plan is subject to a storm water management plan meeting State, VBWD and City rules. Storm
water facilities proposed as part of the site plan to meet State and VBWD permitting requirements must
be constructed in accordance with the City Engineering Design Standards Manual. Preliminary Plan
revisions are required to comply.
All storm water facilities and infiltration basins have been placed in Outlots as required. Drainage and
utility easements have been proposed over all of each Outlot to facilitate maintenance by the City.
The Stormwater facility Outlots must fully incorporate the 100‐year HWL, 10‐foot maintenance bench,
and all maintenance access roads.
Stormwater Ponds must be constructed meeting City standards. Stormwater forebays require a 10:1
safety bench at the NWL with the NWL shown on the plans. Designated maintenance access roads, 20 feet
in width, must be provided for all storm water facilities and must extend from the public right‐of‐way to
the maintenance bench with grades not exceeding 10%. Basin grading must also provide a maintenance
bench from the access road to all storm sewer inlets and outfall pipe locations.
Infiltration basin A proposes significant grading within the existing gas pipeline easement. Documentation
must be provided by the gas main owner to demonstrate approval for this grading impact. The
preliminary plans and existing conditions plan must be updated to show the existing gas main location
including pipe size, material and depth.
The NWL (forebays) and 100‐year HWL basin elevations, and 100‐year HWL contour must be shown on
the plans for each storm water facility to facilitate plan review. The maintenance access roads/benches
must be clearly shown to verify no obstructions (including landscaping) within the access locations.
Infiltration Basin C capacity is required to meet volume control requirements, but the basin must be
relocated. Infiltration basins are not allowed in Type D soils. The basin also appears to be within 35 feet of
an off‐site septic system to the south (see existing conditions plan). No maintenance access is proposed.
Additional borings are required for each infiltration basin. A minimum of 2 borings are required per basin
and must be obtained from within the actual proposed basin location. Additional borings are required for
basins larger than 10,000 square feet (see engineering design standards manual).
Overland emergency overflows have been provided as required. All emergency overflow elevations must
be fully protected by drainage easement.
All lots must have the minimum floor elevation at least 2 feet above any BMP 100‐year HWL and at least
1‐foot above any emergency overflow point. These conditions appear to have been met with the
proposed preliminary plans.
The 100‐year HWL must be calculated and the 100‐year HWL contour placed on the plans for all localized
catch basin low points and the entire 100‐year HWL must be fully protected by drainage and utility
easement. This information has not been provided.
The maximum curb run prior to a catch basin is 350 feet. The preliminary plans appear to meet this
standard. Additional CBs may be required along Road F between STA 0+00 and STA 3+62 to enhance
drainage through flat area.
Additional storm sewer and CBs will likely be required along Road G to accommodate the wider street
pavement widths and drainage from 5th Street North.
Minimum storm sewer pipe size is 15‐inch except for the storm sewer lead pipe located within paved
streets. The storm sewer must be increased to the minimum 15‐inch pipe for storm runs from CB218‐
CB216; CB217‐CB216; CB206‐CB204; CB319‐CB318; CB317‐CB316; CB403‐CB402.
The storm water model assumes a 12” x 6” orifice. This detail should be added to the storm sewer plans.
PAGE 5 of 5
The storm sewer system shall be designed to maintain the City standard minimum pipe cover of 3.0 feet.
Drain tile is required as part of the City standard street section at all localized low points in the street.
Drain tile considerations may impact the storm sewer design and depth requirements at low points.
Street Grades. Street profile design should not include minimum grades to allow for construction
tolerances. The Road A street profile grades from STA 19+00 to STA 21+50 and Road F street profile
grades from STA 1+50 to STA 5+00 should be increased to avoid flat areas and potential standing water in
the curb line.
MUNICIPAL SANITARY SEWER
The development is proposing 240 REC units that will be discharged to the MCES WONE Interceptor. This
is consistent with the Comprehensive Sewer Plan. The applicant will be responsible to connect to the City
sanitary sewer system located along the alignment for the future collector roadway and extend sanitary
sewer into the property at applicant’s sole cost.
Reconfiguration of the sanitary sewer connection points may be required. The preliminary plans show the
sanitary sewer connection to be made outside of the plat boundaries on the adjacent property to the
south. The preliminary plans identify proposed drainage and utility easements necessary to make this
connection. Additional drainage and utility easement will be required to meet the City minimum 15‐feet
from the pipe centerline. Written permission from the adjacent property owner must be submitted with
any final plat demonstrating the ability to acquire the necessary easements.
The applicant may be required to stub sanitary sewer mains to adjacent properties if needed to maintain
sewer access to all adjacent parcels (to be reviewed with final plans).
Any main sewer lines not installed within public right‐of‐way will require minimum 30‐foot easements
centered over the pipe (or wider dependent upon the sewer depths) dedicated to the City and in the form
of the City’s Utility Easement Agreement.
The preliminary plans must be updated to show the sanitary sewer services.
MUNICIPAL WATER SUPPLY
The applicant will be responsible to extend municipal water into the development at its sole cost and will
be required to construct a looped watermain network with multiple connection points. It is assumed that
all of the property can be served by the City’s high‐pressure zone. Watermain should be installed along
Road B and connected to existing watermain in 5th Street North at Julianne Avenue and watermain
should be installed along Road E and connected to existing watermain in 5th Street North at Junco Road.
The applicant may be required to provide watermain stub(s) to adjacent properties to maintain water
access to all adjacent properties. Watermain stubs should be extended to the adjacent property to the
south of the development near the west and east ends of the plat boundaries.
No watermain pipe oversizing is anticipated at this time. Further review will be completed as the
application moves forward through the process.
Reconfiguration of the watermain connection points may be required. The preliminary plans show the
watermain connections to be made outside of the plat boundaries on the adjacent property to the south.
The preliminary plans identify proposed drainage and utility easements necessary to make this
connection. Additional drainage and utility easement will be required to meet the City minimum 15‐feet
from the pipe centerline. Written permission from the adjacent property owner must be submitted with
any final plat demonstrating the ability to acquire the necessary easements.
The applicant will be responsible to place hydrants throughout the property at the direction of the Fire
Department. Hydrant and system valve requirements and placement will be addressed as part of final plat
and construction plan review. All fire hydrants shall be owned and maintained by the City.
Any watermain lines and hydrants placed within the development will require minimum 30‐foot
easements centered over the pipe. Easements must be dedicated to the City and be provided in the City’s
standard form of easement agreement.