HomeMy WebLinkAbout2019-02-18 Four Corners 2nd Addition - Eng. Preliminary Plan Review    PAGE 1 of 2  MEMORANDUM           Date:  February 18, 2019      To:  Ken Roberts, Planner Director  Re:  Four Corners 2nd Addition  Cc:  Chad Isakson, Assistant City Engineer    Preliminary Plan Engineering Review  From:  Jack Griffin, P.E., City Engineer          An engineering review has been completed for the Four Corners 2nd Addition Preliminary Plat/Plans received on  January 31, 2019. The submittal consisted of the following documentation:     Four Corners 2nd Addition Preliminary Plat, dated 01.25.2019, prepared by Folz Freeman Surveying (FFS).   Four Corners 2nd Addition Preliminary Plat Narrative, dated 01.25.2019, prepared by FFS.   Four Corners 2nd Addition Right‐of‐Way Vacation/Jurisdiction, dated 01.22.2019, prepared by FFS.   Four Corners 2nd Addition Lake Elmo Easement Vacation Request, dated 01.23.2019, prepared by FFS.   Four Corners 2nd Addition MnDOT Right‐of‐Way Vacation Request, dated 01.23.2019, prepared by FFS.   Four  Corners  2nd  Addition  Hudson  Blvd  Realignment  &  Trunk  Utility  Extension  Plans,  dated  01.25.2019,  prepared by Larson Engineering.    Four Corners 2nd Addition Stormwater Management Plan, dated 01.25.2019, prepared by Larson Engineering.   Geotechnical Evaluation Report for Metro Transit Park & Ride, dated 04.20.2017, prepard by Braun Intertec.      STATUS/FINDINGS:  Engineering has prepared the following review comments:      PRELIMINARY PLAT AND EASEMENTS   Preliminary  plat  approval  should  be  contingent  upon  all  public improvements  being  designed  and  constructed in accordance with the City Engineering Design Standards Manual.   Preliminary  plat  approval  should  also  be  contingent  upon  the  preliminary  plans  being  revised  and  approved by the City prior to the City accepting an application for any phase of final plat.   Outlots A, B, and C are proposed to be owned by EN Properties. Outlots have been labeled on some plans  but must also be identified on the street, utility and grading plans.   A drainage and utility easement must be provided over all of Outlot C. The Outlot C drainage easement  will allow for City maintenance of the storm water BMPS and storm sewer system. The drainage and  utility easement must be shown on the Preliminary Plat and Preliminary Plans.   The storm water management plan submitted with this application is incomplete and is subject to City,  VBWD, and MnDOT review once finalized. Preliminary Plat approval must be contingent upon revised  Preliminary Plans that provide for a storm water management plan meeting State, VBWD and City rules.    The Preliminary Plat must be contingent upon revised Preliminary Plans to address plan revisions required  by  Washington  County,  including  the  dedication  of  additional  right‐of‐way  along  Manning  Avenue,  if  required,  sight  triangle  right‐of‐way  if  required,  and  additional  intersection  improvements  at  Hudson  Boulevard and Manning Avenue (CSAH‐15), if required.   The Preliminary Plat identifies a proposed off‐site roadway and utility easement to be acquired from the  adjacent  property  north  of  the  plat  to  accommodate  the  Hudson  Boulevard  realignment  at  the  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.   651.300.4261  Jack Griffin, P.E.                651.300.4264  Ryan Stempski, P.E.  651.300.4267  Chad Isakson, P.E.  651.300.4285      PAGE 2 of 2  intersection with Manning Avenue (CSAH‐15). The roadway and utility easement must be submitted as  part of the final plat application.   The Preliminary Plat identifies a proposed roadway and utility easement with 80‐foot right‐of‐way to be  provided  to  facilitate a public street  connection from the adjacent property to  the north  to Hudson  Boulevard at the first intersection west of Manning Avenue (CSAH 15). The roadway and utility easement  must be submitted as part of the final plat application.   Additional drainage and utility easements must be identified and shown on the Preliminary Plat and  Construction Plans (street, utility and grading plans).   Add drainage and utility easements for the drainage ditch on the north side of Hudson Boulevard.   Add drainage and utility easements for the street culvert 100‐year HWL.   Add drainage and utility easement for the storm sewer pipe stub from STMH18 (see comment below).   Add drainage and utility easement for the storm sewer pipe stub from CB27 (see comment below).   Written landowner permission must be submitted as part of the final plat applications for any off‐site  grading work, easements and storm water discharges to adjacent properties.    PRELIMINARY CONSTRUCTION PLANS   C0.1.  Construction  Phasing.  The  Preliminary  Plans  must  be  revised  to  better  detail  the  construction  phasing between street construction and storm water management.     C2.0. Realign water/sewer per attached exhibit.   C2.0 ‐C2.1. Revise the sanitary sewer and watermain stub pipe sizes to 24‐inch sanitary sewer and 12‐inch  watermain at STA 26+00, extending to the northwest.   C3.0. Revise the street widths to 40 feet for both westerly street stubs.   C4.0. Label all FES structures. Add storm sewer chart to the plans with pipe cover and pipe velocities.   C4.0. Extend the storm sewer pipe stub from STMH18 to 15 feet from the bituminous trail to avoid trail  excavation during future extension of pipe.   C4.0. Revise STMH18 to a catch basin to eliminate the manhole in the drive lane.   C4.1. Extend the storm sewer pipe stub from CB27 to 15 feet from the bituminous trail to avoid trail  excavation during future extension of pipe.   C4.1. Extend the bituminous trail to the paved surface along Manning Avenue and extend the concrete  curb through the radius with a pedestrian ramp.   C4.2. Add sight triangles at the intersection with Manning Avenue as required by Washington County.   C4.3. Revise Typical Sections as follows:   Locate trail 2‐feet from right‐of‐way.   Revise paved rural section shoulder from 5‐feet to 6‐feet.   Remove pavement section details for the bituminous trail and add note “see City Standard Detail 509”.   Add 10‐foot utility easement on south side for typical section from 11+50 to 14+88.    C4.4. Revise Typical Sections to add note for trail pavement section to “see City Standard Detail 509”.   C5.0‐C5.2. Add street stationing to the signing and pavement marking plans.   C5.0‐C5.2. Add dimensions and notes for the location and placement of all pavement markings.   C5.0. Add City standard plan notes for signing and pavement markings.   C5.0. Revise sign schedule to identify MUTCD sign codes and sign sizes.   C5.1. Add Type III barricades (2 each) at the end of both stub streets and update sign schedule.   C6.0. Minimum standard ditch grade is 2% for positive drainage. Revise the drainage ditch grading along  the north boulevard to eliminate flat areas and standing water.    C6.0. Add drainage easements for the proposed drainage ditch on the north side of Hudson Boulevard.   C6.0. Additional borings are required for each infiltration basin. A minimum of 2 borings are required per  basin  and  must  be  obtained  from  within  the  actual  proposed  basin  location.  Additional  borings  are  required for basins larger than 10,000 square feet (see engineering design standards manual).   C7.0. Revise vertical curve at STA 31+47. The City standard minimum K‐value for 45 mph sag curve is 79.