HomeMy WebLinkAboutPC Report 5-13-19 - ZMA Prelim Plat and PUD-jwgedits THE CITY OF
LAKE ELMO
STAFF REPORT
DATE: 05/13/19
REGULAR—
ITEM#: 4A-Public Hearing
TO: Planning Commission
FROM: Ken Roberts, Planning Director
AGENDA ITEM: Zoning Map Amendment and the Springs Apartments Preliminary
Plat and Preliminary Planned Unit Development (PUD) Plans
REVIEWED BY: Ben Prchal, City Planner
Jack Griffin, City Engineer
BACKGROUND:
The City has received land use requests from Continental 483 Fund LLC (c/o Gwyn Wheeler) for
approval of:
1. A Zoning Map Amendment(rezoning)from RT(rural development transitional)to HDR(urban
high density residential); and
2. Preliminary Plat and Preliminary Planned Unit Development(PUD)Plans for a 300 unit multi-
family residential development on a 17.01-acre parcel to be called Springs Apartments.
The City Council reviewed and approved the concept plans for this PUD on March 5, 2019. This
approval was documented in Resolution 2019-017 and was subject to 13 conditions of approval.
ISSUE BEFORE COMMISSION:
The Planning Commission is being asked to review the proposal, hold a public hearing, provide feedback
and make a recommendation to the City Council on the above-mentioned requests.
GENERAL INFORMATION:
• Property Owner: DPS-Lake Elmo, LLC of 6007 Culligan Way,Minnetonka, MN 55345
• Applicant: Continental 483 Fund LLC (c/o Gwyn Wheeler)
• Location:North of Hudson Blvd.N,west of Keats Avenue
• Site Area: 17.57 gross acres, 17.33 net acres
• Land Use Guidance: 2030 Comprehensive Plan—Commercial,2040 Comprehensive Plan—
Mixed Use Commercial
• Existing Zoning: Rural Development Transitional
• Proposed Zoning: Urban High Density Residential
• Surrounding Land Use Guidance: Commercial to the East,Urban Medium Density Residential to
the North, Commercial to the West,and Hudson Boulevard and 1-94 to South.
• History: The property has been used as rural vacant land and as a homestead. There is a wetland
on the site that staff is estimating is about 0.3 acres in size. It is located along the north side of
Hudson Blvd about 240 feet west of the east property line of the site(in about the location of
proposed Building 15). A large portion of the eastern part of the site is covered in trees.
1
• Deadline for Action: Application Complete: 4-12-2019
60-day timeline: 6-10-2019
PROPOSAL DETAILS/ANALYSIS:
Project Overview/Site Plan.The proposed site plan includes 15 buildings with 20 units each. The
buildings are a townhouse design,two stories tall with a mix of studio, 1-bedroom,2-bedroom and 3-
bedroom units. Many units provide attached, direct-access garages for a total of 120 attached garage
spaces for the 300 units. The applicant also is planning to have seven detached garage buildings(with a
total of 42 spaces), 399 surface parking spaces, an approximately 4,300 square foot club house(including
a large gathering room, fitness center,kitchen area, coffee bar and office space),pool with sun deck,trash
enclosure,mail kiosk, and one pet playground all within a fenced, controlled access community.
The site plan shows the primary entrance to the development would be off of Hudson Boulevard and there
would be an emergency access drive connecting to the north/south road(Julia Avenue)to the west of the
site. The applicant also is proposing to preserve much of an existing wetland on the site that is near
Hudson Boulevard.
About the Applicant.Continental 483 Fund LLC. (Applicant)desires to develop a Class A,market-rate
apartment community within the City. The company, started in 1979, is based out of Menomonee Falls,
WI, and as of 2016 has broken ground on 3,175 apartment homes in 7 states. 65 Springs Apartment
communities, similar to this proposed development,have been developed,including three in Minnesota
(Apple Valley,Rochester, and Savage). The applicant has indicated in meetings with City that
Continental owns and operates all Springs developments and they do not have third party management of
their properties.
2040 Comprehensive Plan Update. As the Planning Commission is aware,the City has been working to
complete its required 2040 Comprehensive Plan update. The City Council approved the proposed Plan
update at its February 5,2019 meeting and authorized City staff to submit the updated Comprehensive
Plan to the Metropolitan Council for their approval. Since then, City staff and the City Planning
consultant have been working with the Metropolitan Council to clarify information in the proposed plan
and we have submitted additional information to ensure the 2040 Comprehensive Plan will be complete
and will meet all the requirements of the Metropolitan Council. This review and approval process by the
Metropolitan Council may take up to 120 days. However, staff has been working closely with
Metropolitan Council staff and we are confident they will approve the 2040 Comprehensive Plan by
August. Once the Metropolitan Council approves the proposed Plan,the City must give the proposed
2040 Comprehensive Plan final approval and then start using and implementing the updated Plan.
Land Use. The proposed land use map in the 2040 Comprehensive Plan update shows this site
designated as MU-C(mixed use commercial). The proposed 2040 Plan notes "this designation is a new
land use and identifies where a mix of commercial and residential uses may be integrated to benefit from
proximity and adjacencies to each other. Commercial uses in this category include service and retail uses
such as,but not limited to,restaurants, shops,convenience stores, salons, studios and dry cleaners. Land
with this designation is assumed to develop with a minimum of 50 percent residential use with a density
ranging from 10-15 dwelling units per acre."
In this case,the applicant is proposing a development with 300 dwelling units on 17.33 net acres. This
calculates to 17.31 dwelling units per net acre thus exceeding the density limits set for this area in the
2040 Comprehensive Plan(without any credit for density bonuses that the City may grant through the
PUD process). At 15 dwelling units per net acre,this site could accommodate 260 units. (Please see the
Density Analysis below for more information about this.)
2
With the pending land use designation(MU-C) for this site,the City will not be able to give final
approval the proposal until after the Metropolitan Council and the City Council have finalized the 2040
Comprehensive Plan. The City could require the applicant to wait to submit the final plat and final PUD
plans for this project after the City has given the 2040 Comprehensive Plan final approval. This timing
will ensure that what is proposed for this site is consistent with the 2040 Comprehensive Plan and that the
City will get credit for the residential density that the project would bring to this part of Lake Elmo.
Another option would be for the City to require the applicant to wait to submit applications for final PUD
and final plat approval until the City has notification from the Metropolitan Council that the proposed
Comprehensive Plan is complete for their review. City staff has been working closely with the
Metropolitan Council staff since February to submit and resubmit all required data and information to
them to ensure the proposed Comprehensive Plan update is complete. Once the City knows the proposed
Comprehensive Plan update is complete,we are quite confident that that Metropolitan Council will
approve the proposed plan in a timely manner.
No matter when the applicant submits applications for final plat and final PUD approval,the City will
need to make any and all final project approvals contingent upon final approvals of the 2040
Comprehensive Plan by the Metropolitan Council and by the City Council.
Zoning Map Amendment. In order for this development to proceed,the City will need to approve a
zoning map amendment(rezoning)for the property from RT(rural development transitional)to HDR
(urban high density residential). According the Lake Elmo Zoning Code,the HDR district is to provide
for moderate to high density attached and multi-family housing, designed to present an attractive
appearance to neighboring street and adjacent uses,to include sufficient private and semi-private outdoor
space and to be well-integrated into their surroundings. Development in this district may occur at
densities in excess of seven dwelling units per acre,provided the overall densities are consistent with the
net densities specified in the Comprehensive Plan.
Preliminary Plat/PUD Plans
Preliminary Plat. The proposed preliminary plat shows one parcel for the project site. It does not show
the required 100-foot-wide street right-of-way for the north/south street(Julia Avenue)and any additional
right-of-way along Hudson Boulevard that might be needed to accommodate the required turn lanes and
public trail. The City should require the developer to include all necessary street right-of-way on the final
plat as a condition of approval.
Density Analysis. The proposed development includes 300 dwelling units. The applicant's data shows
the site with a total of 20.36 acres(including right-of-way for Hudson Boulevard(2.23 acres)) and right-
of-way for the north/south road(1.12 acres)with no proposed parkland or arterial right-of-way and a 0.24
acre wetland. The calculation by the developer of net density for the site is as follows: 20.36 acre site—
0.24 acre wetland=20.12 net acres. 300 units divided by 20.12 acres= 14.91 units per acre. The net
project density as calculated by the developer is 14.91 units per acre.
However,the City calculates the site density in this case as follows: Site— 17.01 acres plus 0.56 acres
(1/2 right-of-way for north/south road)—0.24 acres(wetland)= 17.33 net acres. 300 divided by 17.33
acres= 17.31 units per net acre. As noted above,this density would exceed the City's density
requirements for residential development in the mixed use commercial land use designation of 15 unit
units per acre(without any credit for density bonuses the City may grant through the PUD process).
Proposed Unit Breakdown.The proposed number of dwelling units totals 300. The following provides a
breakdown of the proposed unit types and the number of units of each:
3
Unit Type Number of Units
Studios 30
1-Bedroom 120
2-Bedroom 120
3-Bedroom 30
PUD—Overlay and Minimum Requirements.
Consistency with Planned Unit Development Regulations. Staff has reviewed the proposed plan for its
consistency with requirements of Article XVII: Planned Unit Development(PUD)Regulations and has
found the following:
• Intent.The intent of a PUD is to provide for flexibility in the use of land and the placement and
size of buildings in order to better utilize site features and obtain a higher quality of development.
A PUD is required for the proposed development, as more than one principal building is proposed
to be placed on a platted lot,there is a proposed reduce building setback from the west property
line and the proposed detached garage buildings are larger than the maximum-allowed 1,000
square feet in size.
• Identified Objectives.When reviewing requests for PUDs,the City is to consider whether one or
more objectives as outlined in Section 154.751: Identified Objectives of the Zoning Code will be
served or is achieved. Staff has found that the proposed development would meet the following
objectives:
A. Innovation in land development techniques that may be more suitable for a given
parcel than conventional approaches.
• The proposed development is not a typical,multi-story apartment building and instead
proposes a townhouse design two stories in height with private, ground-level entrances
to each unit.
C. Provision of a more adequate, usable, and suitably located open space, recreational
amenities and other public facilities than would otherwise be provided under
conventional land development techniques.
• The proposed development is proposing a number of recreational amenities to residents
within the PUD including pet playgrounds, clubhouse, and pool.
D. Accommodation of housing of all types with convenient access to employment
opportunities and/or commercial facilities; and especially to create additional
opportunities for senior and affordable housing.
• The proposed development will provide additional housing opportunities within the City,
as there are currently very few multi-family buildings within the City.
G. Coordination of architectural styles and building forms to achieve greater
compatibility within the development and surrounding land uses.
• The townhouse design will be compatible in design those of the nearby Savona
townhomes and with the future Pulte townhomes to the north of the site.
4
H. Higher standards of site and building design than would otherwise be provided under
conventional land development technique.
• The City does not currently have standards for single family housing. As such,the City
cannot impose guidelines and standards set forth with the Lake Elmo Design Guidelines
& Standards Manual on single family homes. However,the City may impose such
guidelines on high density residential development such as this proposal.
• Minimum Requirements.PUDs must meet the following minimum requirements:
A. Lot Area.A PUD must include a minimum of 5 acres for undeveloped land or 2 acres for
developed land within the approved development.
• The proposed development exceeds this requirement with a proposed 20.36 acre
development.
B. Open Space: For all PUDs, at least 20%of the project area not within street rights-of-
way to be preserved as protected open space. Other public or site amenities may be
approved as an alternative to this requirement.Any required open space must be
available to the residents, tenants, or customers of the PUD for recreational purposes or
similar benefit. Land reserved for storm water detention facilities and other required
site improvements may be applied to this requirement. Open space shall be designed to
meet the needs of residents of the PUD and the surrounding neighborhoods, to the
extent practicable,for parks,playgrounds,playing fields and other recreational
facilities.
• The applicant indicated in their project narrative that there will be 5.77 acres of open
space with this development. This is 28 percent of the gross project site area
including the pet area,green spaces and landscaped areas.
C. Street Layout... In newly developing areas, streets shall be designed to maximize
connectivity in each cardinal direction, except where environmental or physical constraints
make this infeasible.All streets shall terminate at other streets, at public land, or at a park
or other community facility, except that local streets may terminate in stub streets when
those will be connected to other streets in future phases of the development or adjacent
developments.
• The new north/south road connecting 5'Street to Hudson Blvd meets this
requirement. It is a recommended condition of approval that the developer address
all the comments outlined in the Engineering memo dated May 8,2019 before
submitting plans for a final plat and final PUD approval for this site.
Proposed Amenities.The City's PUD ordinance provides that developers may provide amenities with
their projects for increased density of up to 20 percent. In this case,because the applicant is proposing a
housing density of 17.31 units per net acre,the developer will need to provide amenities with the project
to justify the increased housing density above the expected allowed density range 10-15 units per acre of
the future MU-C land use designation. In addition, a PUD should offer the City(and future residents)
amenities in exchange for the flexibility of allowing a reduced setback to the westerly property line,more
than one building on a parcel as well as allowing detached garages larger than 1,000 square feet.
In this case,the developer is proposing the following site amenities that may qualify for amenity points:
• Underground or structure parking. The narrative of the application indicates that many units
provide attached, direct-access garages. It has not been indicated that this will reduce the surface
parking area outside the footprint of the principal structure by 25%,however, as required by the
PUD Code. (5-10 points possible)
5
• Contained Parking. By proposing 162 garage spaces for its residents,the proposed development
limits the amount of visible surface parking. (5 points possible)
• Pedestrian Improvements. By proposing a site and building design that allows for exceptional
and accessible pedestrian and/or bicycle access through and/or around the site. The
improvements shall use a combination of trails,landscaping, decorative materials,access control
and lighting to create safe,clear and aesthetically pleasing pedestrian facilities through and/or
around the site that comply with ADA accessibility requirements. In this case,the developer is
proposing a series of trails and sidewalks in and around their site that will provide many places
for pedestrians to move about without having to walk on the streets or on the driveways. (5 points
possible)
• Plaza. The applicant is proposing a pool, an approximately 4,300 square foot club house
(including a large gathering room, fitness center, a kitchen area, coffee bar and office space)and
the pet play area(dog park)within the development. The clubhouse/pool area could serve as a
plaza within this development as the PUD ordinance indicates that plazas are landscaped or paved
open areas of a minimum of 1,000 square feet and wholly or partially enclosed by a building or
buildings. The PUD ordinance requires that plazas within commercial or mixed-use development
shall be open to the public during daylight hours. The PUD ordinance does not require that
plazas within residential PUDs be open to the public. It also should also be noted that the
proposed development is providing a dog park that Staff believes in and of itself warrants an
additional amenity point. (5 total points possible)
• Providing theming. Significant use of various elements of theming consistent with the 2013 Lake
Elmo Branding and Theming Project, including but not limited to signage, fencing, landscaping
lighting and site furnishings. The City will award amenity points based upon the quality and
magnitude of the Theming elements integrated into the project.
In this case,the City could award the developer amenity points for the use vehicular and
pedestrian lighting in and around their site,increasing their landscaping and tree planting well
above the minimums set by the Code, (especially along Hudson Boulevard), adding several
benches within their site and using a white,ornamental-style fence(instead of chain link) around
their site.
It is a recommended condition of approval that the applicant provide the City specific examples
of proposed development fencing, landscaping, lighting and site furnishings, including the
clubhouse that will meet the standards outlined in the Lake Elmo Branding and Theming Study.
(1-3 points possible)
• Additional Amenities?Additionally,the City also may consider the allotment of amenity"points"
for site amenities that are not otherwise specified within the ordinance.
For this site,with a maximum of 15 dwelling units per acre, a 20 percent increase in density would bring
the maximum density to 18 dwelling units per acre. At 17.33 net acres,the site could have up to 312
dwelling units if the City approved the maximum amount amenity points to increase the project density.
In summary,the Planning Commission should consider and make a recommendation to the City Council
as to what design elements in the development should receive amenity points(and how many points) so
Staff can memorialize these amenities within the findings of fact in the Resolution.
Consistency with Proposed Urban High Density Zoning District.As noted earlier,the proposed
development will require City approval of a Zoning Map Amendment to rezone the property to Urban
High Density Residential(from the current RT(rural development transition))zoning designation. As
6
such, staff reviewed the proposed PUD Plans against the standards including setbacks, impervious
coverage, etc. of the Urban High Density Residential zoning district, as shown below.
Standard Required Pro osed
Impervious Surface Maximum 75 percent 66 percent
Minimum Lot Area 1,800 square feet per unit 2,469 square feet per unit
(average)
Minimum Lot Width 60 feet 1,085 feet on Hudson Blvd.
Front Yard Setback(Hudson 20 feet 20 feet
Blvd)
Interior Side Yard 10 feet 55 feet
Corner Side Yard 15 feet 10 feet(to north/south road)
Rear Yard Setback 20 feet 20 feet
Accessory Building Setbacks 10 feet 15 feet
Maximum Building Height 50 feet 35 feet(to roof peak)
Detached Structures 1,000 square feet maximum 3,000 s uare feet
Parking Not to be located in the front Parking is located in front of the
yard or between the front fagade proposed club house,though
and street. this parking lot design is
consistent the design of parking
lots for commercial/office
buildings and would not be
parking for the residential
buildings on the site.
Open space 200 square feet of common open 251,449 square feet=5.77 acres
space provided per unit. In this (830 square feet per unit)
case, at least 60,000 square feet.
Site Plan Review
Streets and Access.The proposed site plan shows a primary access driveway into the site from Hudson
Boulevard. After their initial submittal,the applicant submitted a revised site plan showing the secondary
site access(at least for emergency vehicles)moved from Hudson Boulevard to the planned north/south
street(Julia Avenue)on the west side of the site. They made this change to the access based on early staff
comments about the proposal. The new north/south street is a planned public street connection between
5t'Street North and Hudson Boulevard North. The developer should either construct the portion of the
north/south street adjacent to the development with a temporary turnaround on the north end or work with
the proposed development to the north to construct the entire planned north/south street to make a
continuous street connection from 5'Street North to Hudson Boulevard North.
Issues with the proposed setbacks. The applicant is asking the City to approve a 10-foot side yard
setback(instead of the required 15-foot setback)from the west property line for the buildings along the
north/south road. As a condition of approval,the City is requiring the developer to dedicate a 100-foot-
wide right-of-way for this road, consistent with the requirements the City made for the Bentley Village
development to the north. The applicant notes that because of this right-of-way requirement,they need
the reduce setback to make their proposed site plan work.
Impervious Surfaces. As noted by the applicant in the project narrative and in the table above,the
proposed plan is 66 percent impervious,well below the maximum impervious surface standard in the
HDR zoning district of 75 percent.
7
Streets, Sidewalks and Trails. The City will be requiring the applicant to reconstruct Hudson Boulevard
along the frontage of their site to an"Urban Section"(with curb and gutter,turn lanes and a bituminous
trail along the north side of the road). The City also will be requiring the applicant to design and
construct the north/south road(Julia Avenue)adjacent to their western property line from Hudson
Boulevard north to Bentley Village. This road section will be in a 100-foot-wide right-of-way to
accommodate drive lanes,a center turn lane,turn lanes, a bituminous trail on one side of the road and a
concrete sidewalk on the other side. This right-of-way width and design is consistent with the City
requirements for the new north/south road in the Bentley Village development to the north of the site.
(Please see the attached design cross section for Road G(now known as Julia Avenue)).
The Comprehensive Plan's Trail Plan shows a planned trail down the proposed north/south street along
the west side of the development. The proposed site plan does not show the future road or a trail or a
sidewalk along the future road. The City should require the developer to show the north/south road on all
project plans and to install the planned trail(s)along Hudson Boulevard and along the north/south street
and crosswalks with pedestrian ramps where needed as part of this development.
%Ko�.. a - : -
�4k
1 40till
•
...�.: �
. L Vr v
w •
A ♦-r r d1w.v% a.Y A�arm 1m- 1 1
Within the development site itself,the developer will be constructing 4 and 5-foot-wide concrete
sidewalks along the private driveways and between the buildings to provide pedestrian access throughout
the site.
Easements. The City will require the applicant to dedicate 10-foot-wide drainage and utility easements
along all property lines and drainage and utility easements for watermains and fire hydrants as they will
become public infrastructure. The City also may require other easements as the applicant refines their
project plans—especially around the wetland and the wetland buffer and in regards to the stormwater
management system.
Architecture/Proposed Design.The proposed design of the development is a townhouse design with the
residential buildings being two stories in height with private, ground-level entrances to each unit. The
building elevations provide architectural interest with use of exterior accents, a large percentage of
windows, and high quality materials including fiber cement board siding and stone masonry. The
8
buildings create additional high architectural value with use of varied roof lines, and vertical and
horizontal articulation. These features will give the buildings a more attractive appearance than buildings
with flat facades and consistent or straight facades and roof lines. The proposed color pallets for the
buildings include slate, gray,beige and browns. I have included several images of the proposed building
elevations for your review.
The typical interiors of the units include dark wood colored cabinets, stainless steel appliances, granite
countertops in all kitchens and wood laminate flooring. Select units will be upgraded to include enhanced
finishes,painted access walls, granite countertops throughout, among other features.
Adherence to Lake Elmo Design Guidelines and Standards.
The proposed development adheres to the Lake Elmo Design Guidelines and Standards in that:
• The proposed structures are located and oriented in a manner that allows for pedestrian
accessibility and provides visual interest from the public right-of-way.
• The buildings are located as close to the public street as possible, easily accessible from the
street; setbacks are varied slightly;recreational and common spaces are located at the interior or
rear of the site.
• The parking areas do not account for more than 50% of street frontage.
• The trash enclosure is located away from most of the residential buildings.
• Examples of past developments adhere to building design requirements. It is a recommended
condition of final PUD approval that the applicant include a detailed architectural plan proposal
(with a listing of colors,materials, etc) for the all the buildings in the development for City
approval.
All of the building exterior designs and materials will need to conform to the design standards in the Lake
Elmo Design Guidelines and Standards Manual including those regarding building facades,rooflines,
colors entries, lighting and exterior building materials. At first review, it appears that all the building
styles and materials will meet or exceed the City's design standards for multiple-family structures. City
staff will need to verify the proposed exterior designs and materials will meet the City's design standards
before issuing building permits for the clubhouse or for the residential buildings.
Garages. The proposed plans include 120 attached garages and 7 detached garage buildings with 6
garage stalls in each building. There also is a proposed maintenance garage building for the residents to
perform minor service to their vehicles and to wash their vehicles.
Wetland and Buffers. The site has a 0.4 acre wetland on the south side of the property along Hudson
Boulevard. The applicant had proposed with the Concept Plan for the site to fill the entire wetland. The
latest project plans show the applicant preserving much of the wetland and providing a 25-foot-wide
buffer around the wetland on their site. The only filling of the wetland is the part along Hudson
Boulevard to accommodate the City-required turn lane and trail on the north side of the road. The City
requires the applicant to put easements on the final plat to accommodate the wetland and the wetland
buffer.
Tree Removal,Preservation and Replacement. There is an area of about 300,000 square feet(6.9
acres)of tree cover on the site. The applicant provided a tree inventory that documented the significant or
specimen trees on the property. They include several large spruce trees in the southeast corner of the site,
along with elms, oaks,maples and aspen trees on the property. The proposed project would remove all
the existing trees on the site. Their proposed tree replacement plan meets all City requirements.
9
Landscaping. The applicant has provided the City with a landscaping plan for the site. The City's
Landscape Architect has reviewed these plans and has found that they do not meet all City requirements. I
have attached his review comments for your review. He noted that the applicant is not proposing to plant
enough trees(184 versus 233)and the proposed composition or types of trees do not meet the City
requirements. He also noted that the applicant is proposing to plant trees near proposed utility lines where
the City wants to have new trees placed at least 10 feet from the nearest utility. In addition,he noted that
the proposed screening along the north side of the site(with a proposed single,row of evergreen trees), is
inadequate to meet the City's screening requirements. The City will require the applicant to revise the
landscaping and screening plans to meet or exceed the City's Landscape Requirements for the replanting
of trees and for screening.
Landscape Walls. The applicant is proposing several landscape(retaining)walls around much of the
perimeter of the site. The proposed grading plans show these walls ranging in height from 3 feet to 12
feet. Any such wall that is taller than 4 feet requires a separate building permit from the City and must be
designed by a licensed Minnesota engineer or architect.
Parkland Dedication.The Parks Commission reviewed the proposed development at its February 20,
2019 meeting. At that meeting they recommended that the developer pay the City cash in lieu of land
dedication to meet the City's park dedication requirements. The Parks Commission may need to reaffirm
this recommendation at their May 20 meeting. The proposed development does not propose a public park
but does provide recreation for its residents through the club house,pool and open space. This area is
already served by Savona Park.
f
The proposed development site(include road right-of-ways)consists of 17.57 acres, and the required
parkland dedication for the Urban High Density Residential zoning district is 10%. The required amount
of fees would be 10%of the purchase price of the property,which has yet to be determined.
Subdivision Signs. Section 154.212(G) (1) (c) of the Zoning Code allows each residential subdivision to
have one subdivision identification sign per entrance. The maximum size for subdivision identification
10
sign is 32 square feet in area for the main entrance and a maximum sign area of 24 square feet per sign for
all other locations.
The developer submitted a drawing for an entrance monument sign with the PUD plans that has 52.1
square feet of sign face. They will need to reduce the size of this sign to a maximum of 32 square feet of
sign face to meet the City Code standards. Any signs would require a permit from the City.
Parking.The City's Zoning Code requires one parking space per studio and 1 bedroom unit,two parking
spaces per 2 and 3 bedroom units and at least one visitor space per four units. With the proposed mix of
300 units,the City Zoning Code requires the developer to provide at least 525 parking spaces on site. In
this case,the developer is proposing a total of 562 parking spaces—including attached garage and
detached garage spaces (163 total) and 399 surface parking spaces. The proposed plans include 17
parking spaces to the west of the main entrance drive aisle for the clubhouse. This computes to a unit
parking ratio of 1.87 spaces per unit—above the 1.75 parking spaces per unit required by the City Code.
The proposed width and length of parking stalls is compliant with code, and the proposed width
(estimated to be 24')is adequate for a 2-way drive aisle width according to the Zoning Code. Of these
parking spaces,a total of 22 spaces are proposed to be Americans with Disabilities Act(ADA)-accessible.
The ADA requires 2%of parking spaces totaling over 501 to be ADA-accessible,and so the proposed
number of ADA parking spaces is compliant,provided they are built with adequate width and access aisle
spacing.
Engineering Comments.The City Engineer has provided a detailed review memo (dated May 8,2019)
regarding the proposed General Preliminary Plat/Plans. I have attached this memo for reference. Staff
would like to highlight the following comments in summary:
• Streets and Transportation
o Hudson Boulevard Right-of-Way. Additional right-of-way on Hudson Blvd must be
dedicated to the City as needed to accommodate the Hudson Boulevard improvements,
including turn lanes and a 10-foot-wide utility easement.
o Hudson Boulevard Improvements. Hudson Boulevard must be improved along the
frontage of the proposed development in accordance with the Hudson Boulevard design
Standards,with and Urban Section along the north boulevard and a bituminous trail. The
developer will be required to construct right turn lanes at both the entrance to the
proposed development and at the intersection with the new north-south collector street,
and a left turn lane at the development entrance.
o New North-South Collector Street Improvements. The developer must construct new
north-south collector street along the west side of the development, from Hudson
Boulevard to the northerly plat line of the Springs of Lake Elmo. The new street shall be
designed and constructed as an urban collector street consistent with City design
standards and within a 100-foot-wide right-of-way,including a bituminous trail along one
side and a concrete sidewalk along the other side.
o New North-South Collector Street right-of-Way Dedication. The property owner or
developer must dedicate a 100-foot-wide right-of-way/roadway easement to the city for
the new north-south collector street. The proposed perimeter fencing must be located
outside of the 10-foot-wide drainage and utility easement.
o Site Access. The proposed site plan proposes a single primary access to the site on
Hudson Boulevard approximately 660 feet east of the proposed new north-south collector
street. This proposed access spacing from the new collector street meets the City
minimum spacing of 660 feet.
o Secondary/Emergency Access. The latest site plan shows a secondary access to the new
north-south collector street(to the west) and is called out a proposed emergency access
point.
11
o Perimeter Decorative Fence. As shown,this fence encroaches the 10 foot utility
easement, and so the fence location must be revised to preserve the City standard 10-foot-
wide drainage and utility easement.
o Private Streets. Private streets are proposed within the development that would remain
privately owned and maintained. The interior street and driveway design may require
revisions to ensure the adequacy of fire lanes and safety access.
• Municipal Sanitary Sewer
o The plans include a sanitary sewer utility plan that proposes 300 REC units plus
additional facilities such as a fitness center, swimming pool and a car care center.
o Sanitary sewer is available to the site. The applicant or developer will be responsible for
connecting to the city's 10-inch sanitary sewer system and extend sanitary sewer in to the
property at the applicant's sole cost.
• Municipal Water Supply
o The existing water system has sufficient capacity for domestic service for the proposed
300 REC units and additional facilities.
o The applicant will be responsible to place fire hydrants throughout the property at the
direction of the Fire Department. All fire hydrants shall be owned and maintained by the
City.
o Any watermain lines and fire hydrants placed within the development will require 30-
foot-wide utility easements centered over the pipe. These easements must be dedicated to
the city and provided in the city's standard form of easement agreement.
• Stormwater Management
o The storm water management plan is not complete. The proposed development is subject
the construction of a storm water management plan and system that meets State,Valley
Branch Watershed District(VBWD) and City rules. All stormwater facilities need to be
designed and installed in accordance with City and Valley Branch Watershed District
(VBWD)requirements. The storm water management plan must be revised to incorporate
storm water management for the Hudson Boulevard and Julia Avenue Street
improvements.
o All stormwater facilities constructed for this development and are internal to the site are
to remain privately owned and maintained. The City will require the applicant or
developer to execute and record of a Stormwater Maintenance and Easement Agreement
with the City in its standard form.
o Even as privately owned and maintained facilities,the City requires the developer to
provide maintenance access roads or drives that meet City engineering design standards
for all storm water facilities.
Valley Branch Watershed District Review. The City has not yet seen any comments from the
Watershed District about this proposal.
North/South Road(Julia Avenue)Design. The City Engineer noted the City standards for this road in
his comments. I have attached the typical cross-section for this road for your review.
Development Phasing/Grading Phasing. The project narrative notes that the developer intends to grade
the entire site and install the public improvements in a single phase with each building gaining occupancy
in sequential order starting with the Clubhouse. Their hope is start site work this fall(pending City
approvals)with final completion of the entire development by the fall of 2021.
Stormwater Management and Storm Sewer System Improvements. The proposed development
site is in the Valley Branch Watershed District(VBWD). The design of the storm water management
systems must be compliant with the requirements of the State,VBWD,the City of Lake Elmo Storm
12
Water Management Ordinance, and the City of Lake Elmo design standards manual. The applicant is
advised to fully read and comprehend the City's storm water and erosion control ordinance since these
standards are different, and in some cases more stringent,than the watershed district.
In his project review,the City Engineer noted the following:
The storm water facilities will be privately owned and maintained so no outlots will be required for the
underground storm water facilities. The storm water management plan must incorporate storm water
management for the Hudson Boulevard and Julia Avenue Street improvements.
The City will require drainage and utility easements over all 100-year high water level areas and
to protect all overland emergency overflow paths.
The City Engineer's review memo further addresses the stormwater management considerations
and requirements for this development.
Utilities—Municipal Water Supply and Municipal Sanitary Sewer. The City Engineer's review
memo provides a review of the municipal sewer and water considerations for this development. Public
water and sanitary sewer service are available in this area of Lake Elmo and the developer will be
extending them into and through the site. He noted the following:
The applicant will be responsible for extending municipal water into the development at its sole
cost and will be required to construct a looped watermain network with multiple connection points. This
includes a connection to the future watermain in the Bentley Village development to the north.
The applicant will be responsible to place hydrants throughout the property at the direction of the
Fire Department. All fire hydrants shall be owned and maintained by the City.
All utility plans will be subject to the final approval of the City Engineer.
Staff has reviewed the plans based on the assumption that the sanitary sewer extended internal to
the site will be privately owned and maintained by the applicant.
Fire Chief Comments. The Fire Chief reviewed and commented on the preliminary project plans. He
notes that the fire hydrant will have to be spaced and placed in the development according to code and
that access to the buildings must be maintained in all weather conditions. I have attached his comments
for your reference.
RECOMMENDED FINDINGS:
Recommended Finding for Rezoning:
That the proposed rezoning will be consistent with the proposed land use classification for the site as
designated in the 2040 Comprehensive Plan.
Recommended Findings for Preliminary Plat/Preliminary PUD. Staff recommends approval of the
Preliminary Plat and Preliminary PUD Plan for the Springs Apartments based on the following findings:
1. That if the 2040 Lake Elmo Comprehensive Plan Update and updated Land Use Map are
approved in 2019,that the new land use designation for the site of the proposed planned
development will be MU-C (mixed use commercial); and that the preliminary PUD Plan would
be consistent with the intent of the 2040 Lake Elmo Comprehensive Plan and the 2040 Land Use
Map for this area.
2. That the preliminary PUD Plan complies with the general intent of the Urban High Density
Residential zoning district with PUD modifications.
13
3. That the preliminary PUD Plan generally complies with the City's Subdivision regulations.
4. That the preliminary PUD Plan must be revised to be consistent with the City's engineering
standards as noted in the City Engineer's memorandum dated May 8,2019.
5. That the preliminary PUD Plan meets the minimum requirements for a PUD including minimum
lot area, open space and street layout.
6. That the preliminary PUD Plan meets more than one of the required PUD objectives identified in
Section 154.751 including providing: innovation in land development techniques that may be more
suitable for a given parcel than conventional approaches; provision of a more adequate, usable,
and suitably located open space, recreational amenities and other public facilities than would
otherwise be provided under conventional land development techniques; accommodation of
housing of all types with convenient access to employment opportunities and/or commercial
facilities; and especially to create additional opportunities for senior and affordable housing;
coordination of architectural styles and building forms to achieve greater compatibility within the
development and surrounding land uses; and higher standards of site and building design than
would otherwise be provided under conventional land development technique.
7. That the preliminary PUD Plan includes several amenities that may be worthy of amenity points to
increase the overall housing density in the development. These amenities include: Underground
or structure parking, contained parking,pedestrian improvements, a plaza(gathering area)and the
use of design elements consistent with the 2013 Lake Elmo Branding and Theming project.
FISCAL IMPACT:
There would be no fiscal impact to the City at this time, as the developer will be required to pay for any
amendments needed to accommodate the increase in REC units. The Concept Plan approval did not afford
the applicant development rights. When the property develops, it will have urban services and will pay
sewer and water connection charges,building permit fees and the like that the developer and/or contractors
will pay.
RECOMMENDATIONS:
Recommended Conditions of Approval. Staff recommends the Planning Commission recommend
to the City Council approval of the requested Preliminary Plat and preliminary PUD plans for the Springs
Apartments on Hudson Boulevard subject to the following conditions:
1. That the Metropolitan Council give final approval of a City's 2040 Comprehensive Plan Update
and adoption of the final version of the 2040 Comprehensive Plan by the Lake Elmo City
Council. The City's final plat approval will be good for 120 days after the Met Council's
approval of the City's 2040 Comprehensive Plan update or for 120 days after the City Council's
approval of the final plat,whichever comes first.
2. That the City approves a Zoning Map Amendment to rezone the site from RT(Rural
Development Transitional)to HDR(Urban High Density Residential).
3. That the applicant prepare the final plat and final PUD plans showing all of the site perimeter
property lines -including any revisions necessary for including the right-of-way for the north-
south street and all additional right-of-way needed for Hudson Boulevard as the proposal only
includes a portion of the parcel with the PID#34.029.21.43.0003.
4. That the final plat and final PUD Plans submittal identify all requests for flexibility from the
Zoning Code.
14
5. That the applicant address all comments and conditions of approval in the City Engineer's
Memorandum dated May 8,2019 with revised project plans for the future final plat and final
PUD Plans submittal.
6. That the final Plat and final PUD Plans submittal include a revised tree preservation/replanting
and revised landscape plans to address all the comments and changes noted in the memo from
the City's Landscape Architect dated May 7,2019. These final plans must be reviewed and
approved by the City's Landscape Architect before the applicant submits applications for final
plat and final PUD approval.
7. That the final Plat and final PUD Plans submittal include accurate open space and impervious
surface calculations.
8. That the final plat show a drainage and utility easement over the wetland and the wetland buffers,
including the 100-year high water level.
9. That a bituminous trail be installed along Hudson Boulevard and along the future north/south road
as part of this development.
10. That the applicant provide the City fees in lieu of park land dedication as required by Section
153.14 with future final plat.
11. That the applicant provide the City for staff approval specific examples of proposed development
fencing, landscaping, lighting and site furnishings, including the clubhouse that will meet the
standards outlined in the Lake Elmo Branding and Theming Study.
12. That the final plat and final PUD Plans submittal include detailed architectural plans for the exterior
of the buildings for staff review and approval.
13. That the applicant receive a permit from the Valley Branch Watershed District for the construction
of the proposed development.
14. All storm water facilities internal to the site shall be privately owned and maintained. A storm
water maintenance and easement agreement in a form acceptable to the City shall be executed and
recorded with the final plat for all 100-year high water level areas and to protect all overland
emergency flow paths.
15. That all comments of the Fire Chief be addressed with any future final plat plans and final PUD
plan submittal.
16. The Preliminary Plat approval is conditioned upon the applicant meeting all City standards and
design requirements unless specifically addressed otherwise in these conditions.
17. That the PUD overlay zoning allow for the following:
a. Setbacks:
Springs Apartments at Lake Elmo Minimum Building Setbacks
Front(Hudson Blvd). 20 ft.
Interior Side 10 ft.
Corner Side (Julia Avenue) 10 ft.
Rear(north property line) 20 ft.
b. Attached Garages: That the attached garages shall not exceed 1,000 sq. ft. in area at the
ground floor level except by conditional use permit.
15
c. Detached Garages: That the detached garages shall not exceed 3,000 sq. ft. in area at the
ground floor level.
18. The Final Plat shall include all necessary public right-of-way and easements for Hudson Boulevard
and for the new north/south road(Julia Avenue North).
19. The Final Plat submittal must include a complete storm water management plan and construction
plans that provide all design details for the proposed underground storage systems including details
regarding building roof drainage connections. These plans also must incorporate storm water
management for the Hudson Boulevard and Julia Avenue Street improvements including the future
east bound left turn lane along Hudson Boulevard at Julia Avenue and must meet all VBWD
requirements.
20. Before the city issues any building permits, the developer shall delineate and identify all wetland
buffers via staking, fencing and/or signage that is acceptable to the City.
21. The developer shall follow all of the rules and regulations spelled out in the Wetland
Conservation Act, and shall acquire the needed permits from the appropriate watershed districts
before the commencement of any grading or development activity on the site.
22. That the applicant shall obtain all necessary permits including but not limited to all applicable
City permits (building, grading, sign, etc.),NPDES/SWPPP permits and Valley Branch
Watershed District approval before starting any grading or construction activities.
23. That the Final Plat include Valley Branch Watershed District preliminary review comments and
that the applicant provide the City evidence that all conditions attached to a Valley Branch
Watershed District permit will be met before the starting any grading activity on the site.
24. The applicant shall provide the City with a copy of written permission for any off-site grading work
and storm sewer discharges to adjacent properties before starting any site work,grading and as part
of any final plat application.
25. That the applicant or developer address all the comments of the Fire Chief and the Building Official
with final PUD, site and building plans including the placement of buildings and fire hydrants,
street and driveway design,parking and emergency vehicle access within the site.
26. That the applicant revise the project plans to show watermain easements and effective maintenance
areas with a minimum width of 30 feet with a minimum of 15 feet of clearance from the pipe
centerline and easement agreements are included with the final plat application and plans.
27. That there shall be no encroachments into drainage and utility easements and corridors other than
those reviewed and approved by the City Engineer and upon execution of an easement
encroachment agreement. Prohibited encroachments include, but are not limited to trees,
landscaping, fences,retaining walls,buildings and storm water retention.
28. That the developer prepare exhibits for City staff approval that clearly identifies the property lines,
easements,proposed locations of retaining walls, fences and accessory buildings and the required
and proposed setbacks for each building site within the development.
29. The Applicant(s)or developer shall submit a photometric plan for the development for staff review
and approval. All lighting must meet the requirements of Sections 150.035-150.038 of the City
Code.
30. Before to the installation or construction of any subdivision identification signs or neighborhood
markers within the development, the developer shall submit sign plans to the City for review and
obtain a sign permit from the City. The proposed monument entrance sign submitted with the
preliminary PUD plans is not approved as it exceeds the City size limit of 32 square feet.
31. That the applicant provide the City a detailed construction and staging plan with the construction
plans and final plat for the development. These plans are to clearly indicate the phasing of the site
grading, the phasing of the construction of each public infrastructure component (including
required streets, turn lanes, trails and sidewalks) and shall address access to that phase of the
development for construction purposes and for residents. The City may require temporary cul-de-
sacs at the end of streets or driveways.
16
32. Before the execution and recording of a final plat for the development, the developer or applicant
shall enter into a Developer's Agreement with the City. The Developer's Agreement must be
approved by the City Attorney and by the City Council. Such Developer's Agreement shall
delineate who is responsible for the design, construction and payment for the required
improvements with financial guarantees therefore.
33. The applicant or developer shall enter into a separate grading agreement with the City before
starting any grading activity in advance of final plat approval. The City Engineer shall review any
grading plan that is submitted in advance of a final plat,and said plan shall document extent of any
proposed grading on the site.
34. That the applicant shall submit revised preliminary plat and project plans meeting all conditions of
approval for City review and approval. The revised applicant/developer project plans shall meet
all of the above conditions before the City will accept a final plat application for any phase of the
development and before the start of any clearing or grading activity on the site.
35. That the City's preliminary plat approval is good for one year from the date of City Council action,
unless the applicant requests and the City Council approves a time extension.
Motions:
Staff recommends that the Planning Commission recommend to the City Council approval of the
Preliminary Plat and Preliminary PUD Plans for the Springs Apartments to be located on Hudson
Boulevard with the following motion(the City Council cannot give this development final approval until
the Metropolitan Council approves the Lake Elmo 2040 Comprehensive Plan update):
"Motion to recommend approval of the preliminary plat and preliminary PUD Plans as requested by
Continental 483 Fund LLC for PID#34.029.21.43.0003 for the project to be known as the Springs
Apartments located on the north side of Hudson Boulevard,subject to recommended conditions of
approval."
Staff recommends the Planning Commission recommend approval of the zoning map amendment
(rezoning)of the site of the proposed Springs Apartments from RT(rural development transitional)to
HDR(urban high-density residential) after final approval of the 2040 Comprehensive Plan with the
following motion:
"Move to recommend approval of the rezoning of site of the Springs Apartments on Hudson Boulevard
from RT(rural development transitional) to HDR(urban high density residential) after final approval
of the 2040 Comprehensive Plan based on the findings listed in the Staff report."
ATTACHMENTS:
1. Project Narrative dated May 1, 2019
2. 2 City Maps
3. Aerial Photo 2
4. Overall Plan and Revised Site Plan
5. Density Exhibit
6. Project Plans (#21654)
7. N/S Road Typical Section
8. Building Elevations
9. Fire Chief comments
10. City Engineer's comments dated May 8,2019
11. Landscape Architect comments dated May 7, 2019
12. Neighbor comments dated May 4, 2019
17