HomeMy WebLinkAbout06 - 2019-08-01 Union Park 1st-Final Plat Engineer's Review PAGE 1 of 2
MEMORANDUM
Date: August 1, 2019
To: Ken Roberts, Planning Director Re: Union Park 1st Addition – Final Plat
Cc: Chad Isakson, P.E., Assistant City Engineer Engineering Review Comments
From: Jack Griffin, P.E., City Engineer
An engineering review has been completed for the Union Park 1st Addition. Final Plat/Final Construction Plans
were received consisting of the following documentation:
• Union Park 1st Addition Narrative dated May 24, 2019.
• Union Park 1st Addition Final Plat, Sheets 1-3, received May 28, 2019. No print/preparation date.
• Union Park 1st Addition Construction Plans, Sheets 1-23, dated May 24, 2019.
• Union Park 1st Addition Stromwater Management Plan, dated May 24, 2019.
• Union Park 1st Addition Landscape Plans, Sheets 24-27, dated May 24, 2019.
STATUS/FINDINGS: Engineering review comments have been provided in two separate memos; one for Final Plat
approval, and one to assist with the completion of the final Construction Plans. Please see the following review
comments relating to the Final Plat application.
FINAL PLAT: UNION PARK 1ST ADDITION
• The 5th Street North roadway along the northern border of the property will be platted at a width of 100-
feet as required. The roadway currently resides within a roadway easement.
• Julia Avenue North will be platted at a width of 100-feet as required by the preliminary plat, extending
from 5th Street North to Hudson Boulevard.
• Outlots A, B, C, and D will be HOA owned and maintained with drainage and utility easements over all of
each Outlot. These easements are consistent with the preliminary plan approval.
• Outlot B includes a storm water infiltration basin which must incorporate the entire basin including the
100-year HWL and maintenance access road.
• Outlots E, F, G, and H will be privately owned for future platting.
• Outlot ownership has been identified on the Final Construction Plans as required.
• Additional drainage and utility easements have been shown on the plat as required in the preliminary plat
approval over portions of Lot 6, Block 3; Lot 1, Block 4; Lot 6, Block 6; and Lot 4, Block 7.
• Final Plat must be contingent upon the City receiving separate drainage and utility easements, or
temporary grading/construction easements in the City’s standard form of easement agreement for all
temporary and off-site development improvements.
A permanent off-site drainage and utility easement is required for the storm sewer run from MH 701 to
FES 700 to maintain a minimum 30-foot easement centered over the pipe and from the end of the FES.
This easement covers storm sewer pipe to be installed as Phase 2, however this easement is required is
needed
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
PAGE 2 of 2
Temporary roadway easements are required over a portion of Outlot E in accordance with the City
standard details for each proposed temporary cul-de-sac. Easements can be held and not recorded until
future plat phases terminate their need.
A temporary drainage and utility easement must be provided over a portion of Outlot E for the proposed
storm sewer discharge pipe from 4th Street Lane North to the Outlot B infiltration basin, and for the
watermain pipe stub and hydrant to the southern property line. This easement can be held and not
recorded until future plat phases terminate their need.
Temporary construction and grading easements are required over a portion of Outlot H to facilitate the
off-site grading and erosion control work.
A drainage and utility easement is required over a portion of Outlot H to facilitate the extension of
watermain with temporary hydrant to the southern property line.
• All off-site easements must be clearly shown on the street, grading and utility plans, with all dimensions
labeled. The easements must be obtained and recorded prior to recording of final plat.
• All easements as requested by the City Engineer and Public Works department shall be documented on the
Final Plat prior to the release of the Final Plat for recording.
• No pipe oversize pipe costs are anticipated for this development.
• Final Construction Plans and Specifications must be prepared in accordance with the latest version of the
City Engineering Design Standards Manual, using City details, plan notes and specifications and meeting
City Engineering Design Guidelines.
• Final Construction Plans and Specifications must be revised in accordance with the Construction Plan
engineering review memorandum dated July 31, 2019.
• The Final Plat shall not be recorded until final construction plan approval is granted.
• No construction for Union Park 1st Addition may begin until the applicant has received City Engineer
approval for the Final Construction Plans; the applicant has obtained and submitted to the City all
applicable permits, easements and permissions needed for the project; and a preconstruction meeting has
been held by the City’s engineering department.