Loading...
HomeMy WebLinkAboutParks Report - 2019-2023 CIP STAFF REPORT DATE: June 11, 2018 ITEM #: TO: Parks Commission FROM: Ben Prchal, City Planner AGENDA ITEM: 2019-2023 Parks CIP REVIEWED BY: Emily Becker, Planning Director BACKGROUND: A Capital Improvement Program, or CIP, is a multi-year (typically 5 years) capital expenditure plan for a City’s infrastructure (such as streets, parks and utility systems), and equipment and public buildings. It identifies the major projects needed and desired by the community, their potential costs and how they would be financed. A project identified and budgeted through the CIP does not commit the city to that project. The City Council must specifically authorize each one, and the associated funding before any project may proceed. When the CIP is reviewed (ideally annually, in conjunction with the budgeting process) projects may go forward as planned, advance ahead of schedule, be removed entirely, or new projects may be added, these adjustments are dependent upon changes in circumstances and priorities. The Minnesota Land Planning Act requires that the implementation plan portion of the Comprehensive Plan include a CIP for major infrastructure needs (transportation, wastewater, water supply, parks and open space) for a five-year time period. Cities often expand the scope of their CIPs to include other capital needs (major equipment replacements, for example) and sometimes look beyond the five-year time period, up to 20 years in the future for some projects. Such projects represent more of a “wish-list” that can be evaluated each time the plan is updated. As a part of the Comprehensive Plan, the CIP has some legal standing. Minnesota Statutes Chapter 473.865 provides that “a local governmental unit shall not adopt any official control or fiscal device which is in conflict with its comprehensive plan.” A fiscal device includes a budget or bond issue; so it is important that the plan and CIP be kept up to date and in synch with city budgets. The primary benefit of a CIP is as a financial planning tool, to help the city plan for the impact of capital needs on future budgets and property taxes, and to help forecast the need for borrowing to undertake major projects. The information developed as part of the capital planning process can help document the need for various projects and help the City Council sort out competing priorities. Lake Elmo’s CIP includes all capital projects that cost at least $25,000 and have a useful life span of five years or longer. ISSUE BEFORE COMMISSION: What are the park improvements that should be included in the 2019-2023 CIP? When should they be completed? In what order should the new parks receive funding? The decision is pertaining to Inwood and Wildflower/Village Preserve parks. PROPOSAL DETAILS/ANALYSIS: Included in your packet is a document listing all of the City parks and trail projects staff is aware of at this time. Other Items? Any other items the Parks Commission would like to see in the 2019-2023 CIP need to be identified. Each member should come prepared to identify their top 5 priorities for the next 5 years. The commission can then also assign a priority to each project based upon the following framework: 1. Critical or urgent, high-priority projects that should be done if at all possible; a special effort should be made to find sufficient funding for all of the projects in this group. 2. Very important, high-priority projects that should be done as funding becomes available. 3. Important and worthwhile projects to be considered if funding is available; may be deferred to a subsequent year. 4. Less important, low-priority projects; desirable but not essential. 5. Future Consideration Items Scheduled for 2018. There are projects scheduled for 2018 that have been planned for but the funds have not been spent yet. Those projects are listed below. - Reid Park $25,000 to improve and widen the walking trails (staff suggests waiting) - Lions Park – Money is still being spent on improvements rd - 1/3 of the Library parking lot - Demontreville Park - $75,000 for baseball field improvements - Tablyn Park – $55,000 - Savona – 2017 park projects FISCAL IMPACT: The fiscal impact is dependent upon project selection and available funds. The City’s parkland dedication fund as of 4.30.2018 is $821,159. 2018 Expenses still to come: Demontreville ball field $75,000 Tablyn Park (up to) $55,000 Savona Park $50,000 (estimated) Easton Village $3,475 (estimated) Library Parking Lot $26,000 Lions $290,000 TOTAL 2018 Expenses $499,475 Incoming Funds in 2018: Phase 2 of Royal Golf $134,464 For Park Dedication $106,556 Payment is for tree replacement but will go to park dedication Lions Park $2,237 from the sign fund on the ball field. (Only for investment into Lions) $500/yr. for each sign displayed at lions - Receipt is yearly Expected Fund Balance as of 12/31/2018 - $562,704 2019 Projected Project Cost(s) Pebble Park $112,000 Sunfish $120,000 New Park Development $105,000 Proposed Budget for 2019 $337,000 Outstanding Funds: The projected fund balance does not take into account the numbers below. Legacy at North Star $71,745 (rough estimate based off the preliminary approval) Receipt unknown 3.383 acres * 21,207.65 (value per acre) = 71,745 Wyndham $101,130 (this is a rough estimate) Receipt unknown 1,011,300 (value of land) * 10% (park dedication) = 101,130 Royal Golf Club $1,000,000 Receipt will happen when the fields are un-usable or in phase 3 OPTIONS: 1) Commission identifies additional projects to add to the 2019-2023 CIP 2) No further projects are added so just the previously-identified projects would be forwarded on in the review process by Finance and Council. ATTACHMENTS:  2019-2023 Draft Capital Improvement Plan