HomeMy WebLinkAbout10-11-07 2006 Overlays Assessment Hearing City Council
Date: October 11,
2007
SPECIAL
Item: 2
Motion
ITEM: Assessment Hearing for the 2006 Overlays Project
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Susan Hoyt, City Administrator
Ryan Stempski, Assistant City Engineer
_____________________________________________________________________________
SUMMARY AND ACTION REQUESTED: The city council is being asked to conduct the
final assessment hearing (public hearing) and adopt the final assessment roll for the
2006 Overlays Project.
ADDITIONAL INFORMATION
The 2006 Overlays Project has been completed and the total project costs are known.
Pursuant to Minnesota Statutes, Section 429 the council has declared the amount to be
assessed against the benefiting properties and the hearing on the proposed assessment for
these improvements has been ordered. Staff has enclosed a final assessment roll as
approved by the city council. Mailed notice has been provided to each assessed property
and the public hearing has been duly noticed.
The final assessment hearing will be conducted on October 11, 2007, and if passed the
final assessment roll will be certified to the county auditor by November 30, 2007.
The city’s assessment policy on street improvement projects is to assess each property
uniformly, according to zoning classification. The assessment rate is held consistent year
to year, with only an adjustment for inflation. For this project, all properties are zoned
R1 (SDR), and have a proposed assessment rate of $1,309.00 per buildable lot. There
are 42 assessable units on this project.
The total cost of the improvements will be $204,150.00; with the city cost
participation in the amount of $149,172.00 and the amount assessed against benefited
property owners is $54,978.00.
The street improvement project included resurfacing streets with a bituminous overlay for Irvin Court, Irvin Circle, Isle Avenue, Ivy Court, and Jamaca Court.
RECOMMENDATION
Staff recommends that the city council conduct the final assessment hearing and adopt
Resolution No. 2007-069, adopting the final assessment roll for the 2006 Overlays
project according to the final assessment roll (see attachment no. 1).
SUGGESTED MOTION FOR CONSIDERATION
Move to approve Resolution No. 2007-069, adopting the final assessment roll for the
2006 Overlays project.
ORDER OF BUSINESS:
• Introduction
Jack Griffin, City Engineer
• Report by staff
Jack Griffin, City Engineer
Ryan Stempski, Assistant City Engineer
• Questions from city council members to the presenter
Mayor and council members
The mayor will facilitate this by asking each individual councilmember for one question allowing for a response
to the individual question then move onto the next council member in the sequence until all questions are
completed. No council member shall take more than 3 minutes to ask a question. (Also called round robin.)
(For example, C.1 asks question 1 and gets answer - C.2 asks question 2 and gets answer and so on.)
• Open public hearing Mayor
• Questions/comments from the public to the city
council
(a maximum of three minutes per question/statement)
Mayor facilitates
• Close public hearing
Mayor
• Call for a motion
This is to get a motion on the table for discussion and is actually required under Roberts Rules of Order.
This action is not an indication that the motion on the table is the motion that will be approved in the
current form. It is purely for discussion purposes.
• Discussion among city council members
(See round robin process above)
Mayor and council members
• Action by the city council City council
ATTACHMENTS
1. Resolution No.2007-069, adopting the final assessment roll for the 2006
Overlays Project, with attached final assessment roll.