HomeMy WebLinkAbout#07 - 2018 Street Improvements STAFF REPORT DATE: November 20, 2018 CONSENT ITEM #: 7 AGENDA ITEM: 2018 Street Improvements – Pay Request No. 4 SUBMITTED BY: Amanda Groh, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Jack Griffin, City Engineer Chad Isakson, Assistant City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 4 for the 2018 Street Improvements? BACKGROUND: Valley Paving, Inc. was awarded a construction contract on May 15, 2018 to complete the 2018 Street Improvements project. Construction work remains in progress. On October 2, 2018, the contractor was granted a three-week extension from their original completion date of September 21, 2018. The current substantial completion date for the project is October 12, 2018. PROPOSAL DETAILS/ANALYSIS: Valley Paving, Inc., has submitted Partial Pay Request No. 4 in the amount of $361,542.17. The request has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of the total work completed. The amount retained is $45,770.66. FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project. Payment remains within the authorized scope and budget. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 4 for the 2018 Street Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Pay Request No. 4 to Valley Paving, Inc. in the amount of $361,542.17 for the 2018 Street Improvements project”. ATTACHMENTS: 1. Partial Pay Estimate No. 4 PARTIAL PAY ESTIMATE NO. 4 2018 STREET IMPROVEMENTS CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2017.156 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 LS 1 $36,000.00 $36,000.00 0.00 $0.00 1.00 $36,000.00 2 LS 1 $4,000.00 $4,000.00 0.00 $0.00 1.00 $4,000.00 3 LF 500 $4.50 $2,250.00 0.00 $0.00 16.00 $72.00 4 EA 30 $135.00 $4,050.00 10.00 $1,350.00 20.00 $2,700.00 5 EA 5 $230.00 $1,150.00 0.00 $0.00 0.00 $0.00 6 HR 30 $150.00 $4,500.00 12.50 $1,875.00 29.50 $4,425.00 7 EA 10 $450.00 $4,500.00 0.00 $0.00 4.00 $1,800.00 8 EA 10 $150.00 $1,500.00 0.00 $0.00 4.00 $600.00 9 EA 88 $100.00 $8,800.00 22.00 $2,200.00 67.00 $6,700.00 10 LF 1,400 $2.00 $2,800.00 650.00 $1,300.00 1,130.00 $2,260.00 11 LF 460 $4.10 $1,886.00 392.00 $1,607.20 392.00 $1,607.20 12 SY 800 $5.50 $4,400.00 447.00 $2,458.50 743.00 $4,086.50 13 SY 300 $14.00 $4,200.00 362.00 $5,068.00 362.00 $5,068.00 14 LF 270 $9.00 $2,430.00 0.00 $0.00 121.00 $1,089.00 15 SF 36 $15.00 $540.00 0.00 $0.00 42.00 $630.00 16 CY 500 $24.00 $12,000.00 0.00 $0.00 0.00 $0.00 17 SY 32,255 $1.40 $45,157.00 0.00 $0.00 30,766.00 $43,072.40 18 CY 2,130 $7.00 $14,910.00 0.00 $0.00 2,317.00 $16,219.00 19 RS 102 $170.00 $17,340.00 0.00 $0.00 102.00 $17,340.00 20 TN 3,630 $49.00 $177,870.00 2,347.00 $115,003.00 3,353.00 $164,297.00 21 TN 2,722 $53.50 $145,627.00 2,612.00 $139,742.00 2,612.00 $139,742.00 22 GAL 1,921 $1.50 $2,881.50 950.00 $1,425.00 1,000.00 $1,500.00 23 SY 800 $21.00 $16,800.00 460.00 $9,660.00 756.00 $15,876.00 24 SY 300 $70.00 $21,000.00 362.00 $25,340.00 362.00 $25,340.00 25 TN 10 $55.00 $550.00 0.00 $0.00 17.50 $962.50 26 LF 6,300 $2.32 $14,616.00 0.00 $0.00 0.00 $0.00 27 LF 13,810 $11.00 $151,910.00 0.00 $0.00 13,103.00 $144,133.00 28 LF 6,425 $10.00 $64,250.00 0.00 $0.00 6,496.00 $64,960.00 29 LF 110 $21.00 $2,310.00 0.00 $0.00 98.00 $2,058.00 30 SY 40 $72.00 $2,880.00 0.00 $0.00 46.00 $3,312.00 31 SF 100 $7.00 $700.00 70.00 $490.00 115.00 $805.00 32 EA 4 $575.00 $2,300.00 0.00 $0.00 4.00 $2,300.00 33 LS 1 $2,900.00 $2,900.00 0.00 $0.00 0.50 $1,450.00 34 LF 300 $21.00 $6,300.00 0.00 $0.00 0.00 $0.00 35 EA 6 $500.00 $3,000.00 0.00 $0.00 0.00 $0.00 36 EA 9 $900.00 $8,100.00 2.00 $1,800.00 10.00 $9,000.00 37 EA 1 $1,500.00 $1,500.00 0.00 $0.00 3.00 $4,500.00 38 LF 246 $9.00 $2,214.00 0.00 $0.00 261.00 $2,349.00 39 EA 6 $350.00 $2,100.00 0.00 $0.00 6.00 $2,100.00 40 EA 5 $900.00 $4,500.00 0.00 $0.00 5.00 $4,500.00 41 EA 6 $2,400.00 $14,400.00 0.00 $0.00 6.00 $14,400.00 42 EA 1 $2,400.00 $2,400.00 0.00 $0.00 1.00 $2,400.00 43 EA 3 $4,500.00 $13,500.00 0.00 $0.00 3.00 $13,500.00 44 EA 6 $3,100.00 $18,600.00 0.00 $0.00 6.00 $18,600.00 45 EA 1 $3,650.00 $3,650.00 0.00 $0.00 1.00 $3,650.00 46 LF 94 $46.00 $4,324.00 0.00 $0.00 95.00 $4,370.00 47 LF 370 $48.00 $17,760.00 0.00 $0.00 365.00 $17,520.00 48 LF 112 $56.00 $6,272.00 0.00 $0.00 109.00 $6,104.00 49 EA 2 $1,100.00 $2,200.00 0.00 $0.00 2.00 $2,200.00 50 EA 3 $1,250.00 $3,750.00 0.00 $0.00 3.00 $3,750.00 51 CY 17 $116.00 $1,972.00 0.00 $0.00 15.00 $1,740.00 52 LF 340 $9.00 $3,060.00 0.00 $0.00 290.00 $2,610.00 53 CY 2,260 $21.50 $48,590.00 1,040.00 $22,360.00 1,525.00 $32,787.50 54 SY 1,500 $1.80 $2,700.00 821.00 $1,477.80 821.00 $1,477.80 55 SY 12,100 $5.80 $70,180.00 3,225.00 $18,705.00 3,225.00 $18,705.00 56 EA 13 $50.00 $650.00 0.00 $0.00 0.00 $0.00 $1,020,729.50 $351,861.50 $880,667.90 1 TN 3,630 $6.00 $21,780.00 2,347.00 $14,082.00 3,353.00 $20,118.00 2 TN 2,722 $5.60 $15,243.20 2,612.00 $14,627.20 2,612.00 $14,627.20 3 LF -6,300 $2.32 -$14,616.00 0.00 $0.00 0.00 $0.00 SEEDING, FERTILIZER, AND EROSION CONTROL BLANKET SODDING SALVAGE AND REINSTALL SIGN 15" RCP STORM SEWER, CLASS 5 18" RCP STORM SEWER, CLASS 5 CLASS 3 RIP RAP WITH FABRIC DITCH GRADING IMPORT AND PLACE TOPSOIL BORROW (LV) SAW & SEAL STREET (40' INTERVALS) B418 CONCRETE CURB & GUTTER CONCRETE RIBBON CURB SURMOUNTABLE CONCRETE CURB AND GUTTER CONCRETE VALLEY GUTTER TYPE SP 9.5 BITUMINOUS WEARING COURSE MIXTURE (2,B) [SPWEA230B] BITUMINOUS MATERIAL FOR TACK COAT BITUMINOUS DRIVEWAY PAVEMENT 6" CONCRETE DRIVEWAY PAVEMENT (HIGH EARLY) PATCH GRAVEL DRIVEWAY TRAFFIC CONTROL SILT FENCE, HAND INSTALLED INLET PROTECTION DITCH CHECK STREET SWEEPING CLEARING GRUBBING SALVAGE AND REINSTALL MAILBOX ALTERNATE NO. 1 BITUMINOUS MIXTURE SPNWB230C IN LIEU OF SPNWB230B (ADD / DEDUCT TO BASE BI BITUMINOUS MIXTURE SPWEA230C IN LIEU OF SPWEA230B (ADD / DEDUCT TO BASE BID SUBTOTAL - BASE BID 4' DIA CBMH WITH CASTING PER DETAIL 406 CONCRETE MATURITY TESTING BASE BID MOBILIZATION DELETE BID ITEM 25 - SAW & SEAL STREET (40' INTERVALS) SAWCUT BITUMINOUS PAVEMENT SAWCUT CONCRETE PAVEMENT REMOVE AND DISPOSE OF EXISTING BITUMINOUS PAVEMENT (DRIVEWAY) REMOVE AND DISPOSE OF EXISTING CONCRETE PAVEMENT (DRIVEWAY) REMOVE AND DISPOSE OF EXISTING CONCRETE CURB AND GUTTER REMOVE AND DISPOSE OF MODULAR BLOCK RETAINING WALL SUBGRADE CORRECTION (CV) RECLAIM EXISTING BITUMINOUS AND BASE MATERIALS, 8" DEPTH HAUL EXCESS RECLAIMED MATERIAL OFF SITE (LV) SUBGRADE PREPARATION OF RECLAIMED SURFACE TYPE SP 12.5 BITUMINOUS NON WEARING COURSE MIXTURE (2,B) [SPNWB230B] 15" RCP FLARED END SECTION INCL TRASH GUARD 18" RCP FLARED END SECTION INCL TRASH GUARD ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE DRAINTILE CLEANOUT REMOVE AND REPLACE CASTING AND RINGS 6" CONCRETE FLUME HIGH CAPACITY CONCRETE APRON REMOVE AND REPLACE 4' DIA BARREL SECTION REMOVE AND DISPOSE OF EXISTING STORM SEWER PIPE REMOVE AND DISPOSE OF EXISTING STORM SEWER STRUCTURE CONNECT TO EXISTING STORM SEWER PERFORATED PVC EDGE DRAIN 2' X 3' CATCH BASIN WITH CASTING PER DETAIL 404 27" DIA MH WITH CASTING 4' DIA CBMH WITH SUMP AND CASTING PER DETAIL 405 4' DIA MH WITH CASTING PER DETAIL 409 12" RCP STORM SEWER, CLASS 5 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE $22,407.20 $28,709.20 $34,745.20 TOTALS - BASE CONTRACT $1,043,136.70 $380,570.70 $915,413.10 SUBTOTAL - ALTERNATE NO. 1