HomeMy WebLinkAbout#24 - Capital Improvement PlanSTAFF REPORT DATE: December 4, 2018 AGENDA ITEM: 2019-2023 CIP #24 TO: Mayor and City Council SUBMITTED BY: Kristina Handt, City Administrator BACKGROUND: In May staff developed recommendations for updates to the 2019-2023 Capital Improvement Plan (CIP) working in consultation with the Public Safety Committee, Maintenance Advisory Committee and the Parks Commission. Beginning in July, the Finance Committee began reviewing the plan and made a recommendation to the Council at their August meeting. The Planning Commission held the public hearing in September. There were no members from the public that spoke at the meeting and no written comments received prior to the public hearing. After increasing the priority of some water projects, the Planning Commission passed a motion recommending the 2019-2023 CIP is consistent with the Comprehensive Plan. Staff had no concerns with the change and the draft has been updated to reflect this. ISSUE BEFORE COMMISSION: Should the Council adopt the proposed 2019-2023 Capital Improvement Plan? PROPOSAL DETAILS/ANALYSIS: A copy of the 2019-2023 CIP is included in your packet. It includes projects that cost at least $25,000 and have a useful life span of five years or longer. Projects are prioritized and funding sources are identified. The 2019-2023 CIP includes 73 separate projects with a total estimated cost of about $52.5 million. These projects include street work, new facilities (city hall and fire station), equipment (fire, public works, parks and utilities), park and trail improvements, and utility infrastructure. For 2019, the street project (36th, 37th, 38th, 39th Innsdale, and Irwin) is still in the draft CIP. Since Council did not approve the ordering of plans for this project at the November 20th meeting, it could be removed from the plan. Staff would recommend it be removed and the $1.755 million planned to be spent on those streets could be redirected to the CSAH 19/Hudson Blvd Traffic Signal Improvements. The CIP includes only $500,000 in MSA funds for the traffic signal, however very recently we learned that the project cost could be in excess of $1.8 million. Staff will continue to look at financing options for this project as we move into 2019. They could include MSA funds, general obligation bonds, or grant funds. FISCAL IMPACT: The total estimated costs of all the projects is about $52.5 million. Funding sources are identified for each project with a summary included on page 14. The park dedication fund is projected to have a balance of approximately $735,000 at 12/31/18 OPTIONS: 1) Approve the 2019-2023 CIP as presented 2) Amend and then Approve the 2019-2023 CIP RECOMMENDATION: “Motion to approve the 2019-2023 CIP” ATTACHMENT: • Draft 2019-2023 Capital Improvement Plan City of Lake Elmo Capital Improvement Program 2019 – 2023 City Council 12/4/18 TABLE OF CONTENTS Introduction What is a CIP? .................................................................................................................1 Scope of the Draft CIP .....................................................................................................1 Funding Sources...............................................................................................................2 Project Priorities...............................................................................................................3 2019-2023 CIP Overview Street Projects ..................................................................................................................4 Project Highlights by Department ...................................................................................4 CIP Reports (Appendix) Projects Listings………………………………………………………………………....7 Projects by Year & Priority ..…………………………………………………………..10 Funding Source Summary……………………………………………………………...14 Projects by Funding Source 2019-2023 ……………………………………………….15 Projects by Funding Source 2019-2028 ……………………………………………….18 Projects & Funding Sources by Department…………………………………………...23 Project Detail……………………………….…………………………………………..27 INTRODUCTION What is a CIP? A Capital Improvement Program, or CIP, is a multi-year (typically 5 years) capital expenditure plan for a city’s infrastructure (such as streets, parks and utility systems), vehicles, equipment and public buildings. It identifies the major projects needed and desired by the community, their potential costs and how they would be financed. Including a project in a CIP does not commit the city to that project. The City Council must specifically authorize each one, and the associated funding, before any project may proceed. When the CIP is reviewed (ideally annually, in conjunction with the budgeting process), projects may go forward as planned, advance ahead of schedule, be removed entirely, or new projects may be added, depending upon changes in circumstances and priorities. The Minnesota Land Planning Act requires that the implementation plan portion of the Comprehensive Plan include a CIP for major infrastructure needs (transportation, wastewater, water supply, parks and open space) for a five-year time period. Cities often expand the scope of their CIPs to include other capital needs (major equipment replacements, for example) and sometimes look beyond the five-year time period, up to 20 years in the future for some projects. Such projects represent more of a “wish-list” that can be evaluated each time the plan is updated. As a part of the Comprehensive Plan, the CIP has some legal standing. Minnesota Statutes Chapter 473.865 provides that “a local governmental unit shall not adopt any official control or fiscal device which is in conflict with its comprehensive plan.” A fiscal device includes a budget or bond issue; so it is important that the plan and CIP be kept-up-to date and in sync with city budgets. The primary benefit of a CIP is as a financial planning tool to help the city plan for the impact of capital needs on future budgets and property taxes, and to help forecast the need for borrowing to undertake major projects. The information developed as part of the capital planning process can help document the need for various projects and assist the City Council to sort out competing priorities. Scope of the CIP Lake Elmo’s CIP includes all capital projects that cost at least $25,000 and have a useful life span of five years or longer. Projects include all capital needs including major repairs to buildings and equipment purchases and replacements. Any projects not meeting these parameters would be reviewed as part of the annual operating budget, but would not be included in the CIP. Funding Sources The CIP identifies a possible funding source(s) for each project listed. The various funding sources are as follows: Debt Service Fund Projects financed by borrowing, later to be repaid with property taxes, and potentially special assessments depending upon the characteristics of the project. General Fund Annual operating budget, primarily funded by property tax revenues. Park Improvement Fund Existing City fund, receipts from cash-in-lieu of land park dedication fees paid by developers and others who subdivide their land. Stormwater Fund Funds come from fees paid by users of the Stormwater system Wastewater Fund Funds come from fees paid by users of the Wastewater System Water Fund Municipal State Aid (MSA) Funds come from fees paid by users of the Water System State aid funds allocated to the City each year; annual allocation grows as the City grows. In addition to these sources, it is possible that future projects could be funded from donations, grants, user fees or other sources not listed. The City also has a City Facility Fund that was created during the building of the public works barn. There is no plan to continue contributing to the fund but staff expects to spend the remaining balance in 2018 on the library parking lot and salt shed at public works. Staff is also proposing the Vehicle Replacement Fund be revived during this planning period. The Vehicle Replacement Fund would allow the city to set aside funds each year in a designated account for the purchase of future vehicles. Staff proposes transferring $100,000 from fund balance in 2019 to start the fund. In addition, each year funds would be transferred from the General Operating Budgets of the departments consistent with their percentage of vehicle replacement needs in the next ten year period. The allocation would begin with $75,000 in 2019 and increase by $25,000 each year until 2024. The 2019 allocation among funds in the General Fund would be $9,438 for fire, $50,745 for public works, and $14,818 for parks. If Council approves the 2% tax rate increase, 2019 will be the last year the City will need to borrow for vehicle replacements. Given Council direction at the August 28, 2018 work session to plan for a 2% increase in the tax rate, the proposed schedule is included below: Revenue from the sale of equipment is not included in the above table. Project Priorities Capital improvement projects should be prioritized in some way so that limited funding can be allocated to those which are most important. This is difficult because the varying nature of the projects and their benefits and objectives are so disparate as to be essentially not comparable. Some public agencies have developed elaborate rating and ranking systems to try to set priorities. Complicated scoring systems may have some disadvantages because they may give a false sense of objectivity or precision to the priority setting process. Others use simpler systems, or simply do not try to compare projects that are like “apples and oranges.” There is no accepted system or “industry standard” for prioritizing projects. The following system has been utilized by staff: 1 Critical or urgent, high-priority projects that should be done if at all possible; a special effort should be made to find sufficient funding for all of the projects in this group. 2 Very important, high-priority projects that should be done as funding becomes available. 3 Important and worthwhile projects to be considered if funding is available; may be deferred to a subsequent year. 4 Less important, low-priority projects; desirable but not essential. 5 Future Consideration $100,000 Year Revenue Expense Balance 2019 $510,076 $365,000 $245,076 2020 $732,440 $460,000 $517,516 2021 $585,830 $170,000 $933,346 2022 $655,675 $985,000 $604,021 2023 $175,000 $250,000 $529,021 2024 $200,000 $191,500 $537,521 2025 $200,000 $0 $737,521 2026 $325,500 $35,000 $1,028,021 2027 $318,500 $965,500 $381,021 2028 $690,500 $0 $1,071,521 2019-2023 CIP OVERVIEW For 2019 through 2023, the draft CIP includes 73 separate projects (active, pending and new recommendations) with a total estimated cost of $52,497,916. All cost estimates are preliminary and based on current dollars. No assumptions have been made about inflation. It will be important to refine and update costs when the plan is reviewed, especially for projects in the first year or two of the plan. Some projects beyond the five-year planning period are also included in the CIP. Most of these projects are replacements for equipment and vehicles (such as fire trucks) which may have a life span of 10, 15 or 20 years and more. The plan may include “pending” projects for which timelines (and in most cases, cost estimates) have not yet been identified. As more information is developed about the need for, cost, and possible funding sources for these projects, they will be included in future CIP updates. Street Projects The update includes the following street projects in the CIP:  PW-013, 36th, 37th, 38th, 39th, Irwin and Innsdale streets are planned for reconstruction in 2019 at a revised estimated cost of $1,755,000.  PW-026, Reclaim roads in Heritage Farms, Stonegate 2nd at a cost of $1,305,000 in 2020  PW-027, Reconstruction of roads in Fields of St Croix, Tamarack Farms, and Hamlet on Sunfish Lake and Old Village Phase 5 for $3,437,500 in 2021.  PW-029, CSAH 19/Hudson Blvd Signal and Turn Lanes for an estimated $500,000 has been back to 2019 from 2018.  PW-030, CSAH 15/30th St Signal for $250,000 in 2023  PW-034, 15th St N (MSA Street) for $950,000 in 2020  PW-035, UP RR Crossing-Village Parkway for $500,000 moved to 2020 from 2019  PW-036, UP RR Crossing-Private Drive Closure for $100,000 moved to 2020 from 2019  PW-037, UP RR Crossing-Klondike Ave for $250,000 moved to 2020 from 2019  PW-038, 2022 Street Improvements and Old Village Phase 6 streets, $2,187,500  PW-039, 2023 Street Improvements, $1,867,500 (new)  PW-051, CSAH 14/CSAH 15 realignment payment in 2019, $500,000  PW-052, Ideal Ave (Phase 2) for $800,000 in 2021 (new)  PW-053, Ideal Ave (CSAH 13) from CSAH 14 to CSAH 6, costs estimates needed from county for project in 2021 (new)  PW-057, Manning Phase 3 for $400,000 in 2023  PW-058, TH 36/Manning Interchange for $2 million (very rough estimate) in 2021 (new)  PW-059, Keats Ave/TH 36 Acceleration Lane for $70,000 in 2019 and $710,000 in 2020 if grant received from state (new) Project Highlights by Department Administration/Finance:  AF-001, New City Hall, Fire Station and Public Works Improvements, is the only request in this department. The project description has been modified to reflect the recent purchase of the Brookfield building and utilizes the recent cost estimates from Leo A Daly. The project would be split over three years 2020-2022 since the last tenant lease expires in June 2022. Fire:  F-004, Replace Tender 1 for revised estimated cost of $425,000 in 2019  F-005, Replacement of the parking lot at Station 2 for $87,560 is still pending.  F-007, Self-Contained Breathing Apparatus (SCBA) replacements for revised estimated cost of $245,500 in 2019  F-010, Replace B1 for revised estimated cost of $60,000 in 2021.  F-011, Engine E1 replacement for revised estimated cost of $580,000 in 2022  F-017, Turnout Gear Replacements for $60,000 in 2022 Parks and Recreation:  PR-005, Pebble Park Improvements for $65,000 in 2019 (tennis court paving, two volleyball courts, lighting and security features).  PR-007, Sunfish Lake Park Improvements for $120,000 in 2019 for mountain bike trails and $90,000 in 2021 includes paving hiking trails to meet ADA standards.  PR-009, Lake Elmo Regional Trail for $827,316 in 2021 and $765,600 in 2022. This project would be 75% grant funded and is dependent upon County participation. The City share is estimated at $398k.  PR-014, Tri Deck Mower for $70,000 in 2020  PR-015, One Ton Truck for $130,000 in 2022  PR-017, New or Refurbished Ballfields for $1 million in 2022.  PR-018, New Park Development for $105,000 in 2019 (Village Preserve/Wildflower) $150,000 in 2020 (Inwood) (new)  PR-019, Dog Park for $25,000 in 2023 (new) Public Works:  Street Projects were mentioned above  The remaining projects are equipment purchases. The only new equipment purchase from the last CIP is the skid loader (PW-054) for $65,000 in 2023 Sewer System:  S-003, Sunfish Lake Sewer (Includes Hamlet), for $250,000 in 2019. This is per an agreement with MPCA  The City Engineer has proposed doing S-005, Old Village Sewer Extension Phase Five and S-016 Old Village Phase Six combined over a two year period in 2021 and 2022  S-012, Section 36 Trunk Sewer for $1,500,000 in 2021  S-013, Sewer Oversizing for $295,000 in 2019  S-017, Old Village Sewer Extension Phase Seven for $522,500 in 2023 Storm Water System:  SW-001, Phase 2 Regional Drainage Improvements for $600,000 in 2022 and $800,000 in 2023. The costs and dates are estimates and will depend upon development.  SW-002, Phase 3 Regional Drainage Improvements for $500,000 in 2022. The costs and dates are estimates and will depend upon development.  SW-003, Kramer Lake Floodplain Study for $60,000 in 2022 assumes a grant from the watershed district  SW-004, Surface Water Management Plan (Comp Plan) update for $40,000 in 2019 Water System:  W-001, 36th, 37th , 38th, 39th, Innsdale and Irwin water main for revised estimate of $1,020,000 in 2019  W-004, Pressure reduction Station-Hammes Bypass for $120,000 in 2020  W-005, Old Village water main Phase Five and Phase 6 (W-025) done combined over two years for revised estimated cost of $596,750 each year in 2021 and 2022  W-006, Elevated Storage Tank #3, for revised estimated costs of $275,000 in 2019 and 3,200,000 in 2020  W-007, Hammes Estates bypass, for $120,000 in 2019  W-008, Village East Trunk Water main, for $120,000 in 2020  W-013, Water main Oversizing for $188,000 in 2019  W-014, Well & Pump house #5 for $2,100,000 in 2021  W-017, Water Main replacement consistent with 2020 Street Replacement for $725,000 in 2020 assumes funding for water extension to Stonegate is paid for by the state  W-018, Water Main replacement consistent with 2021 Street Replacement for $50,000 in 2021.  W-019, SCADA System Upgrade for revised estimated costs of $50,000 in 2022  W-022, Utility Truck for $70,000 in 2021 with costs split equally amongst water and sewer  W-023, Water Meter Change out for revised cost of $50,000 each year in 2019-2022  W-024, Automated Radio Read System for $300,000 in 2022  W-026, Old Village water extension Phase Seven for revised cost estimate of $253,000 in 2023  W-027, Pressure Reduction Station-Connection to WT #3 for revised cost estimate of $132,000 in 2022  W-028, Blackford Water Extension for $75,000 in 2020 assumes state funding (new)  W-029, 31st St Water Extension for $225,000 in 2020 assume state funding (new)  W-030, water component of 2023 street work. Cost would increase if water extended to Parkview Estates but would only be done if covered by state funds (new) Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota PROJECT LISTING20192023thru Includes Projects from All Years Admin/Finance Department Status Project #Project Name New City Hall, Fire Station, PW ImprovementsActiveAF-001 Building Department Status Project #Project Name Replacement Inspection TruckActiveB-001 Fire Department Status Project #Project Name Replacement of Parking Lot at Station #2PendingF-005 Rescue Engine E2ActiveF-001 Tender 1ActiveF-004 SCBA ReplacementsActiveF-007 B 1ActiveF-010 E1 EngineActiveF-011 B 2ActiveF-012 T2 Tender/EngineActiveF-013 Boat and TrailerActiveF-014 RangerActiveF-015 L1 Ladder TruckActiveF-016 Turnout Gear ReplacementsActiveF-017 Parks and Recreation Status Project #Project Name Manning Trail UpdatesActivePR-001 50th Street TrailActivePR-002 Demontreville Park ImprovementsActivePR-003 Lions Park RenovationsActivePR-004 Pebble Park ImprovementsActivePR-005 Sunfish Lake Park ImprovementsActivePR-007 Lake Elmo Regional TrailActivePR-009 Pickup TruckActivePR-010 Savona ParkActivePR-011 Tri-Deck MowerActivePR-014 One Ton TruckActivePR-015 CushmanActivePR-016 New or Refurbished BallfieldsActivePR-017 New Park DevelopmentActivePR-018 Dog ParkNew Recommendation PR-019 Utility Vehicile/Trail GroomerNew Recommendation PR-020 Public Works Department Status Project #Project Name Dump Truck/Plow wing/SanderActivePW-002 LoaderActivePW-004 TractorActivePW-006 Manning Trail Reconstruction CSAH 15ActivePW-009 Lake Elmo Ave at 5th St Turn LaneActivePW-010 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software 2018 Street ImprovementsActivePW-011 2019 Street ImprovementsActivePW-013 PickupTruckActivePW-019 Pickup TruckActivePW-020 Dump Truck/Plow/SanderActivePW-022 Vac TrailerActivePW-023 2020 Street ImprovementsActivePW-026 2021 Street ImprovementsActivePW-027 CSAH15/50th Street Temp Signal Imp.Active PW-028 CSAH19/Hudson Blvd Signal & Turn LaneActivePW-029 CSAH 15/30th Street SignalActivePW-030 CSAH 6/Inwood SignalActivePW-031 CSAH13 - Ideal Avenue ImprovementsActivePW-033 15th Street North (MSA Street)Active PW-034 UP RR Crossing - Village ParkwayActivePW-035 UP RR Crossing - Private Drive ClosureActivePW-036 UP RR Crossing: Klondike AveActivePW-037 2022 Street ImprovementsActivePW-038 2023 Street ImprovementsActivePW-039 2024 Street ImprovementsActivePW-040 2025 Street IrmprovementsActivePW-041 2026 Street ImprovementsActivePW-042 Service TruckActivePW-043 Trac HoeActivePW-044 Tandem Plow TruckActivePW-045 Asphalt RollerActivePW-046 Dump Truck w/PlowActivePW-047 Mini LoaderActivePW-048 Asphalt Hot BoxActivePW-049 Dump Truck with PlowActivePW-050 CSAH 14/CSAH 15 RealignmentActivePW-051 2027 Street ImprovementsActivePW-055 2028 Street ImprovementsActivePW-056 Ideal Ave (CSAH 13) Phase 2New Recommendation PW-052 Ideal Ave (CSAH 13) CSAH 14 to CSAH 6New Recommendation PW-053 SkidloaderNew Recommendation PW-054 Manning Ave Phase 3New Recommendation PW-057 TH 36/Manning InterchangeNew Recommendation PW-058 Keats Ave/TH 36 Acceleration LaneNew Recommendation PW-059 Pickup w/plowNew Recommendation PW-060 PickupNew Recommendation PW-061 DumpTruck w/plow, sander & underbodyNew Recommendation PW-062 Pickup w/lift gate & plowNew Recommendation PW-063 Pickup w/lift gate & plowNew Recommendation PW-064 Dump Truck w/plow, sander & underbodyNew Recommendation PW-065 Sewer Department Status Project #Project Name Sunfish Lake Sewer Extension & Lift StationActiveS-003 Old Village Sewer Extension Phase 4ActiveS-004 Old Village Sewer Extension Phase 5 & 6ActiveS-005 Utility VehicleActiveS-007 Old Village Sewer Extension Phase 3ActiveS-011 Section 36 Trunk Sewer MainActiveS-012 Sewer OversizingActiveS-013 Old Village Sewer Extension Phase 5 & 6ActiveS-016 Old Village Sewer Extension Phase 7ActiveS-017 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Storm Water Department Status Project #Project Name Phase 2 Regional Drainage ImprovementsActiveSW-001 Phase 3 Regional Drainage ImprovementsActiveSW-002 Kramer Lake Floodplain StudyActiveSW-003 Surface Water Management Plan (Comp Plan) updateActiveSW-004 Water Department Status Project #Project Name 2019 Street Improvement Project - water componentActiveW-001 OV sewer extension phase 4; water componentActiveW-003 Pressure Reduction ValveActiveW-004 OV Sewer Extension; Phase 5&6; water componentActiveW-005 Elevated Storage Tank #3ActiveW-006 Hammes Estates 12" bypassActiveW-007 Village East Trunk WatermainActiveW-008 Utility VehicleActiveW-009 Paint Water Tank at PWActiveW-010 Well #2 Pull and rebuild pumpActiveW-011 Well #4 Pump - Pull and RebuildActiveW-012 Watermain OversizingActiveW-013 Well & Pumphouse #5ActiveW-014 OV Sewer Extension Phase 3; water componentActiveW-015 2020 Street & Utility Improvements-WaterActiveW-017 2021 Street & Utility Improvements-WaterActiveW-018 SCADA UpgradeActiveW-019 Utility TruckActiveW-022 Water Meter Change OutActiveW-023 Automated Radio Read SystemActiveW-024 OV sewer extension phase 6 & 5; water componentActiveW-025 OV sewer extension Phase 7; water componentActiveW-026 Pressure Reduction Station-Connection to WT #3ActiveW-027 Blackford Water ExtNew Recommendation W-028 31st St Area Water ExtensionNew Recommendation W-029 2023 Street Projects-water componentNew Recommendation W-030 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota PROJECTS BY YEAR & PRIORITY 2019 2023thru Project Name Department Project #Priority Project Cost 2019 Priority 1 Critical F-004Tender 1 1 425,000Fire Department F-007SCBA Replacements 1 245,500Fire Department PW-043Service Truck 1 200,000Public Works Department PW-045Tandem Plow Truck 1 265,000Public Works Department W-006Elevated Storage Tank #3 1 275,000Water Department W-023Water Meter Change Out 1 50,000Water Department 1,460,500Total for: Priority 1 Priority 3 Important PR-005Pebble Park Improvements 3 65,000Parks and Recreation PR-007Sunfish Lake Park Improvements 3 120,000Parks and Recreation PW-0132019 Street Improvements 3 1,755,000Public Works Department PW-029CSAH19/Hudson Blvd Signal & Turn Lane 3 500,000Public Works Department PW-051CSAH 14/CSAH 15 Realignment 3 500,000Public Works Department PW-059Keats Ave/TH 36 Acceleration Lane 3 70,000Public Works Department S-003Sunfish Lake Sewer Extension & Lift Station 3 250,000Sewer Department S-013Sewer Oversizing 3 295,000Sewer Department SW-004Surface Water Management Plan (Comp Plan) update 3 40,000Storm Water Department W-0012019 Street Improvement Project - water component 3 1,020,000Water Department W-013Watermain Oversizing 3 188,000Water Department 4,803,000Total for: Priority 3 Priority 4 Less Important PR-018New Park Development 4 105,000Parks and Recreation W-007Hammes Estates 12" bypass 4 120,000Water Department 225,000Total for: Priority 4 6,488,500Total for 2019 2020 Priority 1 Critical PW-047Dump Truck w/Plow 1 240,000Public Works Department W-006Elevated Storage Tank #3 1 3,200,000Water Department W-023Water Meter Change Out 1 50,000Water Department 3,490,000Total for: Priority 1 Priority 2 Very Important AF-001New City Hall, Fire Station, PW Improvements 2 1,250,000Admin/Finance Department PW-035UP RR Crossing - Village Parkway 2 500,000Public Works Department PW-036UP RR Crossing - Private Drive Closure 2 100,000Public Works Department PW-037UP RR Crossing: Klondike Ave 2 250,000Public Works Department PW-044Trac Hoe 2 60,000Public Works Department Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Project Name Department Project #Priority Project Cost PW-048Mini Loader 2 120,000Public Works Department W-008Village East Trunk Watermain 2 132,000Water Department W-028Blackford Water Ext 2 75,000Water Department W-02931st St Area Water Extension 2 225,000Water Department 2,712,000Total for: Priority 2 Priority 3 Important PR-014Tri-Deck Mower 3 70,000Parks and Recreation PW-0262020 Street Improvements 3 1,305,000Public Works Department PW-03415th Street North (MSA Street)3 950,000Public Works Department PW-059Keats Ave/TH 36 Acceleration Lane 3 710,000Public Works Department W-004Pressure Reduction Valve 3 120,000Water Department W-0172020 Street & Utility Improvements-Water 3 725,000Water Department 3,880,000Total for: Priority 3 Priority 4 Less Important PR-018New Park Development 4 150,000Parks and Recreation 150,000Total for: Priority 4 10,232,000Total for 2020 2021 Priority 1 Critical W-014Well & Pumphouse #5 1 2,100,000Water Department W-023Water Meter Change Out 1 50,000Water Department 2,150,000Total for: Priority 1 Priority 2 Very Important AF-001New City Hall, Fire Station, PW Improvements 2 4,475,000Admin/Finance Department PW-006Tractor 2 110,000Public Works Department PW-058TH 36/Manning Interchange 2 2,000,000Public Works Department 6,585,000Total for: Priority 2 Priority 3 Important F-010B 1 3 60,000Fire Department PR-007Sunfish Lake Park Improvements 3 90,000Parks and Recreation PR-009Lake Elmo Regional Trail 3 827,316Parks and Recreation PW-0272021 Street Improvements 3 3,437,500Public Works Department PW-052Ideal Ave (CSAH 13) Phase 2 3 800,000Public Works Department PW-053Ideal Ave (CSAH 13) CSAH 14 to CSAH 6 3 0Public Works Department S-005Old Village Sewer Extension Phase 5 & 6 3 885,500Sewer Department S-012Section 36 Trunk Sewer Main 3 1,500,000Sewer Department W-005OV Sewer Extension; Phase 5&6; water component 3 596,750Water Department W-0182021 Street & Utility Improvements-Water 3 50,000Water Department W-022Utility Truck 3 70,000Water Department 8,317,066Total for: Priority 3 Priority 4 Less Important PW-049Asphalt Hot Box 4 60,000Public Works Department 60,000Total for: Priority 4 17,112,066Total for 2021 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Project Name Department Project #Priority Project Cost 2022 Priority 1 Critical F-011E1 Engine 1 580,000Fire Department F-017Turnout Gear Replacements 1 60,000Fire Department PR-017New or Refurbished Ballfields 1 1,000,000Parks and Recreation PW-050Dump Truck with Plow 1 245,000Public Works Department W-023Water Meter Change Out 1 50,000Water Department 1,935,000Total for: Priority 1 Priority 2 Very Important AF-001New City Hall, Fire Station, PW Improvements 2 5,225,000Admin/Finance Department W-019SCADA Upgrade 2 50,000Water Department 5,275,000Total for: Priority 2 Priority 3 Important PR-009Lake Elmo Regional Trail 3 765,600Parks and Recreation PR-015One Ton Truck 3 130,000Parks and Recreation PW-0382022 Street Improvements 3 2,187,500Public Works Department S-016Old Village Sewer Extension Phase 5 & 6 3 885,500Sewer Department SW-001Phase 2 Regional Drainage Improvements 3 600,000Storm Water Department SW-002Phase 3 Regional Drainage Improvements 3 500,000Storm Water Department SW-003Kramer Lake Floodplain Study 3 60,000Storm Water Department W-024Automated Radio Read System 3 300,000Water Department W-025OV sewer extension phase 6 & 5; water component 3 596,750Water Department 6,025,350Total for: Priority 3 Priority 4 Less Important PW-019PickupTruck 4 30,000Public Works Department 30,000Total for: Priority 4 13,265,350Total for 2022 2023 Priority 2 Very Important PW-004Loader 2 185,000Public Works Department 185,000Total for: Priority 2 Priority 3 Important PW-030CSAH 15/30th Street Signal 3 250,000Public Works Department PW-0392023 Street Improvements 3 1,867,500Public Works Department PW-054Skidloader 3 65,000Public Works Department PW-057Manning Ave Phase 3 3 400,000Public Works Department S-017Old Village Sewer Extension Phase 7 3 522,500Sewer Department SW-001Phase 2 Regional Drainage Improvements 3 800,000Storm Water Department W-026OV sewer extension Phase 7; water component 3 253,000Water Department W-027Pressure Reduction Station-Connection to WT #3 3 132,000Water Department W-0302023 Street Projects-water component 3 100,000Water Department 4,390,000Total for: Priority 3 Priority 4 Less Important PR-019Dog Park 4 25,000Parks and Recreation W-010Paint Water Tank at PW 4 800,000Water Department 825,000Total for: Priority 4 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Project Name Department Project #Priority Project Cost 5,400,000Total for 2023 GRAND TOTAL 52,497,916 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota FUNDING SOURCE SUMMARY 2019 thru 2023 TotalSource20192020202120222023 Debt Service 36,432,5003,970,500 6,105,000 13,294,750 9,994,750 3,067,500 General Fund 190,00070,000 60,000 60,000 Grants/Donation 5,939,6872,185,000 2,120,487 1,634,200 Municipal Sate Aid (MSA)3,200,0001,000,000 950,000 1,000,000 250,000 Park Dedication Fund 953,229290,000 150,000 296,829 191,400 25,000 Sewer Fund 902,500345,000 35,000 522,500 Storm Water Fund 55,00040,000 15,000 Vehicle Replacement Fund 2,230,000365,000 460,000 170,000 985,000 250,000 Water Fund 2,595,000408,000 367,000 135,000 400,000 1,285,000 6,488,500 10,232,000 17,112,066 13,265,350 5,400,000 52,497,916GRAND TOTAL Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota PROJECTS BY FUNDING SOURCE 2019 2023thru TotalSourceProject #Priority 2019 2020 2021 2022 2023 Debt Service AF-001 10,950,0001,250,000 4,475,000 5,225,000New City Hall, Fire Station, PW Improvements 2 F-004 425,000425,000Tender 1 1 F-007 245,500245,500SCBA Replacements 1 PW-013 1,755,0001,755,0002019 Street Improvements 3 PW-026 1,305,0001,305,0002020 Street Improvements 3 PW-027 3,437,5003,437,5002021 Street Improvements 3 PW-036 100,000100,000UP RR Crossing - Private Drive Closure 2 PW-037 250,000250,000UP RR Crossing: Klondike Ave 2 PW-038 2,187,5002,187,5002022 Street Improvements 3 PW-039 1,867,5001,867,5002023 Street Improvements 3 PW-052 800,000800,000Ideal Ave (CSAH 13) Phase 2 3 PW-053 00Ideal Ave (CSAH 13) CSAH 14 to CSAH 6 3 PW-057 400,000400,000Manning Ave Phase 3 3 PW-058 1,000,0001,000,000TH 36/Manning Interchange 2 S-003 250,000250,000Sunfish Lake Sewer Extension & Lift Station 3 S-005 885,500885,500Old Village Sewer Extension Phase 5 & 6 3 S-016 885,500885,500Old Village Sewer Extension Phase 5 & 6 3 SW-001 1,400,000600,000 800,000Phase 2 Regional Drainage Improvements 3 SW-002 500,000500,000Phase 3 Regional Drainage Improvements 3 W-001 1,020,0001,020,0002019 Street Improvement Project - water component 3 W-005 596,750596,750OV Sewer Extension; Phase 5&6; water component 3 W-006 3,475,000275,000 3,200,000Elevated Storage Tank #3 1 W-014 2,100,0002,100,000Well & Pumphouse #5 1 W-025 596,750596,750OV sewer extension phase 6 & 5; water component 3 36,432,5003,970,500 6,105,000 13,294,750 9,994,750 3,067,500Debt Service Total General Fund F-017 60,00060,000Turnout Gear Replacements 1 PW-049 60,00060,000Asphalt Hot Box 4 PW-059 70,00070,000Keats Ave/TH 36 Acceleration Lane 3 190,00070,000 60,000 60,000General Fund Total Grants/Donation PR-009 1,194,687620,487 574,200Lake Elmo Regional Trail 3 PR-017 1,000,0001,000,000New or Refurbished Ballfields 1 PW-035 500,000500,000UP RR Crossing - Village Parkway 2 PW-059 710,000710,000Keats Ave/TH 36 Acceleration Lane 3 S-012 1,500,0001,500,000Section 36 Trunk Sewer Main 3 SW-003 60,00060,000Kramer Lake Floodplain Study 3 W-017 675,000675,0002020 Street & Utility Improvements-Water 3 W-028 75,00075,000Blackford Water Ext 2 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software TotalSourceProject #Priority 2019 2020 2021 2022 2023 W-029 225,000225,00031st St Area Water Extension 2 5,939,6872,185,000 2,120,487 1,634,200Grants/Donation Total Municipal Sate Aid (MSA) PW-029 500,000500,000CSAH19/Hudson Blvd Signal & Turn Lane 3 PW-030 250,000250,000CSAH 15/30th Street Signal 3 PW-034 950,000950,00015th Street North (MSA Street)3 PW-051 500,000500,000CSAH 14/CSAH 15 Realignment 3 PW-058 1,000,0001,000,000TH 36/Manning Interchange 2 3,200,0001,000,000 950,000 1,000,000 250,000Municipal Sate Aid (MSA) Total Park Dedication Fund PR-005 65,00065,000Pebble Park Improvements 3 PR-007 210,000120,000 90,000Sunfish Lake Park Improvements 3 PR-009 398,229206,829 191,400Lake Elmo Regional Trail 3 PR-018 255,000105,000 150,000New Park Development 4 PR-019 25,00025,000Dog Park 4 953,229290,000 150,000 296,829 191,400 25,000Park Dedication Fund Total Sewer Fund PW-043 50,00050,000Service Truck 1 S-013 295,000295,000Sewer Oversizing 3 S-017 522,500522,500Old Village Sewer Extension Phase 7 3 W-022 35,00035,000Utility Truck 3 902,500345,000 35,000 522,500Sewer Fund Total Storm Water Fund PW-044 15,00015,000Trac Hoe 2 SW-004 40,00040,000Surface Water Management Plan (Comp Plan) update 3 55,00040,000 15,000Storm Water Fund Total Vehicle Replacement Fund F-010 60,00060,000B 1 3 F-011 580,000580,000E1 Engine 1 PR-014 70,00070,000Tri-Deck Mower 3 PR-015 130,000130,000One Ton Truck 3 PW-004 185,000185,000Loader2 PW-006 110,000110,000Tractor2 PW-019 30,00030,000PickupTruck4 PW-043 100,000100,000Service Truck 1 PW-044 30,00030,000Trac Hoe 2 PW-045 265,000265,000Tandem Plow Truck 1 PW-047 240,000240,000Dump Truck w/Plow 1 PW-048 120,000120,000Mini Loader 2 PW-050 245,000245,000Dump Truck with Plow 1 PW-054 65,00065,000Skidloader3 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software TotalSourceProject #Priority 2019 2020 2021 2022 2023 2,230,000365,000 460,000 170,000 985,000 250,000Vehicle Replacement Fund Total Water Fund PW-043 50,00050,000Service Truck 1 PW-044 15,00015,000Trac Hoe 2 W-004 120,000120,000Pressure Reduction Valve 3 W-007 120,000120,000Hammes Estates 12" bypass 4 W-008 132,000132,000Village East Trunk Watermain 2 W-010 800,000800,000Paint Water Tank at PW 4 W-013 188,000188,000Watermain Oversizing 3 W-017 50,00050,0002020 Street & Utility Improvements-Water 3 W-018 50,00050,0002021 Street & Utility Improvements-Water 3 W-019 50,00050,000SCADA Upgrade 2 W-022 35,00035,000Utility Truck 3 W-023 200,00050,000 50,000 50,000 50,000Water Meter Change Out 1 W-024 300,000300,000Automated Radio Read System 3 W-026 253,000253,000OV sewer extension Phase 7; water component 3 W-027 132,000132,000Pressure Reduction Station-Connection to WT #3 3 W-030 100,000100,0002023 Street Projects-water component 3 2,595,000408,000 367,000 135,000 400,000 1,285,000Water Fund Total 52,497,9166,488,500 10,232,000 17,112,066 13,265,350 5,400,000GRAND TOTAL Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota PROJECTS BY FUNDING SOURCE 2019 2028thru Total20192020202120222023Source20242025202620272028 #Priority Debt Service 10,950,0001,250,000 4,475,000 5,225,000New City Hall, Fire Station, PW Improvements AF-001 2 425,000425,000Tender 1 F-004 1 245,500245,500SCBA Replacements F-007 1 1,755,0001,755,0002019 Street Improvements PW-013 3 1,305,0001,305,0002020 Street Improvements PW-026 3 3,437,5003,437,5002021 Street Improvements PW-027 3 100,000100,000UP RR Crossing - Private Drive Closure PW-036 2 250,000250,000UP RR Crossing: Klondike Ave PW-037 2 2,187,5002,187,5002022 Street Improvements PW-038 3 1,867,5001,867,5002023 Street Improvements PW-039 3 1,500,0001,500,0002024 Street Improvements PW-040 3 1,500,0001,500,0002025 Street Irmprovements PW-041 3 1,500,0001,500,0002026 Street Improvements PW-042 3 800,000800,000Ideal Ave (CSAH 13) Phase 2 PW-052 3 00Ideal Ave (CSAH 13) CSAH 14 to CSAH 6 PW-053 3 1,500,0001,500,0002027 Street Improvements PW-055 3 1,500,0001,500,0002028 Street Improvements PW-056 3 400,000400,000Manning Ave Phase 3 PW-057 3 1,000,0001,000,000TH 36/Manning Interchange PW-058 2 250,000250,000Sunfish Lake Sewer Extension & Lift Station S-003 3 885,500885,500Old Village Sewer Extension Phase 5 & 6 S-005 3 885,500885,500Old Village Sewer Extension Phase 5 & 6 S-016 3 1,400,000600,000 800,000Phase 2 Regional Drainage Improvements SW-001 3 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Total20192020202120222023Source20242025202620272028 #Priority 500,000500,000Phase 3 Regional Drainage Improvements SW-002 3 1,020,0001,020,0002019 Street Improvement Project - water component W-001 3 596,750596,750OV Sewer Extension; Phase 5&6; water component W-005 3 3,475,000275,000 3,200,000Elevated Storage Tank #3 W-006 1 2,100,0002,100,000Well & Pumphouse #5 W-014 1 596,750596,750OV sewer extension phase 6 & 5; water component W-025 3 Debt Service Total 43,932,5003,970,500 6,105,000 13,294,750 9,994,750 3,067,500 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 General Fund 60,00060,000Turnout Gear Replacements F-017 1 60,00060,000Asphalt Hot Box PW-049 4 70,00070,000Keats Ave/TH 36 Acceleration Lane PW-059 3 General Fund Total 190,00070,000 60,000 60,000 Grants/Donation 1,194,687620,487 574,200Lake Elmo Regional Trail PR-009 3 1,000,0001,000,000New or Refurbished Ballfields PR-017 1 500,000500,000UP RR Crossing - Village Parkway PW-035 2 710,000710,000Keats Ave/TH 36 Acceleration Lane PW-059 3 1,500,0001,500,000Section 36 Trunk Sewer Main S-012 3 60,00060,000Kramer Lake Floodplain Study SW-003 3 675,000675,0002020 Street & Utility Improvements- Water W-017 3 75,00075,000Blackford Water Ext W-028 2 225,000225,00031st St Area Water Extension W-029 2 Grants/Donation Total 5,939,6872,185,000 2,120,487 1,634,200 Municipal Sate Aid (MSA) 500,000500,000CSAH19/Hudson Blvd Signal & Turn Lane PW-029 3 250,000250,000CSAH 15/30th Street Signal PW-030 3 100,000100,000CSAH 6/Inwood Signal PW-031 3 950,000950,00015th Street North (MSA Street)PW-034 3 500,000500,000CSAH 14/CSAH 15 Realignment PW-051 3 1,000,0001,000,000TH 36/Manning Interchange PW-058 2 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Total20192020202120222023Source20242025202620272028 #Priority Municipal Sate Aid (MSA) Total 3,300,0001,000,000 950,000 1,000,000 250,000 100,000 Park Dedication Fund 65,00065,000Pebble Park Improvements PR-005 3 210,000120,000 90,000Sunfish Lake Park Improvements PR-007 3 398,229206,829 191,400Lake Elmo Regional Trail PR-009 3 255,000105,000 150,000New Park Development PR-018 4 25,00025,000Dog Park PR-019 4 Park Dedication Fund Total 953,229290,000 150,000 296,829 191,400 25,000 Sewer Fund 50,00050,000Service Truck PW-043 1 295,000295,000Sewer Oversizing S-013 3 522,500522,500Old Village Sewer Extension Phase 7 S-017 3 35,00035,000Utility Truck W-022 3 Sewer Fund Total 902,500345,000 35,000 522,500 Storm Water Fund 15,00015,000Trac Hoe PW-044 2 40,00040,000Surface Water Management Plan (Comp Plan) update SW-004 3 Storm Water Fund Total 55,00040,000 15,000 Vehicle Replacement Fund 60,00060,000B 1 F-010 3 580,000580,000E1 Engine F-011 1 90,00090,000B 2 F-012 3 650,000650,000T2 Tender/Engine F-013 4 20,00020,000Boat and Trailer F-014 3 70,00070,000Tri-Deck Mower PR-014 3 130,000130,000One Ton Truck PR-015 3 35,50035,500Utility Vehicile/Trail Groomer PR-020 3 185,000185,000LoaderPW-004 2 110,000110,000TractorPW-006 2 30,00030,000PickupTruckPW-019 4 30,00030,000Pickup Truck PW-020 4 100,000100,000Service Truck PW-043 1 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Total20192020202120222023Source20242025202620272028 #Priority 30,00030,000Trac Hoe PW-044 2 265,000265,000Tandem Plow Truck PW-045 1 240,000240,000Dump Truck w/Plow PW-047 1 120,000120,000Mini Loader PW-048 2 245,000245,000Dump Truck with Plow PW-050 1 65,00065,000SkidloaderPW-054 3 36,00036,000Pickup w/plow PW-060 3 35,00035,000PickupPW-061 3 205,500205,500DumpTruck w/plow, sander & underbody PW-062 3 45,00045,000Pickup w/lift gate & plow PW-063 3 45,00045,000Pickup w/lift gate & plow PW-064 3 Vehicle Replacement Fund Total 3,422,000365,000 460,000 170,000 985,000 250,000 191,500 35,000 965,500 Water Fund 50,00050,000Service Truck PW-043 1 15,00015,000Trac Hoe PW-044 2 120,000120,000Pressure Reduction Valve W-004 3 120,000120,000Hammes Estates 12" bypass W-007 4 132,000132,000Village East Trunk Watermain W-008 2 800,000800,000Paint Water Tank at PW W-010 4 35,00035,000Well #4 Pump - Pull and Rebuild W-012 3 307,000188,000 119,000Watermain Oversizing W-013 3 50,00050,0002020 Street & Utility Improvements- Water W-017 3 50,00050,0002021 Street & Utility Improvements- Water W-018 3 50,00050,000SCADA Upgrade W-019 2 35,00035,000Utility Truck W-022 3 200,00050,000 50,000 50,000 50,000Water Meter Change Out W-023 1 300,000300,000Automated Radio Read System W-024 3 253,000253,000OV sewer extension Phase 7; water component W-026 3 132,000132,000Pressure Reduction Station- Connection to WT #3 W-027 3 100,000100,0002023 Street Projects-water component W-030 3 Water Fund Total 2,749,000408,000 367,000 135,000 400,000 1,285,000 119,000 35,000 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Total20192020202120222023Source20242025202620272028 #Priority 6,488,500 10,232,000 17,112,066 13,265,350 5,400,000 61,443,916GRAND TOTAL 1,910,500 1,535,000 1,535,000 2,465,500 1,500,000 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota PROJECTS & FUNDING SOURCES BY DEPARTMENT 2019 2023thru Total20192020202120222023DepartmentProject #Priority Admin/Finance Department AF-001 10,950,0001,250,000 4,475,000 5,225,000New City Hall, Fire Station, PW Improvements 2 Debt Service 1,250,000 4,475,000 5,225,000 10,950,000 10,950,0001,250,000 4,475,000 5,225,000Admin/Finance Department Total Fire Department F-004 425,000425,000Tender 1 1 Debt Service 425,000 425,000 F-007 245,500245,500SCBA Replacements 1 Debt Service 245,500 245,500 F-010 60,00060,000B 1 3 Vehicle Replacement Fund 60,000 60,000 F-011 580,000580,000E1 Engine 1 Vehicle Replacement Fund 580,000 580,000 F-017 60,00060,000Turnout Gear Replacements 1 General Fund 60,000 60,000 1,370,500670,500 60,000 640,000Fire Department Total Parks and Recreation PR-005 65,00065,000Pebble Park Improvements 3 Park Dedication Fund 65,000 65,000 PR-007 210,000120,000 90,000Sunfish Lake Park Improvements 3 Park Dedication Fund 120,000 90,000 210,000 PR-009 1,592,916827,316 765,600Lake Elmo Regional Trail 3 Grants/Donation 620,487 574,200 1,194,687 Park Dedication Fund 206,829 191,400 398,229 PR-014 70,00070,000Tri-Deck Mower 3 Vehicle Replacement Fund 70,000 70,000 PR-015 130,000130,000One Ton Truck 3 Vehicle Replacement Fund 130,000 130,000 PR-017 1,000,0001,000,000New or Refurbished Ballfields 1 Grants/Donation 1,000,000 1,000,000 PR-018 255,000105,000 150,000New Park Development 4 Park Dedication Fund 105,000 150,000 255,000 PR-019 25,00025,000Dog Park 4 Park Dedication Fund 25,000 25,000 3,347,916290,000 220,000 917,316 1,895,600 25,000Parks and Recreation Total Public Works Department PW-004 185,000185,000Loader2 Vehicle Replacement Fund 185,000 185,000 PW-006 110,000110,000Tractor2 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Total20192020202120222023DepartmentProject #Priority Vehicle Replacement Fund 110,000 110,000 PW-013 1,755,0001,755,0002019 Street Improvements 3 Debt Service 1,755,000 1,755,000 PW-019 30,00030,000PickupTruck4 Vehicle Replacement Fund 30,000 30,000 PW-026 1,305,0001,305,0002020 Street Improvements 3 Debt Service 1,305,000 1,305,000 PW-027 3,437,5003,437,5002021 Street Improvements 3 Debt Service 3,437,500 3,437,500 PW-029 500,000500,000CSAH19/Hudson Blvd Signal & Turn Lane 3 Municipal Sate Aid (MSA)500,000 500,000 PW-030 250,000250,000CSAH 15/30th Street Signal 3 Municipal Sate Aid (MSA)250,000 250,000 PW-034 950,000950,00015th Street North (MSA Street)3 Municipal Sate Aid (MSA)950,000 950,000 PW-035 500,000500,000UP RR Crossing - Village Parkway 2 Grants/Donation 500,000 500,000 PW-036 100,000100,000UP RR Crossing - Private Drive Closure 2 Debt Service 100,000 100,000 PW-037 250,000250,000UP RR Crossing: Klondike Ave 2 Debt Service 250,000 250,000 PW-038 2,187,5002,187,5002022 Street Improvements 3 Debt Service 2,187,500 2,187,500 PW-039 1,867,5001,867,5002023 Street Improvements 3 Debt Service 1,867,500 1,867,500 PW-043 200,000200,000Service Truck 1 Sewer Fund 50,000 50,000 Vehicle Replacement Fund 100,000 100,000 Water Fund 50,000 50,000 PW-044 60,00060,000Trac Hoe 2 Storm Water Fund 15,000 15,000 Vehicle Replacement Fund 30,000 30,000 Water Fund 15,000 15,000 PW-045 265,000265,000Tandem Plow Truck 1 Vehicle Replacement Fund 265,000 265,000 PW-047 240,000240,000Dump Truck w/Plow 1 Vehicle Replacement Fund 240,000 240,000 PW-048 120,000120,000Mini Loader 2 Vehicle Replacement Fund 120,000 120,000 PW-049 60,00060,000Asphalt Hot Box 4 General Fund 60,000 60,000 PW-050 245,000245,000Dump Truck with Plow 1 Vehicle Replacement Fund 245,000 245,000 PW-051 500,000500,000CSAH 14/CSAH 15 Realignment 3 Municipal Sate Aid (MSA)500,000 500,000 PW-052 800,000800,000Ideal Ave (CSAH 13) Phase 2 3 Debt Service 800,000 800,000 PW-053 00Ideal Ave (CSAH 13) CSAH 14 to CSAH 6 3 Debt Service 0 0 PW-054 65,00065,000Skidloader3 Vehicle Replacement Fund 65,000 65,000 PW-057 400,000400,000Manning Ave Phase 3 3 Debt Service 400,000 400,000 PW-058 2,000,0002,000,000TH 36/Manning Interchange 2 Debt Service 1,000,000 1,000,000 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Total20192020202120222023DepartmentProject #Priority Municipal Sate Aid (MSA)1,000,000 1,000,000 PW-059 780,00070,000 710,000Keats Ave/TH 36 Acceleration Lane 3 General Fund 70,000 70,000 Grants/Donation 710,000 710,000 19,162,5003,290,000 4,235,000 6,407,500 2,462,500 2,767,500Public Works Department Total Sewer Department S-003 250,000250,000Sunfish Lake Sewer Extension & Lift Station 3 Debt Service 250,000 250,000 S-005 885,500885,500Old Village Sewer Extension Phase 5 & 6 3 Debt Service 885,500 885,500 S-012 1,500,0001,500,000Section 36 Trunk Sewer Main 3 Grants/Donation 1,500,000 1,500,000 S-013 295,000295,000Sewer Oversizing 3 Sewer Fund 295,000 295,000 S-016 885,500885,500Old Village Sewer Extension Phase 5 & 6 3 Debt Service 885,500 885,500 S-017 522,500522,500Old Village Sewer Extension Phase 7 3 Sewer Fund 522,500 522,500 4,338,500545,000 2,385,500 885,500 522,500Sewer Department Total Storm Water Department SW-001 1,400,000600,000 800,000Phase 2 Regional Drainage Improvements 3 Debt Service 600,000 800,000 1,400,000 SW-002 500,000500,000Phase 3 Regional Drainage Improvements 3 Debt Service 500,000 500,000 SW-003 60,00060,000Kramer Lake Floodplain Study 3 Grants/Donation 60,000 60,000 SW-004 40,00040,000Surface Water Management Plan (Comp Plan) update 3 Storm Water Fund 40,000 40,000 2,000,00040,000 1,160,000 800,000Storm Water Department Total Water Department W-001 1,020,0001,020,0002019 Street Improvement Project - water component 3 Debt Service 1,020,000 1,020,000 W-004 120,000120,000Pressure Reduction Valve 3 Water Fund 120,000 120,000 W-005 596,750596,750OV Sewer Extension; Phase 5&6; water component 3 Debt Service 596,750 596,750 W-006 3,475,000275,000 3,200,000Elevated Storage Tank #3 1 Debt Service 275,000 3,200,000 3,475,000 W-007 120,000120,000Hammes Estates 12" bypass 4 Water Fund 120,000 120,000 W-008 132,000132,000Village East Trunk Watermain 2 Water Fund 132,000 132,000 W-010 800,000800,000Paint Water Tank at PW 4 Water Fund 800,000 800,000 W-013 188,000188,000Watermain Oversizing 3 Water Fund 188,000 188,000 W-014 2,100,0002,100,000Well & Pumphouse #5 1 Debt Service 2,100,000 2,100,000 W-017 725,000725,0002020 Street & Utility Improvements-Water 3 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Total20192020202120222023DepartmentProject #Priority Grants/Donation 675,000 675,000 Water Fund 50,000 50,000 W-018 50,00050,0002021 Street & Utility Improvements-Water 3 Water Fund 50,000 50,000 W-019 50,00050,000SCADA Upgrade 2 Water Fund 50,000 50,000 W-022 70,00070,000Utility Truck 3 Sewer Fund 35,000 35,000 Water Fund 35,000 35,000 W-023 200,00050,000 50,000 50,000 50,000Water Meter Change Out 1 Water Fund 50,000 50,000 50,000 50,000 200,000 W-024 300,000300,000Automated Radio Read System 3 Water Fund 300,000 300,000 W-025 596,750596,750OV sewer extension phase 6 & 5; water component 3 Debt Service 596,750 596,750 W-026 253,000253,000OV sewer extension Phase 7; water component 3 Water Fund 253,000 253,000 W-027 132,000132,000Pressure Reduction Station-Connection to WT #3 3 Water Fund 132,000 132,000 W-028 75,00075,000Blackford Water Ext 2 Grants/Donation 75,000 75,000 W-029 225,000225,00031st St Area Water Extension 2 Grants/Donation 225,000 225,000 W-030 100,000100,0002023 Street Projects-water component 3 Water Fund 100,000 100,000 11,328,5001,653,000 4,527,000 2,866,750 996,750 1,285,000Water Department Total GRAND TOTAL 52,497,9166,488,500 10,232,000 17,112,066 13,265,350 5,400,000 Thursday, November 29, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact City Administrator 2019 2023thru Department Admin/Finance Department Description New City Facilities 1. Space Needs Study in 2017 including fire station and public works needs 2. cost estimates from BKV Space Needs Study dated November 21, 2017 for public works improvements 3. cost estimates for new fire station/city hall from Leo A Dlay study April 4, 2018 ($10.2m) 4. Public Works Improvements to existing facility $250,000 in 2018 for larger salt shed $500,000 in 2020 for office addition $250,000 in 2021 for yard improvements 5. New City Hall/Fire Station 2020-2022 Project #AF-001 Priority 2 Very Important Justification Would allow all staff (except public works) to be at one site, community meeting rooms, updated council chambers. Locate single fire station in more central location with better access to main roads. Brookfield lease was $33k per year and increasing. Brookfield office builiding and land purchased in 2018 Lease expirations: 4- month to month with 60-90 day notice 1-annual 12/31/18 1-3/31/20 1-12/31/20 1-12/31/21 1-6/30/22 *relocation costs: personal propoerty moving costs and reestablishment costs Budget Impact/Other Borrowing split over multiple years. 50% of funds borrowed must be spent within 12 months. Debt payments to be split amongst General Fund (80%), Water (10%) and Sewer (10%) 2020: degisn and preconstruction costs of new city hall/fire station ($750,000); public works office addition ($500,000) 2021: council chambers and fire apparatus bay additions ($4,225,000) and public works yard impr ($250,000) 2022: remodel of Brookfield and repurchase from EDA ($5,225,000) costs are based off of 2019 build estimates and do not include construction inflation of 3-4% Useful Life 40 years Project Name New City Hall, Fire Station, PW Improvements Category Buildings Type Improvement Total Project Cost:$11,215,000 Status Active Total20192020202120222023Expenditures 750,000750,000Planning/Design 10,200,000500,000 4,475,000 5,225,000Construction/Maintenance 1,250,000 4,475,000 5,225,000 10,950,000Total Total20192020202120222023Funding Sources 10,950,0001,250,000 4,475,000 5,225,000Debt Service 1,250,000 4,475,000 5,225,000 10,950,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Fire Chief 2019 2023thru Department Fire Department Description Replacement of 1987 Tender that was refurbished in 2004. Project #F-004 Priority 1 Critical Justification End of Useful Life Priority for providing service in non-hydrant areas Budget Impact/Other None. Useful Life 20 years Project Name Tender 1 Category Vehicles Type Equipment Total Project Cost:$925,000 Status Active Total20192020202120222023Expenditures 425,000425,000Equip/Vehicles/Furnishings 425,000 425,000Total Total20192020202120222023Funding Sources 425,000425,000Debt Service 425,000 425,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Fire Chief 2019 2023thru Department Fire Department Description Replacement of Self Contained Breathing Apparatus (SCBA) 25, plus 2-RIT packs Repairs done in Sept 2014 to extend the life of the SCBA's by 5 years. Only option now is to replace. Project #F-007 Priority 1 Critical Justification End of Useful Life, NFPA requirement Budget Impact/Other Useful Life 15 years Project Name SCBA Replacements Category Equipment: Fire Equip Type Equipment Total Project Cost:$245,500 Status Active Total20192020202120222023Expenditures 245,500245,500Equip/Vehicles/Furnishings 245,500 245,500Total Total20192020202120222023Funding Sources 245,500245,500Debt Service 245,500 245,500Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Fire Chief 2019 2023thru Department Fire Department Description Replace 2001 B1 brush/grass rig=F350 w/markings and lighting Project #F-010 Priority 3 Important Justification End of Useful Life Replaces 2001 F-350 Budget Impact/Other Useful Life 15 years Project Name B 1 Category Vehicles Type Equipment Total Project Cost:$135,000 Status Active Total20192020202120222023Expenditures 60,00060,000Equip/Vehicles/Furnishings 60,000 60,000Total Total20192020202120222023Funding Sources 60,00060,000Vehicle Replacement Fund 60,000 60,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Fire Chief 2019 2023thru Department Fire Department Description Replacement of 1997 Engine that was refurbished in 2007 Project #F-011 Priority 1 Critical Justification End of Useful Life May not be needed if in one station, depending on staffing and pumping capacity Budget Impact/Other Useful Life 25 years Project Name E1 Engine Category Vehicles Type Equipment Total Project Cost:$580,000 Status Active Total20192020202120222023Expenditures 580,000580,000Equip/Vehicles/Furnishings 580,000 580,000Total Total20192020202120222023Funding Sources 580,000580,000Vehicle Replacement Fund 580,000 580,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Fire Chief 2019 2023thru Department Fire Department Description Replacement of 24 sets of turnout gear Project #F-017 Priority 1 Critical Justification End of useful life Budget Impact/Other Useful Life Project Name Turnout Gear Replacements Category Equipment: Fire Equip Type Maintenance Total Project Cost:$60,000 Status Active Total20192020202120222023Expenditures 60,00060,000Equip/Vehicles/Furnishings 60,000 60,000Total Total20192020202120222023Funding Sources 60,00060,000General Fund 60,000 60,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact City Administrator 2019 2023thru Department Parks and Recreation Description Phase 1 Improvements were completed in 2016 which included a new shelter. Phase 2 (2019) Improvements would include paving the parking area, development of two volleyball courts and lighting and secuirty features. Resurcafing of tennis courts and basketball court. Cost estimates: Volleyball Courts estimate is $10,000 Lighting and Security Features: $15,000 Court resurfacing: $40,000 Project #PR-005 Priority 3 Important Justification Feedback from park user survey in 2013 Budget Impact/Other Useful Life Project Name Pebble Park Improvements Category Park Improvements Type Improvement Total Project Cost:$65,000 Status Active Total20192020202120222023Expenditures 65,00065,000Construction/Maintenance 65,000 65,000Total Total20192020202120222023Funding Sources 65,00065,000Park Dedication Fund 65,000 65,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact City Administrator 2019 2023thru Department Parks and Recreation Description (2019) Development of 5 miles of mountain biking trails at $24,000 per mile per Trail Source (2021) Paving of trails Cost estimate: Improve trails to ADA standards in Area 2 (prairie area): $90,000 for 6 foot wide asphalt 1 mile trail Project #PR-007 Priority 3 Important Justification Explore Mt biking at direction of Council (10/17) ADA trails consistent with Development Guide for Sunfish Lake Park as approved by MN Land Trust Budget Impact/Other Useful Life Project Name Sunfish Lake Park Improvements Category Park Improvements Type Improvement Total Project Cost:$210,000 Status Active Total20192020202120222023Expenditures 210,000120,000 90,000Construction/Maintenance 120,000 90,000 210,000Total Total20192020202120222023Funding Sources 210,000120,000 90,000Park Dedication Fund 120,000 90,000 210,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact City Administrator 2019 2023thru Department Parks and Recreation Description Regional east west trail through Lake Elmo Phase 1: ($827,316-construction only, no land Connect to existing Oakdale trail at Stillwater Blvd and Helmo/Ideal Ave Travel through Tablyn Park to Lake Elmo Park Reseerve (LEPR) Pass through LEPR-provide exit point to Sunfish Lake Park Continue down Hwy5/CSAH 14 righ tof way to Gorman's-connect to exisitng trail Phase 2: ($765,600-construction only, no land) Lake Elmo to Stillwater Senior High Project #PR-009 Priority 3 Important Justification Trail would address the following community needs: -Deliver students safely to school -Bring people to our downtown -Bring people to our parks -Provide safe recreation -Trail Diversity-Provide feel of Lake Elmo -Omit need to bike down Hwy 5/CSAH 14 -Compatibility with public grant opportunities -Compatibility with private funding opportunities Feasibility of land acquisition Budget Impact/Other Additional trails to maintain-labor and materials Useful Life Project Name Lake Elmo Regional Trail Category Park Improvements Type Improvement Total Project Cost:$1,592,916 Status Active Total20192020202120222023Expenditures 1,592,916827,316 765,600Construction/Maintenance 827,316 765,600 1,592,916Total Total20192020202120222023Funding Sources 1,194,687620,487 574,200Grants/Donation 398,229206,829 191,400Park Dedication Fund 827,316 765,600 1,592,916Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Parks and Recreation Description Tri-Deck 10ft mower replaces 2002 model Project #PR-014 Priority 3 Important Justification End of Useful Life Budget Impact/Other lease options available Useful Life Project Name Tri-Deck Mower Category Vehicles Type Equipment Total Project Cost:$70,000 Status Active Total20192020202120222023Expenditures 70,00070,000Equip/Vehicles/Furnishings 70,000 70,000Total Total20192020202120222023Funding Sources 70,00070,000Vehicle Replacement Fund 70,000 70,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Parks and Recreation Description One ton hook truck replaces 2009 vehicle. Truck will have interchangeable boxes and flat beds for multiple uses. Project #PR-015 Priority 3 Important Justification End of Useful life Budget Impact/Other Useful Life Project Name One Ton Truck Category Vehicles Type Equipment Total Project Cost:$130,000 Status Active Total20192020202120222023Expenditures 130,000130,000Equip/Vehicles/Furnishings 130,000 130,000Total Total20192020202120222023Funding Sources 130,000130,000Vehicle Replacement Fund 130,000 130,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact City Administrator 2019 2023thru Department Parks and Recreation Description New ballfields to be constructed or refurbished after Tartan ball fields are no longer used by the public Project #PR-017 Priority 1 Critical Justification Replacement of some of the fields at Tartan Park lost to development of Royal Oaks Golf Course Community Budget Impact/Other Funding to be provided from developer in development agreement with Royal Golf. Funds to be used for acquisition of land, if necessary, and builidngor refurbishing of (a) new ballfield(s). Useful Life 40 years Project Name New or Refurbished Ballfields Category Park Improvements Type Improvement Total Project Cost:$1,000,000 Status Active Total20192020202120222023Expenditures 1,000,0001,000,000Construction/Maintenance 1,000,000 1,000,000Total Total20192020202120222023Funding Sources 1,000,0001,000,000Grants/Donation 1,000,000 1,000,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact City Administrator 2019 2023thru Department Parks and Recreation Description New park to be developed in the Wildflower/Village Preserve area in 2019 and in Inwood in 2020 Project #PR-018 Priority 4 Less Important Justification Areas identified during development as a park search area to provide recreational opportunities to new residents. Budget Impact/Other Useful Life 40 years Project Name New Park Development Category Park Improvements Type Improvement Total Project Cost:$255,000 Status Active Total20192020202120222023Expenditures 255,000105,000 150,000Construction/Maintenance 105,000 150,000 255,000Total Total20192020202120222023Funding Sources 255,000105,000 150,000Park Dedication Fund 105,000 150,000 255,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Parks and Recreation Description Parks commission recommended the search and planning for a dog park somewhere near the denser developments Improvements would be minimal such as fencing Project #PR-019 Priority 4 Less Important Justification Residents on small lots in denser developments need a place to take their dogs for exercise. By providing a dog park those who let their dogs run off leash in other parks can be redirected Budget Impact/Other Useful Life 25 years Project Name Dog Park Category Park Improvements Type Improvement Total Project Cost:$25,000 Status New Recommendation Total20192020202120222023Expenditures 25,00025,000Construction/Maintenance 25,000 25,000Total Total20192020202120222023Funding Sources 25,00025,000Park Dedication Fund 25,000 25,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Replace 1999 loader Project #PW-004 Priority 2 Very Important Justification End of Useful Life Budget Impact/Other Useful Life 15 years Project Name Loader Category Vehicles Type Equipment Total Project Cost:$185,000 Status Active Total20192020202120222023Expenditures 185,000185,000Equip/Vehicles/Furnishings 185,000 185,000Total Total20192020202120222023Funding Sources 185,000185,000Vehicle Replacement Fund 185,000 185,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Replace 2004 Tractor Cost include all ditch and mowing attachments Additional cost for snowblower ($30k included in total) Project #PW-006 Priority 2 Very Important Justification End of Useful Life Budget Impact/Other Useful Life 15 years Project Name Tractor Category Vehicles Type Equipment Total Project Cost:$110,000 Status Active Total20192020202120222023Expenditures 110,000110,000Equip/Vehicles/Furnishings 110,000 110,000Total Total20192020202120222023Funding Sources 110,000110,000Vehicle Replacement Fund 110,000 110,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description 36th, 37th St, 38th, 39th, Innsdale, Irwin Project #PW-013 Priority 3 Important Justification Annual street impvovements per Engineering program/recommendation Budget Impact/Other $526,500 assessment revenue Useful Life 25 years Project Name 2019 Street Improvements Category Street Construction Type Improvement Total Project Cost:$1,755,000 Status Active Total20192020202120222023Expenditures 1,755,0001,755,000Construction/Maintenance 1,755,000 1,755,000Total Total20192020202120222023Funding Sources 1,755,0001,755,000Debt Service 1,755,000 1,755,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Replacement for 2012 F250 End of usefull life (7 years) Project #PW-019 Priority 4 Less Important Justification Replacement for 2012 F250 End of useful life Budget Impact/Other Useful Life 10 years Project Name PickupTruck Category Vehicles Type Equipment Total Project Cost:$30,000 Status Active Total20192020202120222023Expenditures 30,00030,000Equip/Vehicles/Furnishings 30,000 30,000Total Total20192020202120222023Funding Sources 30,00030,000Vehicle Replacement Fund 30,000 30,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description Reconstruction of roads in Heritage Farms, Stonegate 2nd Project #PW-026 Priority 3 Important Justification Per pavement management plan reviewed by Engineer and Public Works Director Budget Impact/Other $391,500 assessment revenue Useful Life 25 years Project Name 2020 Street Improvements Category Street Reconstruction Type Improvement Total Project Cost:$1,305,000 Status Active Total20192020202120222023Expenditures 1,305,0001,305,000Construction/Maintenance 1,305,000 1,305,000Total Total20192020202120222023Funding Sources 1,305,0001,305,000Debt Service 1,305,000 1,305,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description $2,200,000 Fields of St. Croix 2, Tamarack Farms & Hamlet on Sunfish Lake Street Improvements. $1,237,500 for Ov Phase 5 & 6 (completed in 2 years) Project #PW-027 Priority 3 Important Justification Per pavement management plan reviewed by Engineer and Public Works Director Budget Impact/Other $660,000 assessment revenue Useful Life 25 years Project Name 2021 Street Improvements Category Street Reconstruction Type Improvement Total Project Cost:$3,437,500 Status Active Total20192020202120222023Expenditures 3,437,5003,437,500Construction/Maintenance 3,437,500 3,437,500Total Total20192020202120222023Funding Sources 3,437,5003,437,500Debt Service 3,437,500 3,437,500Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description CSAH 19/Hudson Blvd Signal and Turn Lane Improvements Project #PW-029 Priority 3 Important Justification Traffic levels warrant a stop light per study completed by Washington County Budget Impact/Other Useful Life 25 years Project Name CSAH19/Hudson Blvd Signal & Turn Lane Category Street Reconstruction Type Improvement Total Project Cost:$500,000 Status Active Total20192020202120222023Expenditures 500,000500,000Construction/Maintenance 500,000 500,000Total Total20192020202120222023Funding Sources 500,000500,000Municipal Sate Aid (MSA) 500,000 500,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description CSAH 15/30th Street signal improvements. May be stand alone project or with CSAH 15 Phase 3 Project #PW-030 Priority 3 Important Justification Improvement needed due to increase of traffic Washington County study Budget Impact/Other Useful Life 25 years Project Name CSAH 15/30th Street Signal Category Street Construction Type Maintenance Total Project Cost:$250,000 Status Active Total20192020202120222023Expenditures 250,000250,000Construction/Maintenance 250,000 250,000Total Total20192020202120222023Funding Sources 250,000250,000Municipal Sate Aid (MSA) 250,000 250,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description 15th Street reconstruction Project #PW-034 Priority 3 Important Justification Significant patching made in 2018 to extend road life a couple years. Recon needed per pavement management plan reviewed by Engineer and Public Works Director Budget Impact/Other Useful Life 25 years Project Name 15th Street North (MSA Street)Category Street Reconstruction Type Improvement Total Project Cost:$950,000 Status Active Total20192020202120222023Expenditures 950,000950,000Construction/Maintenance 950,000 950,000Total Total20192020202120222023Funding Sources 950,000950,000Municipal Sate Aid (MSA) 950,000 950,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description UP RR Crossing - Village Parkway Project #PW-035 Priority 2 Very Important Justification To allow connectivity between developing neighborhoods north and south of the tracks Budget Impact/Other Useful Life 40 years Project Name UP RR Crossing - Village Parkway Category Street Construction Type Improvement Total Project Cost:$500,000 Status Active Total20192020202120222023Expenditures 500,000500,000Construction/Maintenance 500,000 500,000Total Total20192020202120222023Funding Sources 500,000500,000Grants/Donation 500,000 500,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description UP RR Crossing - Private driveway closure required for Village Parkway Crossing Project #PW-036 Priority 2 Very Important Justification Railroad requirement in order to get new crossing at Village Parkway Budget Impact/Other Useful Life 40 years Project Name UP RR Crossing - Private Drive Closure Category Unassigned Type Improvement Total Project Cost:$100,000 Status Active Total20192020202120222023Expenditures 100,000100,000Construction/Maintenance 100,000 100,000Total Total20192020202120222023Funding Sources 100,000100,000Debt Service 100,000 100,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description UP RR Crossing - Klondike - upgraded crossing to inlcude light and gates Project #PW-037 Priority 2 Very Important Justification Railroad requirement in order to build new crossing at Village Parkway Budget Impact/Other Useful Life 40 years Project Name UP RR Crossing: Klondike Ave Category Street Construction Type Unassigned Total Project Cost:$250,000 Status Active Total20192020202120222023Expenditures 250,000250,000Construction/Maintenance 250,000 250,000Total Total20192020202120222023Funding Sources 250,000250,000Debt Service 250,000 250,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description Annual Street Improvements- Fields of St Croix and Irish Court: $950,000 And $1,237,500 for OV 5 & 6 (Over 2 years) Project #PW-038 Priority 3 Important Justification Annual street improvements per Engineering recommendation Budget Impact/Other $285,000 assessment revenue Useful Life 25 years Project Name 2022 Street Improvements Category Street Reconstruction Type Improvement Total Project Cost:$2,187,500 Status Active Total20192020202120222023Expenditures 2,187,5002,187,500Construction/Maintenance 2,187,500 2,187,500Total Total20192020202120222023Funding Sources 2,187,5002,187,500Debt Service 2,187,500 2,187,500Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description Annual Street Imrpovements $1.4 million-Tana Ridge, Parkview Estates, Beaut Crest $467,500-Old Village Phase 7 (Legion Ave N) Project #PW-039 Priority 3 Important Justification Annual street improvements per Engineering recommendation Budget Impact/Other $420,000 assessment revenue Useful Life 25 years Project Name 2023 Street Improvements Category Street Reconstruction Type Improvement Total Project Cost:$1,867,500 Status Active Total20192020202120222023Expenditures 1,867,5001,867,500Construction/Maintenance 1,867,500 1,867,500Total Total20192020202120222023Funding Sources 1,867,5001,867,500Debt Service 1,867,500 1,867,500Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description truck will be multi-function with boom for tree trimming and other high work, crane for pulling lift station pumps, air compressor and tools for street sign work, line of tools and equipment to make fleet field repairs Project #PW-043 Priority 1 Critical Justification New vehicle to improve efficiencies in dept due to multiple functions Budget Impact/Other $200,000 total cost split eqaully amongst water (W-020), sewer (S-014), streets and parks (PR-012) Useful Life Project Name Service Truck Category Vehicles Type Equipment Total Project Cost:$200,000 Status Active Total20192020202120222023Expenditures 200,000200,000Equip/Vehicles/Furnishings 200,000 200,000Total Total20192020202120222023Funding Sources 50,00050,000Sewer Fund 100,000100,000Vehicle Replacement Fund 50,00050,000Water Fund 200,000 200,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Replace 2006 Case Backhoe with a more manuverable unit. Project #PW-044 Priority 2 Very Important Justification End of Useful Life Budget Impact/Other $60,000 total cost split equally amongst water (W-021), stormwater (SW-006), streets and parks (PR-013) Useful Life Project Name Trac Hoe Category Vehicles Type Equipment Total Project Cost:$60,000 Status Active Total20192020202120222023Expenditures 60,00060,000Equip/Vehicles/Furnishings 60,000 60,000Total Total20192020202120222023Funding Sources 15,00015,000Storm Water Fund 30,00030,000Vehicle Replacement Fund 15,00015,000Water Fund 60,000 60,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Plow will replace a 2000 model year that has mech problems due to a past accident. A larger truck is needed due to growth and increased traffic on 5th St/Hudson Blvd. Will also be utillized in larger OP developments in the north side of city. Larger truck of this size is cabable of carrying more salt so it can stay on routes longer w/out returning to refill. Project #PW-045 Priority 1 Critical Justification End of Useful life and increase in lane miles Budget Impact/Other Useful Life Project Name Tandem Plow Truck Category Vehicles Type Equipment Total Project Cost:$265,000 Status Active Total20192020202120222023Expenditures 265,000265,000Equip/Vehicles/Furnishings 265,000 265,000Total Total20192020202120222023Funding Sources 265,000265,000Vehicle Replacement Fund 265,000 265,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Single Axel plow truck to replace 1998 model Project #PW-047 Priority 1 Critical Justification End of Useful Life Budget Impact/Other Useful Life Project Name Dump Truck w/Plow Category Vehicles Type Equipment Total Project Cost:$240,000 Status Active Total20192020202120222023Expenditures 240,000240,000Equip/Vehicles/Furnishings 240,000 240,000Total Total20192020202120222023Funding Sources 240,000240,000Vehicle Replacement Fund 240,000 240,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Mini loader to replace 2006 Case Back Hoe with a more manuverable unit. Will be outfitted with a plow for cul de sacs and other narrow streets. Project #PW-048 Priority 2 Very Important Justification End of Useful Life Budget Impact/Other Useful Life Project Name Mini Loader Category Equipment: PW Equip Type Equipment Total Project Cost:$120,000 Status Active Total20192020202120222023Expenditures 120,000120,000Equip/Vehicles/Furnishings 120,000 120,000Total Total20192020202120222023Funding Sources 120,000120,000Vehicle Replacement Fund 120,000 120,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Slide in unit for dump truck. Will replace a trailer hot box and utilize a single axel dump truck during the summer months Project #PW-049 Priority 4 Less Important Justification End of Useful Life Budget Impact/Other Useful Life Project Name Asphalt Hot Box Category Equipment: PW Equip Type Equipment Total Project Cost:$60,000 Status Active Total20192020202120222023Expenditures 60,00060,000Equip/Vehicles/Furnishings 60,000 60,000Total Total20192020202120222023Funding Sources 60,00060,000General Fund 60,000 60,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Replace 2006 model Project #PW-050 Priority 1 Critical Justification End of Useful Life Budget Impact/Other Useful Life Project Name Dump Truck with Plow Category Vehicles Type Equipment Total Project Cost:$245,000 Status Active Total20192020202120222023Expenditures 245,000245,000Equip/Vehicles/Furnishings 245,000 245,000Total Total20192020202120222023Funding Sources 245,000245,000Vehicle Replacement Fund 245,000 245,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description Realignment of CSAH 15 (Manning Ave) and CSAH 14 (Stilwater Blvd) Project #PW-051 Priority 3 Important Justification County led project to improve traffic flow south on Manning Ave Budget Impact/Other Construction scheduled for 2018, payment request for 2019 when more MSA funds available Useful Life 25 years Project Name CSAH 14/CSAH 15 Realignment Category Street Construction Type Improvement Total Project Cost:$500,000 Status Active Total20192020202120222023Expenditures 500,000500,000Construction/Maintenance 500,000 500,000Total Total20192020202120222023Funding Sources 500,000500,000Municipal Sate Aid (MSA) 500,000 500,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description Cooperatvie project between Washington County, City of Oakdale and City of Lake Elmo Improvements to CSAH 13 from CSAH 14 to 44th St Project #PW-052 Priority 3 Important Justification Need determined by Washington County New development in Oakdale will increase traffic in area Budget Impact/Other No Cost Estimates available from County at this time 30% assessment to residential properties and public works building Useful Life 20 years Project Name Ideal Ave (CSAH 13) Phase 2 Category Street Reconstruction Type Improvement Total Project Cost:$800,000 Status New Recommendation Total20192020202120222023Expenditures 800,000800,000Construction/Maintenance 800,000 800,000Total Total20192020202120222023Funding Sources 800,000800,000Debt Service 800,000 800,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description Cooperative project between Washington County, City of Oakdale and City of Lake Elmo Project #PW-053 Priority 3 Important Justification Need determined by Washington County Budget Impact/Other No cost estimates available at this time One Ag property owned by 3M Useful Life 20 years Project Name Ideal Ave (CSAH 13) CSAH 14 to CSAH 6 Category Street Reconstruction Type Improvement Total Project Cost:$0 Status New Recommendation Total20192020202120222023Expenditures 00Construction/Maintenance 0 0Total Total20192020202120222023Funding Sources 00Debt Service 0 0Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Public Works Department Description Additional skidloader to be used to mow park trails and asphalt in the summer. During the winter it can be used to aid in snow removal at city parking lots and possibly on park trails. Project #PW-054 Priority 3 Important Justification additional skidloader needed due to growth in streets and parks Budget Impact/Other Useful Life Project Name Skidloader Category Equipment: PW Equip Type Equipment Total Project Cost:$65,000 Status New Recommendation Total20192020202120222023Expenditures 65,00065,000Equip/Vehicles/Furnishings 65,000 65,000Total Total20192020202120222023Funding Sources 65,00065,000Vehicle Replacement Fund 65,000 65,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description CSAH 15 from CSAH 14 to CSAH 10 Project #PW-057 Priority 3 Important Justification Need deterined by Washington County Increased traffic due to growth in the area Budget Impact/Other No cost estimates from Wash Co 30% assessment to residential properties Trail could come from park dedication funds Useful Life 25 years Project Name Manning Ave Phase 3 Category Street Reconstruction Type Improvement Total Project Cost:$400,000 Status New Recommendation Total20192020202120222023Expenditures 400,000400,000Construction/Maintenance 400,000 400,000Total Total20192020202120222023Funding Sources 400,000400,000Debt Service 400,000 400,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description New Interchange to replace stop lights at TH 36 and Manning Project #PW-058 Priority 2 Very Important Justification Cooperative project with MNDOT, Washington County, Stillwater, Grant, Oak Park Heights and Stillwater Township. Increased traffic on TH 36 Fatality at intersection in 2013 Budget Impact/Other No cost estimates available Cost share between Wash Co, Mn DOT, Lake Elmo, Grant, Stillwater, and Stillwater Twp Useful Life 25 years Project Name TH 36/Manning Interchange Category Street Construction Type Improvement Total Project Cost:$2,000,000 Status New Recommendation Total20192020202120222023Expenditures 2,000,0002,000,000Construction/Maintenance 2,000,000 2,000,000Total Total20192020202120222023Funding Sources 1,000,0001,000,000Debt Service 1,000,0001,000,000Municipal Sate Aid (MSA) 2,000,000 2,000,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Public Works Department Description Acceleration lane added to TH 36 at Keats Ave to go westbound on TH 36 Project #PW-059 Priority 3 Important Justification Multiple requests from community members, particularly those leaving services at Rock Point Church Budget Impact/Other Predesign engineering costs required to apply for grant for construction costs from MNDOT Useful Life 40 years Project Name Keats Ave/TH 36 Acceleration Lane Category Street Construction Type Improvement Total Project Cost:$780,000 Status New Recommendation Total20192020202120222023Expenditures 70,00070,000Planning/Design 710,000710,000Construction/Maintenance 70,000 710,000 780,000Total Total20192020202120222023Funding Sources 70,00070,000General Fund 710,000710,000Grants/Donation 70,000 710,000 780,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Sewer Department Description Sewer Extension to Sunfish Lake Park Project #S-003 Priority 3 Important Justification Per 2016 MPCA agreement 100% assessed Budget Impact/Other Useful Life 40 years Project Name Sunfish Lake Sewer Extension & Lift Station Category Wastewater Type Improvement Total Project Cost:$250,000 Status Active Total20192020202120222023Expenditures 250,000250,000Construction/Maintenance 250,000 250,000Total Total20192020202120222023Funding Sources 250,000250,000Debt Service 250,000 250,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Sewer Department Description Sewer extension in the Old Village Phases 5 & 6 (over 2 years) OV 5: 33rd, Kraft , Lampert, 32nd, Langley OV 6: Upper 33rd, 34th, 35th, 36th Properties just south of railroad track would only be completed if easements granted to reach properties Project #S-005 Priority 3 Important Justification Met Coucnil requirement to extend sewer Failing septic systems 100% Assessed Budget Impact/Other Useful Life 40 years Project Name Old Village Sewer Extension Phase 5 & 6 Category Wastewater Type Improvement Total Project Cost:$885,500 Status Active Total20192020202120222023Expenditures 885,500885,500Construction/Maintenance 885,500 885,500Total Total20192020202120222023Funding Sources 885,500885,500Debt Service 885,500 885,500Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Sewer Department Description Section 36 Trunk Sewer Main (Cimarron/Oakland Jr High) Project #S-012 Priority 3 Important Justification Section 36 Trunk Sewer Main to Cimarron and Oakland Jr. High Development driven from Hudson Blvd to the north Budget Impact/Other Developer paid except for oversizing costs possibly Useful Life 40 years Project Name Section 36 Trunk Sewer Main Category Wastewater Type Improvement Total Project Cost:$1,500,000 Status Active Total20192020202120222023Expenditures 1,500,0001,500,000Construction/Maintenance 1,500,000 1,500,000Total Total20192020202120222023Funding Sources 1,500,0001,500,000Grants/Donation 1,500,000 1,500,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Sewer Department Description Sewer Oversizing Project #S-013 Priority 3 Important Justification Sewer oversizing based on developer pace and phasing Budget Impact/Other Useful Life 40 years Project Name Sewer Oversizing Category Wastewater Type Improvement Total Project Cost:$476,500 Status Active Total20192020202120222023Expenditures 295,000295,000Construction/Maintenance 295,000 295,000Total Total20192020202120222023Funding Sources 295,000295,000Sewer Fund 295,000 295,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Sewer Department Description Sewer extension in the Old Village Phases 5 & 6 (over 2 years) OV 5: 33rd, Kraft , Lampert, 32nd, Langley OV 6: Upper 33rd, 34th, 35th, 36th Properties just south of railroad track would only be completed if easements granted to reach properties Project #S-016 Priority 3 Important Justification Met Coucnil requirement to extend sewer Failing septic systems 100% Assessed Budget Impact/Other Useful Life Project Name Old Village Sewer Extension Phase 5 & 6 Category Wastewater Type Improvement Total Project Cost:$885,500 Status Active Total20192020202120222023Expenditures 885,500885,500Construction/Maintenance 885,500 885,500Total Total20192020202120222023Funding Sources 885,500885,500Debt Service 885,500 885,500Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Sewer Department Description Legion Ave N Project #S-017 Priority 3 Important Justification Met Coucnil requirement to extend sewer Failing septic systems 100% Assessed Budget Impact/Other Useful Life Project Name Old Village Sewer Extension Phase 7 Category Wastewater Type Improvement Total Project Cost:$522,500 Status Active Total20192020202120222023Expenditures 522,500522,500Construction/Maintenance 522,500 522,500Total Total20192020202120222023Funding Sources 522,500522,500Sewer Fund 522,500 522,500Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Storm Water Department Description Land acquistion (Schiltgen) and/or possible diversion to Sunfish Lake Park Project #SW-001 Priority 3 Important Justification 2nd Phase to improving the regional drainage issues timing dependent upon development Budget Impact/Other Useful Life 40 years Project Name Phase 2 Regional Drainage Improvements Category Storm Sewer/Drainage Type Improvement Total Project Cost:$1,400,000 Status Active Total20192020202120222023Expenditures 600,000600,000Land Acquisition 800,000800,000Construction/Maintenance 600,000 800,000 1,400,000Total Total20192020202120222023Funding Sources 1,400,000600,000 800,000Debt Service 600,000 800,000 1,400,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Storm Water Department Description Phase 3 of Regional Drainage Improvements (VFW Park) Project #SW-002 Priority 3 Important Justification 3rd Phase of Regional Drainage Improvements (VFW Park) Budget Impact/Other Useful Life 40 years Project Name Phase 3 Regional Drainage Improvements Category Storm Sewer/Drainage Type Improvement Total Project Cost:$500,000 Status Active Total20192020202120222023Expenditures 500,000500,000Construction/Maintenance 500,000 500,000Total Total20192020202120222023Funding Sources 500,000500,000Debt Service 500,000 500,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact 2019 2023thru Department Storm Water Department Description Kramer Lake Floodplain Study Project #SW-003 Priority 3 Important Justification Required for I94 Phase 3 area development Budget Impact/Other Funding to come from developer or included as watershed study Useful Life 40 years Project Name Kramer Lake Floodplain Study Category Unassigned Type Improvement Total Project Cost:$60,000 Status Active Total20192020202120222023Expenditures 60,00060,000Planning/Design 60,000 60,000Total Total20192020202120222023Funding Sources 60,00060,000Grants/Donation 60,000 60,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Storm Water Department Description Surface Water Management Plan (Comp Plan) update Project #SW-004 Priority 3 Important Justification Part of the Comprehensive Comp Plan Update Requirement Budget Impact/Other Useful Life 10 years Project Name Surface Water Management Plan (Comp Plan) update Category Storm Sewer/Drainage Type Improvement Total Project Cost:$40,000 Status Active Total20192020202120222023Expenditures 40,00040,000Planning/Design 40,000 40,000Total Total20192020202120222023Funding Sources 40,00040,000Storm Water Fund 40,000 40,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Water component of 2019 Street Improvement Projects Project #W-001 Priority 3 Important Justification Need to upgrade the water services as street improvments are done Budget Impact/Other Additional utility and maintenance costs will be realized. Useful Life 40 years Project Name 2019 Street Improvement Project - water component Category Water Type Improvement Total Project Cost:$1,020,000 Status Active Total20192020202120222023Expenditures 1,020,0001,020,000Construction/Maintenance 1,020,000 1,020,000Total Total20192020202120222023Funding Sources 1,020,0001,020,000Debt Service 1,020,000 1,020,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Pressure reduction station-12" Tower #3 Project #W-004 Priority 3 Important Justification Necessary to control pressures due to the city having multiple pressure zones in the water system Budget Impact/Other None. Useful Life 40 years Project Name Pressure Reduction Valve Category Water Type Improvement Total Project Cost:$120,000 Status Active Total20192020202120222023Expenditures 120,000120,000Construction/Maintenance 120,000 120,000Total Total20192020202120222023Funding Sources 120,000120,000Water Fund 120,000 120,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Replace waterman in Old Village phase 5; Upper 33rd, Lower 33r. 34/36th St. W OV Phase 5 and 6 done over 2 years Project #W-005 Priority 3 Important Justification Watermain past useful life Replace when street already dug up for sewer to be most efficient Budget Impact/Other 100% covered by water fund Useful Life 40 years Project Name OV Sewer Extension; Phase 5&6; water component Category Water Type Improvement Total Project Cost:$596,750 Status Active Total20192020202120222023Expenditures 596,750596,750Construction/Maintenance 596,750 596,750Total Total20192020202120222023Funding Sources 596,750596,750Debt Service 596,750 596,750Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Water Tower #3 Project #W-006 Priority 1 Critical Justification needed for development in Phase 2 400 RECs available before needed Can be located in either Phase 2 or 3, the closer to Lake Elmo Ave the better Budget Impact/Other Useful Life 40 years Project Name Elevated Storage Tank #3 Category Water Type Equipment Total Project Cost:$3,475,000 Status Active Total20192020202120222023Expenditures 275,000275,000Land Acquisition 3,200,0003,200,000Construction/Maintenance 275,000 3,200,000 3,475,000Total Total20192020202120222023Funding Sources 3,475,000275,000 3,200,000Debt Service 275,000 3,200,000 3,475,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description 12" water main bypass in Hammes Project #W-007 Priority 4 Less Important Justification Needed to reduce water pressure and make flows Contingent upon whether a developer comes forward on the project Budget Impact/Other Useful Life 40 years Project Name Hammes Estates 12" bypass Category Water Type Improvement Total Project Cost:$120,000 Status Active Total20192020202120222023Expenditures 120,000120,000Construction/Maintenance 120,000 120,000Total Total20192020202120222023Funding Sources 120,000120,000Water Fund 120,000 120,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description 12" water main bypass Project #W-008 Priority 2 Very Important Justification need to reduce pressure and accommodate water flows Budget Impact/Other Useful Life 40 years Project Name Village East Trunk Watermain Category Water Type Improvement Total Project Cost:$132,000 Status Active Total20192020202120222023Expenditures 132,000132,000Construction/Maintenance 132,000 132,000Total Total20192020202120222023Funding Sources 132,000132,000Water Fund 132,000 132,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Water Department Description Project #W-010 Priority 4 Less Important Justification Recommended by TKDA Utility study in 2016 Regular maintenance of water tank Budget Impact/Other Useful Life 25 years Project Name Paint Water Tank at PW Category Water Type Equipment Total Project Cost:$800,000 Status Active Total20192020202120222023Expenditures 800,000800,000Equip/Vehicles/Furnishings 800,000 800,000Total Total20192020202120222023Funding Sources 800,000800,000Water Fund 800,000 800,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Oversizing cost of watermain pipe installed by developers. Project #W-013 Priority 3 Important Justification Ensures all pipe in the City will have flow capacity necessary for water system Budget Impact/Other Useful Life 40 years Project Name Watermain Oversizing Category Water Type Improvement Total Project Cost:$613,000 Status Active Total20192020202120222023Expenditures 188,000188,000Construction/Maintenance 188,000 188,000Total Total20192020202120222023Funding Sources 188,000188,000Water Fund 188,000 188,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Well and Pumphouse #5 Project #W-014 Priority 1 Critical Justification A 5th well and pumphouse will be necessary when the City water system reaches a population of 10,000 or sooner if well#1 taken offline Budget Impact/Other Useful Life 40 years Project Name Well & Pumphouse #5 Category Water Type Equipment Total Project Cost:$2,100,000 Status Active Total20192020202120222023Expenditures 2,100,0002,100,000Construction/Maintenance 2,100,000 2,100,000Total Total20192020202120222023Funding Sources 2,100,0002,100,000Debt Service 2,100,000 2,100,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description 2020 street improvement project - water component Hertitage Farms (existing water) and Stonegate 2nd (new water) Project #W-017 Priority 3 Important Justification improvements to existing watermain in Heritage farms $50,000 extension of water to Stonegate 2nd due to PFCs $675,000 Budget Impact/Other funding for Stonegate 2nd water component subject to city receving 3M settlement funds from the state Useful Life 40 years Project Name 2020 Street & Utility Improvements-Water Category Water Type Improvement Total Project Cost:$725,000 Status Active Total20192020202120222023Expenditures 725,000725,000Construction/Maintenance 725,000 725,000Total Total20192020202120222023Funding Sources 675,000675,000Grants/Donation 50,00050,000Water Fund 725,000 725,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description 2021 Street & Utility Improvements-water component Project #W-018 Priority 3 Important Justification City needs to upgrade water infrastructure when doing street improvement projects Fields of St. Croix 2 and Tamarack Farms Budget Impact/Other Useful Life 40 years Project Name 2021 Street & Utility Improvements-Water Category Water Type Improvement Total Project Cost:$50,000 Status Active Total20192020202120222023Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total20192020202120222023Funding Sources 50,00050,000Water Fund 50,000 50,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Upgrade current water system SCADA Project #W-019 Priority 2 Very Important Justification Current 2008 system useful life through 2023; however upgrades would provide critical functionality improvements Budget Impact/Other Useful Life 15 years Project Name SCADA Upgrade Category Water Type Equipment Total Project Cost:$50,000 Status Active Total20192020202120222023Expenditures 50,00050,000Equip/Vehicles/Furnishings 50,000 50,000Total Total20192020202120222023Funding Sources 50,00050,000Water Fund 50,000 50,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Water Department Description Replaces current 2007 vehicle Project #W-022 Priority 3 Important Justification End of Useful Life Budget Impact/Other $70,000 total cost shared equally amongst water and sewer (S-015) Useful Life Project Name Utility Truck Category Vehicles Type Equipment Total Project Cost:$70,000 Status Active Total20192020202120222023Expenditures 70,00070,000Equip/Vehicles/Furnishings 70,000 70,000Total Total20192020202120222023Funding Sources 35,00035,000Sewer Fund 35,00035,000Water Fund 70,000 70,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Water Department Description Replace 200 obsolete Sensus and Neptune meters each year with new Sensus 1 pro meters Project #W-023 Priority 1 Critical Justification Old meters not working properly leads to the need to estimate usage therefore billing process takes more staff time Budget Impact/Other Useful Life 15 years Project Name Water Meter Change Out Category Water Type Improvement Total Project Cost:$247,000 Status Active Total20192020202120222023Expenditures 200,00050,000 50,000 50,000 50,000Equip/Vehicles/Furnishings 50,000 50,000 50,000 50,000 200,000Total Total20192020202120222023Funding Sources 200,00050,000 50,000 50,000 50,000Water Fund 50,000 50,000 50,000 50,000 200,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Public Works Director 2019 2023thru Department Water Department Description Automated radio read system for water meters. Project #W-024 Priority 3 Important Justification Eliminates the need to drive around and obtain reads. Improves billing and gives "real time" readings to help detect leaks. Budget Impact/Other Useful Life Project Name Automated Radio Read System Category Water Type Improvement Total Project Cost:$300,000 Status Active Total20192020202120222023Expenditures 300,000300,000Equip/Vehicles/Furnishings 300,000 300,000Total Total20192020202120222023Funding Sources 300,000300,000Water Fund 300,000 300,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Replacement of water mains in conjunction with sewer extension to Phase 6 and 5 done over 2 years Project #W-025 Priority 3 Important Justification Watermain past useful life Replace when street already dug up for sewer to be most efficient Budget Impact/Other Useful Life Project Name OV sewer extension phase 6 & 5; water component Category Water Type Improvement Total Project Cost:$596,750 Status Active Total20192020202120222023Expenditures 596,750596,750Construction/Maintenance 596,750 596,750Total Total20192020202120222023Funding Sources 596,750596,750Debt Service 596,750 596,750Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Old Village Phase 7 water main replacement on Legion Ave Project #W-026 Priority 3 Important Justification Watermain past useful life Replace when street already dug up for sewer to be most efficient Budget Impact/Other Useful Life Project Name OV sewer extension Phase 7; water component Category Water Type Improvement Total Project Cost:$253,000 Status Active Total20192020202120222023Expenditures 253,000253,000Construction/Maintenance 253,000 253,000Total Total20192020202120222023Funding Sources 253,000253,000Water Fund 253,000 253,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Pressure reduction station-12" Project #W-027 Priority 3 Important Justification nneded when water crosses Keats Ave Budget Impact/Other Useful Life 40 years Project Name Pressure Reduction Station-Connection to WT #3 Category Water Type Improvement Total Project Cost:$132,000 Status Active Total20192020202120222023Expenditures 132,000132,000Construction/Maintenance 132,000 132,000Total Total20192020202120222023Funding Sources 132,000132,000Water Fund 132,000 132,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Extension of water main to Blackford property Project #W-028 Priority 2 Very Important Justification some private wells have received health based advisories and are on bottled water Budget Impact/Other project continegent upon city recevieng state funds Useful Life 40 years Project Name Blackford Water Ext Category Water Type Improvement Total Project Cost:$75,000 Status New Recommendation Total20192020202120222023Expenditures 75,00075,000Construction/Maintenance 75,000 75,000Total Total20192020202120222023Funding Sources 75,00075,000Grants/Donation 75,000 75,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description Petition recevied from city in 2017 to extend water on 31st St south of the UP Railroad Project #W-029 Priority 2 Very Important Justification private wells recevied health based advisories due to PFCs Budget Impact/Other project contingent upon city receeving state funds Useful Life 40 years Project Name 31st St Area Water Extension Category Water Type Improvement Total Project Cost:$225,000 Status New Recommendation Total20192020202120222023Expenditures 225,000225,000Construction/Maintenance 225,000 225,000Total Total20192020202120222023Funding Sources 225,000225,000Grants/Donation 225,000 225,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software Capital Improvement Plan - 2019 - 2023 City of Lake Elmo, Minnesota Contact Engineer 2019 2023thru Department Water Department Description $100,000 for valve and hydrant replacement in the Tana Ridge and Beaut Crest areas to be done when road is redone. Any additional costs for extending water to Parkview Estates would only be done if funding from state is recevied Project #W-030 Priority 3 Important Justification Opportune time for water replacements is when road is already opened for construction Budget Impact/Other Useful Life 40 years Project Name 2023 Street Projects-water component Category Water Type Improvement Total Project Cost:$100,000 Status New Recommendation Total20192020202120222023Expenditures 100,000100,000Construction/Maintenance 100,000 100,000Total Total20192020202120222023Funding Sources 100,000100,000Water Fund 100,000 100,000Total Friday, November 30, 2018Produced Using the Plan-It Capital Planning Software