HomeMy WebLinkAbout#27 - Royal Golf 3rd Addn Final Plat, PUD and Easement Vacation reduced1 STAFF REPORT DATE: 11/28/2018 REGULAR ITEM #: 27 MOTION TO: Mayor and City Council Members FROM: Jennifer Haskamp, Consulting Planner AGENDA ITEM: Royal Golf Club at Lake Elmo 3rd Addition Final Plat and Planned Unit Development (PUD) Plans and Easement Vacation REVIEWED BY: Ken Roberts, Planning Director Jack Griffin, City Engineer BACKGROUND: The City Council is being asked to consider a request by H.C. Golf Land, LLC for approval of the Final Plat and final PUD plans for the Royal Golf Club at Lake Elmo 3rd Addition. The Final Plat for the 3rd Addition includes 67 residential lots for development of 33 single-family villa style townhomes and 34 traditional single-family detached homes. REVIEW/ANALYSIS: Applicant and Owner: H.C. Golf Land, LLC Location: Outlot T, Royal Golf Club at Lake Elmo, PID# 25.029.21.22.0001, and Outlot J, Royal Golf Club at Lake Elmo, PID #25.029.21.31.0041. Request: Application for Final Plat and PUD Plans to approve 67 residential lots and easement vacation Existing Land Use: Vacant Outlot; Current Zoning: GCC – Golf Course Community Surrounding Land Use: North – Rural Single Family (RS) and Rural Residential (RR), South – The Homestead (OP – Open Space), East – Golf Course (GCC – Golf Course Community), Comprehensive Plan: GCC – Golf Course Community History: Preliminary Plat and PUD Plans approval was granted on June 6, 2017 by Resolution 2017-047. Final Plat and PUD Plans for 1st Addition was granted on September 5, 2017 by 2 Resolution 2017-093. Final Plat and PUD Plans for 2nd Addition was granted on July 3, 2018 by Resolution 2018- 070. Deadline for Action: Application Complete – 10/16/18 60 Day Deadline – 12/14/18 Extension Letter Mailed – No 120 Day Deadline – NA Applicable Regulations: Chapter 153 – Subdivision Regulations Article 10 – Urban Residential Districts (GCC) §150.270 Storm Water, Erosion, and Sediment Control ISSUE BEFORE CITY COUNCIL: To determine if the proposed Royal Golf Club at Lake Elmo 3rd Addition is consistent with the approved Preliminary Plat and that the relevant conditions to the 3rd Addition have been completed. Public Hearing and Planning Commission Recommendation The Planning Commission held a duly noticed public hearing at their regular November 26, 2018 meeting to consider the subject application. No public testimony was given or submitted regarding the proposed Final Plat. After closing the public hearing, the Planning Commission discussed the proposed Final Plat, the following summary of their discussion is provided: • Planning Commissioners discussed the changed configuration of the road network serving the Villa Lots in the Final Plat, and ultimately determined that the change from a loop road to two cul-de-sacs did not constitute a significant change. • Discussion regarding the reduction in total number of lots in the 3rd Addition from that which was reflected in the Preliminary Plat was determined to be consistent with preliminary plans when considering all three platted additions collectively (1st Addition, 2nd Addition, and the 3rd Addition if granted.) Planning Commissioners noted the importance of ensuring that future phases, whether one or multiple, be consistent with the total number of lots approved as part of the Preliminary Plat. After discussion, the Planning Commission recommended unanimous approval to the City Council of the Final Plat, Final PUD plans and Easement Vacation with the conditions as drafted and contained herein. The following staff report is generally as presented to the Planning Commission and is provided for your review and consideration. 3 FINAL PLAT AND PUD PLANS Consistency with Preliminary Plat. The proposed lot sizes, widths, and proposed impervious surface are generally consistent with that of preliminary plat. The only change is the modification of Kings Lane which was shown as a loop road in the Preliminary Plat, and is now proposed as two cul-de-sacs in the Final Plat. As a result of the conversion to two cul-de-sacs, forty original villa lots fronting Kings Lane have been reduced to 33 villa lots. General circulation is maintained in the broader development with through-traffic along Palmer Drive. Previous Preliminary Plat Updated Final Plat PUD Flexibility. The development was afforded the following flexibility through preliminary approval: a. Setbacks: Royal Golf Club at Lake Elmo Setbacks 100 Ft. Wide Lots 80-90 Ft. Wide Lots 55-65 Ft. Wide Lots Front 30 ft. 30 ft. 20 ft. for side loaded garages, or 25’ Side 10 ft. 10 ft. 10ft. house/5ft. garage or 7.5 ft./7.5 ft. Corner Side 15 ft. 15 ft. 15 ft. Rear 30 ft. 30 ft. 20 ft. b. Maximum Impervious Coverage: The maximum impervious coverage for 55-65’ wide lots shall be 50%. All other lots shall have a maximum impervious coverage of 40%. Villa Lots Villa Lots 4 c. Lot Sizes: The minimum lot size for Villa lots (55-65’ wide) in the development shall be 6,600 sq. ft. d. Attached Garages: That attached garages shall not exceed 1,300 sq. ft. in area at the ground floor level except by conditional use permit. The width of the visible garage door area when closed shall not exceed 60% of the principal building façade (including garage) fronting on the primary street. e. Subdivision Identification Signs: the Royal Golf Club at Lake Elmo residential subdivision shall be allowed up to a maximum of 4 subdivision identification signs, including the identification sign for the golf course entrance, not to exceed 24 sq. feet in sign area each, located no closer than 10 feet to any public right-of-way. In addition, neighborhood identification markers (pillars) shall be permitted to be no larger than 2 ft. x 2 ft. to identify the development logo and the name of the neighborhood. Additional subdivision signs should be considered for a subdivision of this size. f. All other requirements for the City’s GCC – Golf Course Community zoning district will apply, including the allowed uses and other site and development standards. g. That the proposed street names within the development are generally consistent with the City’s Street Naming Policy except for Annika Drive. Lot Sizes and Widths. The smallest lot size of this addition is 7,621 square feet, with the largest lot size at 25,251 square feet. The smallest lot width is 57.1 feet and the largest lot width is 131.1 feet. Density. The total area of the 3rd Addition is 103.70 acres. This total includes 20.56 acres of single-family residential lots, 6.62 acres of residential right-of-way, 4.75 acres of wetland, and 76.53 acres of outlots. Residential Density is therefore calculated as 103.70 – 4.75 Wetland = 98.95 / 67 units = 1.48 units per acre for the 3rd Addition. Outlots. An explanation of ownership and purpose of the outlots is below. • Outlot A will be owned by the HOA to be used for drainage and utility easement, landscaping, and open space purposes, and future residential development. • Outlot B will be owned by the HOA. A drainage and utility easement will be over all of Outlot B. • Outlot C will be owned by the HOA to be used for drainage and utility easement, landscaping, and open space purposes. Parkland Dedication. As approved with the Preliminary Plat, the developer is required to dedicate 8.8 acres of land or pay a cash contribution of $611,457.00 for the entire preliminary plat area (291 lots) and dedicate a total of 8,085 lineal feet of trails with a 30- foot wide corridor, less a 5,010 foot buffer encroachment. For this phase, the developer will be required to pay a cash contribution of $140,834.00, calculated as follows: 67 lots at $2,101.00 per lot. 5 A 30-foot-wide trail corridor was required to be dedicated to the City centered on public trails in the development and the value of the dedicated land was to be credited toward any fees in lieu of parkland dedication. The 3rd Addition does not include the trail corridor location, and therefore no reduction or credit is provided within this phase. Construction of a play structure near the HOA fitness center was a condition of the 2nd Addition Final Plat, which was originally required to be completed prior to the 3rd Addition Final Plat. The developer asked the City in July 2018 to change this condition of approval to delay the installation of the required play structure until the construction of the 3rd Addition as it was not practical and potentially unsafe to install it during the construction of the 2nd Addition. The city approved a revised condition that the developer install the play structure in Outlot D of the 2nd Addition before the city releases building permits for the 3rd Addition. Landscaping. The developer has provided landscaping plans for the 3rd Addition, which are attached hereto. The City’s Landscape Architect has reviewed the landscape plans and has recommended approval with the condition of adjusting the location of trees noted on sheet L4 that will overlap proposed buildings and drive locations when mature. It should be noted that the City approved an amendment to the Royal Golf Development Agreement which allowed the total number of trees in the development to be reduced from 3,800 warrantied trees to 2,912 warrantied trees, provided that the developer plant a minimum of two trees per villa lot and four trees per single-family traditional home lots. Further, the developer would reduce the number of trees required to be planted within the entire subdivision from 2,912 to 1,943 provided that the developer pay a park dedication fee of $500.00 per 2.5-caliper-inch tree in lieu of planting the difference of 969 trees. With this provision, the developer will be required to pay the City a cash contribution of $111,552 which is that proportion of trees associated within the 3rd Addition Final Plat. The calculation to determine the associated 3rd Addition Final Plat fee is as follows: [($500 X 969 2.5-caliper inch trees reduced within the entire preliminary plat area) / 291 Single Family Lots within all phases of the Subdivision X 67 Lots within the 3rd Addition] Street Design. As shown on the 3rd Addition Final Plat the Applicant has proposed to reconfigure the ‘loop’ road and instead develop two cul-de-sacs to serve the lots within the 3rd Addition. Both cul-de-sacs as shown meet the City’ ordinance requirements for cul-de-sac length, required right-of-way and cul-de-sac terminus. This change is generally consistent with the lot types shown on the Preliminary Plat and the cul-de-sacs do not change the character of the Plat. Street Naming. The City amended its Street Naming Policy at the April 17, 2018, removing the provision that if appropriate, names with the same theme (i.e. flowers, nature) are permitted for naming streets in an entire subdivision. While the proposed street names of Royal Golf Club at Lake Elmo do not fit the City’s now amended street naming policy, they are consistent with 1st Addition in that they are “golf-themed.” While the names have already been approved through the Preliminary Plat process, it was a condition of approval that the Final Plat include street names as approved by Council. Engineering Comments. The City Engineer review memo dated November 19, 2018 is attached to this report for your review and consideration. 6 Fire Chief and Building Official Comments. The application has been reviewed by the Fire Chief and Building Official, and they have provided no additional comments. Preliminary Plat Conditions. The following explains how Preliminary Plat conditions have been met (Staff comments italicized and bold). 1. That cross-access easements be recorded between the owner of the golf course/golf club and the HOA to permit HOA and resident access to the future fitness center, clubhouse and other amenities by the HOA residents over the clubhouse entrance drive and parking lot and trails. Comment: This easement has been granted. 2. Any expansion to the Royal Golf Club clubhouse or intensification of its use shall require a conditional use permit. Comment: The lot on which the clubhouse is situated was platted with 1st Addition, and this condition does not apply to 3rd Addition. 3. That there shall be no encroachments to drainage and utility easements on residential lots other than those reviewed and approved by the City Engineer and upon execution of an easement encroachment agreement. Comment: No encroachments are proposed or shown on the Final Plat. Staff has included this as a recommended condition of approval. 4. That the developer prepares an exhibit that clearly identifies the proposed setbacks for specific lots within the development. Comment: The developer has provided an exhibit which outlines setbacks within the development. The developer has been granted PUD flexibility which allows a 30 ft. setback on the 100 and 80-90 ft. lots and a 20 ft. setback on the 55-65 ft. lots; 10 ft. side yard setback on the 100 and 80-90 ft. lots and a 7.5 ft./7.5 ft. setback on the 55-65 ft. lots; a corner yard setback of 15 ft. on all lots; and a 30 ft. setback on the 100 and 80-90 ft. lots and a 20 ft. setback on the 55-65 ft. lots. This condition has been met. 5. Prior to the execution of a Final Plat for any phase of the development by City officials, the Developer shall enter into a Developer’s Agreement for that phase acceptable to the City Attorney and approved by the City Council that delineates who is responsible for the design, construction, and payment of the required improvements with financial guarantees therefore. A development agreement will be prepared by Staff and approved by both the developer and City Council. 6. Each phase of the Royal Golf Club at Lake Elmo shall be incorporated into the Common Interest Agreement concerning management of the common areas and establish a homeowner’s association which shall be submitted in final form to the Planning Director before any building permit may be issued for any structure in any phase of the development. Said agreement shall comply with Minnesota Statues 515B-103, and specifically the provisions concerning the transfer of control to the future property owners. The HOA documents shall include required maintenance of wetland buffers. The Common Interest Agreement will need to be updated to include Royal Golf Club at Lake Elmo 7 3rd Addition and approved by the City Attorney prior to recording of the Final Plat. 7. That the HOA documents include architectural requirements that require 4- sided architecture and garages facing the public right-of-ways to have windows and/or other architectural features. Consistent with the 1st Addition and 2nd Addition, the 3rd Addition of Royal Golf Club at Lake Elmo shall be added into the HOA documents that establish the architectural standards consistent with this condition. The Applicant shall furnish this language to the City Staff for review prior to any building permit being issued for the 3rd Addition. 8. The applicant shall enter into a landscape license and maintenance agreement with the City that clarifies the individuals or entities responsible for any landscaping installed in areas outside of land dedicated as public park and open space for each platted phase of the development. This has been added as a recommended condition of approval of the 3rd Addition Final Plat. 9. That the HOA be responsible for the maintenance of all landscape walls that cross residential property lines or publicly owned Outlots or rights-of-way and that the walls be contained within a landscape easement. As shown on the Landscape Plans, there are no retaining walls proposed as part of the 3rd Addition. 10. The developer shall provide for an HOA owned and maintained children’s play structure or other similar improvement near the HOA fitness center as discussed by the developer during the PUD concept review. The 2nd Addition Final Plat required that the play structure near the HOA fitness center be installed prior to the application for the 3rd Addition Final Plat. As noted above, the developer as not yet installed the required play structure and so staff is recommending the City require the developer install the play structure in Outlot D of the 2nd Addition before the release of building permits in the 3rd Addition. This is consistent with the revised condition of approval approved by the city earlier this year. 11. That a fee in lieu of park land dedication be paid to the City based upon an appraisal by an appraiser to be chosen by the City and paid for by the developer. Also, that a 30 ft. wide trail corridor be dedicated to the City centered on public trails in the development and that the value of the dedicated land be credited toward any fees in lieu of parkland dedication. The park land dedication shall not include wetlands, wetland buffer area, and no credit will be given for land beyond the 30 ft. centered on public trails. And lastly, that the cost of constructing any public trails within the dedicated park land be credited towards any fees in lieu of park dedication. The portion of park land dedication fee due for the 3rd Additional Final Plat has been calculated and added as a proposed condition of approval. As stated in previous sections of this report, there is no portion of the 30-foot wide trail corridor in this phase and therefore no credit to the fee is due. 8 12. That a trail phasing plan be submitted by the developer to be approved by City Staff and that the public trails be constructed within each phase prior to building permits being issued for that phase of development. This condition has not yet been met as the developer has not paved the required trail. City staff agreed to allow the developer to pave the trail in spring to help ensure a better finish rather than having the developer install the trail this fall as it was cold and wet – making a proper installation of the pavement difficult. 13. That a 10’ wide trail segment be provided from Palmer Drive (on preliminary plans) to the east edge of the plat within the County Right-of-Way. This condition has been met. 14. That the Tree Preservation Plans and Preliminary Landscape Plans be updated to comply with the City’s tree preservation requirements and the City’s landscape requirements for review and approval by the City prior to recording the Final Plat. The developer has submitted updated Tree Preservation and Preliminary Landscape Plans approved by the City. Additional comments from the City’s Landscape Architect specific to the 3rd Addition are attached to this report. 15. The developer consider woodland management and pollinator friendly native seeding in lieu of some required tree preservation replacement tree requirements as recommended by the City’s Landscape Architect. The developer requested and the City approved a Development Agreement amendment which no longer requires that trees planted within single family lots be warrantied. This reduced the number of trees required within the development from 3,800 to 2,900. The developer also submitted, and the City approved a preliminary landscape plan which further reduces the number of trees within the development from 2,900 to 1,943. The developer will be required to pay a park land dedication fee of $500 per 2.5 caliper inch tree not planted within each addition, totaling $478,500 for the entire development. The portion of park land dedication fee associated with the 3rd Addition is calculated and included as a condition of the 3rd Addition Final Plat. 16. All changes and modifications to the plans requested by the City Engineer in the Engineer’s report dated, March 8, 2017 and June 1, 2017 shall be incorporated into the preliminary plat and PUD plans. The developer has submitted updated preliminary plat and PUD plans that have been approved by the City. 17. The Preliminary Plat approval is conditioned upon the applicant meeting all City standards and design requirements unless specifically addressed otherwise in this resolution. It is a recommended condition of Final Plat approval that the developer meet all City standards and design requirements. 18. The developer shall comply with all comments identified within the Washington County letter dated March 6, 2017, including providing an additional 17 feet of right-of-way along 10th Street N. and constructing turn lane improvements meeting Washington County standards at the developer’s sole expense. It is a recommended condition of Final Plat approval that the developer comply with these comments. This condition does not apply to the 3rd Addition. 9 19. That the preliminary PUD Plans be approved by Valley Branch Watershed District and that evidence be provided that all conditions attached to a Valley Branch Watershed District permit be provided prior to the commencement of any grading activity on the site. The preliminary PUD Plans were approved by the Valley Branch Watershed District, and grading activity on the site has already commenced. 20. That open space within the shorelands of the residential development be protected with a conservation easement and that conservation easements be provided for review by the City Attorney and to be executed prior to Final Plat approval. It is a recommended condition of Final Plat approval that the developer provide these easements on Outlots H, F, E, B, D, C, A, L are all within the shoreland. None of the identified outlots from the Preliminary Plat are located within the 3rd Addition Final Plat; therefore this condition does not apply to the 3rd Addition Final Plat approval. 21. That golf carts shall be prohibited on city streets and city trails unless specifically allowed by City Ordinance. The City approved an ordinance which allows golf carts on local streets through the adoption of Ordinance 08-209 on May 15, 2018. 22. Prior to the issuance of building permits all wetland buffers shall be delineated and identified via staking or signage that is acceptable to the City. This is a recommended condition of Final Plat approval. 23. The applicant must provide the city a letter of approval to perform the proposed work in the gas pipeline easement within the development area as a condition of preliminary plat approval. This condition is not applicable to 3rd Addition. 24. Prior to the construction of any subdivision identification signs or neighborhood markers within the development, the developer shall submit sign plans for review and obtain a sign permit from the Planning Department. This is a recommended condition of Final Plat approval. 25. That the preliminary plat be updated to include street names that are consistent with the City’s street naming ordinance and approved by the City Council. This condition is met; see approved street naming conventions above. 26. The developer shall follow all of the rules and regulations spelled out in the Wetland Conservation Act and shall acquire the needed permits from the appropriate watershed districts prior to the commencement of any grading or development activity on the site. This is a recommended condition of Final Plat approval. 27. The developer shall enter into a separate grading agreement with the City prior to the commencement of any grading activity in advance of Final Plat and PUD plan approval. The City Engineer shall review any grading plan that is submitted in advance of a Final Plat and said plan shall document extent of any proposed grading on the site. This condition has been met. 10 28. The developer shall submit a revised preliminary plat and plans meeting all conditions of approval. All of the above conditions shall be met prior to the City accepting an application for Final Plat. This condition has been met. 29. That approval of the preliminary plat be contingent on Street D access to 10th Street. This condition has been met and does not apply to the 3rd Addition. 30. That the Royal Golf Club development will not have street lights except at street intersections and cul-de-sacs. This is a recommended condition of Final Plat approval. 31. That the developer work with the adjacent property owners to get an agreement in place for screening and that it be incorporated into the final landscape plans. The developer has had landscape plans approved by the Homestead neighborhood, and the submitted landscape plans for Final Plat are consistent with this approved landscape plan. 32. That the developer address the Public Works Director’s concerns as they pertain to the lift station designs as identified in a Public Works memorandum dated 5/19/2017. This condition has been met. 33. That a $1,000,000 donation to the Parks fund will be made with the phase of development when the former Tartan Park ballfields are no longer able to be used by the City. Development of the 3rd Addition affects the ballfields at former Tartan Park, therefore this requirement is added as a condition of Final Plat approval for the 3rd Addition. The developer will be required to make this donation to the City at the time the ballfields become unusable by the City (this includes storage of construction material, etc.) and before the City releases the final plat for recording. Recommended Findings. Staff recommends the following findings: 1. That all the requirements of City Code Sections 153.07 and 154.759 related to Final Plat and Final PUD Plans have been met by the Applicant. 2. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans are generally consistent with Preliminary Plat and PUD Plans approved by the City of Lake Elmo on June 6, 2017. 3. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans are consistent with the Lake Elmo Comprehensive Plan and the Future Land Use Map for this area. 4. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans generally comply with the City’s GCC - Golf Course Community zoning districts as modified by the PUD regulations. 5. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat PUD Plans comply with the City’s subdivision ordinance. 11 6. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans comply with the City’s Planned Unit Development Regulations. 7. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans comply with the City’s Engineering Standards, except where noted in the review memorandum from the City Engineer dated November 19, 2018 and modified by PUD regulations. 8. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans generally comply with other City zoning ordinances, shoreland, and erosion and sediment control, except as noted in this staff report and review memorandum from the City Engineer dated November 19, 2018. 9. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans generally comply with the City’s landscaping and tree preservation ordinances, providing some flexibility to the Applicant to allow for woodland management and pollinator friendly native seeding in lieu of some required tree replacement in order to avoid possible detriment caused by over planting. 10. That the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans achieve multiple identified objectives for planned developments within Lake Elmo. 11. That the proposed Final Plat and PUD Plans are for the 3rd Addition of 67 single family residential units of a 291-unit total residential golf course community Planned Unit Development on 103.7 acres of land (of 231 acres total) located on the former 3M Tartan Park properties. 12. That the Final Plat and PUD Plans will be located on property legally described on the attached Exhibit “A”. 13. That there has been significant public testimony that 20th Street is already dangerous without the additional traffic and that the City and developer need to explore ways to make the road safer. 14. That the proposed PUD will allow a more flexible, creative, and efficient approach to the use of the land, and will specifically relate to existing zoning district standards in the following manner (with exceptions as noted): a. Setbacks: i. Royal Golf Club at Lake Elmo Setbacks 15. 16. 100 Ft. Wide Lots 17. 80-90 Ft. Wide Lots 18. 55-65 Ft. Wide Lots 19. Front 20. 30 ft. 21. 30 ft. 22. 20 ft. for side loaded garages, or 25’ 23. Side 24. 10 ft. 25. 10 ft. 26. 10ft. house/5ft. 12 garage or 7.5 ft./7.5 ft. 27. Corner Side 28. 15 ft. 29. 15 ft. 30. 15 ft. 31. Rear 32. 30 ft. 33. 30 ft. 34. 20 ft. a. Maximum Impervious Coverage: The maximum impervious coverage for 55- 65’ wide lots shall be 50%. All other lots shall have a maximum impervious coverage of 40%. b. Lot Sizes: The minimum lot size for Villa lots (55-65’ wide) in the development shall be 6,600 sq. ft. c. Attached Garages: That attached garages shall not exceed 1,300 sq. ft. in area at the ground floor level except by conditional use permit. The width of the visible garage door area when closed shall not exceed 60% of the principal building façade (including garage) fronting on the primary street. d. Subdivision Identification Signs: The Royal Golf Club at Lake Elmo residential subdivision shall be allowed up to a maximum of 4 subdivision identification signs, including the identification sign for the golf course entrance, not to exceed 24 sq. feet in sign area each, located no closer than 10 feet to any public right-of-way. In addition, neighborhood identification markers (pillars) shall be permitted to be no larger than 2 ft. x 2 ft. to identify the development logo and the name of the neighborhood. Additional subdivision signs should be considered for a subdivision of this size. i. Staff Note: If the developer requests a change to this, a variance should be requested. e. All other requirements for the City’s GCC – Golf Course Community zoning district will apply, including the allowed uses and other site and development standards. f. That the proposed street names within the development are generally consistent with the City’s Street Naming Policy as amended April 17, 2018. g. The developer has not yet constructed an HOA-owned and maintained play structure as required by the original condition of approval of the 2nd Addition Final Plat. Recommended Conditions of Approval. Staff recommends the following conditions of approval: 1. That there shall be no encroachments to drainage and utility easements on residential lots other than those reviewed and approved by the City Engineer and upon execution of an easement encroachment agreement. 2. Prior to the execution of Final Plat, the Developer shall enter into a Developer’s Agreement acceptable to the City Attorney and approved by the City Council that 13 delineates who is responsible for the design, construction, and payment of the required improvements with financial guarantees therefore. 3. The Royal Golf Club at Lake Elmo 3rd Addition shall be incorporated into the Common Interest Agreement concerning management of the common areas and establish a homeowner’s association (HOA) which shall be submitted in final form to the Planning Director before any building permit may be issued for any structure in any phase of the development. Said agreement shall comply with Minnesota Statues 515B-103 and specifically the provisions concerning the transfer of control to the future property owners. The HOA documents shall include required maintenance of wetland buffers. 4. That the HOA documents include architectural requirements that require four-sided architecture and garages facing the public rights-of-way to have windows and/or other architectural features. 5. The applicant shall enter into a landscape license and maintenance agreement with the City that clarifies the individuals or entities responsible for landscaping. 6. The developer shall provide evidence of an HOA owned and maintained children’s play structure or other similar improvement has been constructed within Outlot D of the 2nd Addition before the release of building permits for the 3rd Addition. 7. That a fee in lieu of park land dedication be paid to the City based upon an appraisal by an appraiser to be chosen by the City and paid for by the developer. 8. That the developer pay a parkland dedication fee equal to $500 per 2.5 caliper inch required in lieu of some required tree preservation replacement tree requirements, totaling $111,552.00 in lieu of planting the required number of trees required. This fee was calculated as follows: $500.00 multiplied by 969 2.5-caliper inch tree not planted within the entire subdivision, divided by 291 single family lots within the entire subdivision, multiplied by 67 single family lots within the 3rd Addition. 9. All changes and modifications to the plans requested by the City Engineer in the Engineer’s review memo dated November 19, 2018 shall be incorporated into the Final Plat and PUD Plans. The Applicant should note the requirements for VBWD permits for temporary storm water management. 10. The Final Plat and PUD Plans approval is conditioned upon the applicant meeting all City standards and design requirements unless specifically addressed otherwise in this resolution. 11. Prior to the City issuing building permits, all wetland buffers shall be delineated and identified via staking or signage that is acceptable to the City. 12. Prior to the construction of any subdivision identification signs or neighborhood markers within the development, the developer shall submit sign plans for review and obtain a sign permit from the Planning Department. Any amendments to the finding regarding signs indicated in this Resolution shall be subject to a PUD amendment or variance. 13. That the Final Plat include street names as approved by Council. 14. The developer shall follow all of the rules and regulations spelled out in the Wetland Conservation Act and shall acquire the needed permits from the appropriate 14 watershed districts prior to the commencement of any grading or development activity on the site. 15. That the Royal Golf Club development will not have street lights except at street intersections and cul-de-sacs. 16. That the developer make a $1,000,000 donation to the City Parks fund when construction of the 3rd Addition prohibits use of the former Tartan Park ballfields, including construction materials storage and before the city releases the 3rd Addition final plat for recording. 17. The location and spacing of the trees that overlap the buildings and on edge of driveway when shown at mature diameter is adjusted and resubmitted on a revised landscape plan, per the Landscape Review memo, dated November 8, 2018. 18. The developer shall pave the unfinished trail in the 2nd Addition as soon as favorable conditions are available in the spring of 2019. The City may choose to not release building permits for the 3rd Addition in the spring of 2019 if the developer has not completed the required trail paving in a timely manner. EASEMENT VACATION Reason. The Applicant is requesting an easement vacation over Outlot T of Royal Golf Club at Lake Elmo. These drainage and utility easements were dedicated to the City with the Final Plat. This outlot will be re-platted with the 3rd Addition. In order to avoid “stacking easements” and to keep the title clean for future owners/users of the parcels, the Applicant is requesting that the easements be vacated with dedication of new easements. Outlot T will be dedicated right-of-way, residential lots, and become Outlot C for wetland and future development of the 4th Addition. Recommended Condition of Approval. Staff is recommending approval, subject to the following condition of approval: 1. New easements on Outlot T as requested by the City Engineer and Public Works Director shall be recorded with the Royal Golf Club at Lake Elmo 3rd Addition Final Plat. RECOMMENDATION: Staff recommends that the City Council approve the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans, as well as the easement vacation request, based on the findings of fact and conditions outlined in the Staff Report. “Move to approve the Royal Golf Club at Lake Elmo 3rd Addition Final Plat and PUD Plans based on the findings of fact and conditions outlined in the Staff Report.” “Move to approve the easement vacation request to vacate existing drainage and utility easements over Outlot T, subject to conditions of approval.” 15 ATTACHMENTS: 1. Final Plat Application and Narrative – October 15, 2018 2. 3rd Addition Final Plat 3. City Engineer’s Review Memo – November 19, 2018 4. 3rd Addition Landscaping Plans 5. Landscape Architect’s Review – November 8, 2018 6. Easement Vacation Application – October 16, 2018 T IIE C ITY O F U\KEELMO FINAL PLAT APPLICATION REQUIREMENTS 1 All Subdivisions of Land creating four (4) or more lots This h andout is intended to provide guidance on putting together and submitting a Final Plat appl ication for the subdivision of property in Lake Elmo. The purpose of the Final Plat is to incorporate all conditions placed on the Preliminary Plat application into th e final plans, and to finalize a ll documentation for legal recording at the County. This steps completes the subdivision process. In order to have your Final P lat application be complete and reviewed in a timely fashion, there are a number of steps that must be followed: 1. Pre-submittal Meeting: Contact City Staff to discuss the status of any outstanding Preliminary Plat conditions, to discuss the requirements for Final Plat app lication submittal and obtain another land use application. 2. Final Plat Submittal: Prepare an informational packet (described herein) that fulfills the Final P lat submittal requirements . Providing a detailed and thorough app lication packet will greatly reduce the overall review time. Submit your completed packet to Staff to initiate review. 3. Completeness Review: Staff will examine your submittal to determine if the application is complete, and contact you if additional information is required or was omitted. It is to your advantage to submit your materials as early as possible so Staff can assist you in meeting all requirements. Applications found to be incomplete will be returned to the applicant. 2 4. Final Plat Review/Processing: Staff will process completed applications. This process typically requires at least one applicant revision and resubmittal of plans to work through review comments. The process may also include additional applicant meetings, requesting review comments from partnering agencies, and writing reports. 5. Planning Commission Meeting: Once the plans are revised to full y meet the Zoning and Subdivision Ordinance and Engineering Design Standards as outlined by Staff, planning and engineering reports are prepared and the item is scheduled for the next available Planning Commission meeting (2nd or 4 th Monday of the month3). 1 The information provided in thi s document is intended to be a correct statement of the law as set forth in the Lake Elmo City Code and the laws of the State of Minnesota. However, the applicant should refer to the actual sources and consult with their own legal advisor regarding applicability to their application. In providing this information, the City makes no representations nor provides any legal advice or opinion. 2 Minnesota State Statute 15 .99 requires local governments to review an application within 15 business days of its submission to detennine if an application is complete and/or if additional information is needed to adequately review the subject request. 3 Staff will determine when applications are reviewed based on the time needed to review the application and the number of items already scheduled on future agendas. Please note that meeting dates are ange due to holidays, lack of quorum, etc. Please contact City Hall to confirm all dates and times. f'i,wl !'/in Ap11liwrio11 Handow Ci1_r u/Lake E/1110 6. Revisions: If needed, the Final Plat is revised to address the Planning Commission 's recommendation(s) and any outstanding review comments prior to City Council consideration. 7. City Council Meeting: Once the plans are finalized and ready for the City Council's consideration, staff reports are prepared and the Final Plat is placed on the next available City Council meeting agenda (1 st or 3rd Tuesday of the month3). Applicants are advised to attend both the Planning Commission and City Council meetings and be open to questions regarding the request. 8. Decision: The City Council will review the request and either grant or deny the Final Plat. 9. Title Work: If the Final Plat application is approved by the City Council, all title work must be reviewed and approved by the City Attorney before the plat is recorded by the County. The applicant shall provide evidence in a form satisfactory to the City Attorney that he/she has fee interest in the subject property. Above all else, it is imperative that an applicant begin preparations as early as possible and to ensure that a complete application is submitted. Review by the Planning Commission will not occur until at least three weeks have passed from when the City has deemed the application complete. Final Plat Fees: The City Council has established a non-refundable fee 4 for processing Final Plat applications. Please see the current fee schedule on our website. In addition, the City requires that the applicant enter into an Escrow Agreement with the City and post an $8,000 escrow to reimburse the City for all technical planning, engineering, public works and legal review. You will find that a great deal of the information requested for a Final Plat application matches the requirements for Preliminary Plat application submittal. While we have your original applications, the City does require that all applicants submit a new and complete application at every stage of the development process (updating information as needed). This allows us to track changes as the application progresses through the various levels ofreview. With this in mind, the following materials must be submitted prior to deeming an application complete: Sub: Reg: □ □ I. Item: A completed land use application form signed by all property owners along with payment of the proper filing fee, escrow and escrow agreement. 4 Applicant is also responsible for any additional fees incurred by the City (i.e. engineering, planning, po stage, legal expenses, et cetera). 2 F'inal Plat 1pp/icatiou Handout Ci(y of Lake Elmo D D 2. Written statements providing information regarding your proposal. Please provide a separate answer for each of the lettered items listed below ( answers must be submitted in both hard copy and electronic form--MS Word format or PDF): a. A listing of contact information including name(s), address(es) and phone number(s) of: the owner of record, authorized agents or representatives, engineer, surveyor, and any other relevant associates. b. A listing of the following site data: Address, current zoning, parcel size in acres and square feet, property identification number(s) (PID), and current legal description(s). c. Final Subdivision and Lot Information: i. The name of the Final Plat. ii. A table listing the lot and block number, size of lot, width of lot, and depth of lot. iii. Final exact area calculations of parks, trails, and any other dedicated public open space; and estimated values of all dedicated land and improvements (trails, park equipment, sports fields, etc.). iv. Final exact area calculations of wetlands and buffers. v. Final proposed area calculations for all dedicated right-of-ways. vi. Proposed legal descriptions for: all lots, easements to be created (if not being dedicated on the plat), and easements to be vacated (if any). d. An explanation of how issues have been addressed since the Preliminary Plat phase of the development. e. A statement showing the final density of the project with the method of calculating said density shown. f. Discuss proposed infrastructure improvements and phasing thereof (i.e. proposed roadways, sewer systems, water systems, sidewalks/trails, parking, etc) necessary to serve the subdivision. g. If applicable, a narrative addressing how concerns/issues raised by neighboring properties have been addressed ( discussing your proposal with the neighboring land owners is recommended to get a sense of what issues may arise as your application is processed). h. If applicable, a description of how conflicts with nearby land uses (livability, value, potential future development, etc.) and/or disturbances to wetlands or natural areas are being avoided or mitigated. i. Provide justification that the proposal will not place an excessive burden on roads (traffic), sewage, water supply, parks, schools, fire, police, or other public facilities/services (including traffic flows) in the area. 3 Final Plat Application Handout Ci(Y uf Luke Eb'.~;. 0 0 3. Final Grading Plan: The developer shall submit a final grading, drainage and erosion control plan utilizing a copy of the current certificate of survey as a base for the site in question, prepared and signed by a Minnesota licensed engineer, depicting the following information: D O 4. North arrow and date of preparation. D O 5. Graphic Scale ( engineering scale only, not less than one (1) inch equals fifth (50) feet). D D 6. For each lot, provide lot and block numbers, building pad location, building type and proposed building first floor elevation, low floor elevation and elevation at garage slab. 0 0 7. Stormwater Management Plan, with a narrative, including the configuration of drainage areas and calculations that meet the requirements of the City Code and/or applicable Watershed Standards. 0 0 8. Location of all natural features on the tract. Natural features are considered to include, but are not limited to the following: tree lines, wetlands, ponds, lalces, streams, drainage channels, bluffs, steep slopes, etc. □ □ □ □ □ □ □ □ □ □ □ □ □ □ □ □ □ □ Final Grading, Drainage and Erosion Control Plan continued: 9. All delineated Wetlands and watercourse buffers per the City and Watershed standards; and wetland replacement plan, if needed. 10. Location of all existing storm sewer facilities, including pipes, manholes, catch basins, ponds, swales, and drainage channels within one hundred fifty (150) feet of the tract. Existing pipe type, grades, rim and invert elevations and normal and high water elevations must be included. 11. Normal water level (NWL) and 100-year high water level (100- year HWL) for all water bodies, existing and proposed. 12. Spot elevations at drainage break points and emergency overflows (in BOLD) with directional arrows indicating site, swale and lot drainage. 13. Retaining Walls (wall heights and elevations). 14. Locations, grades, rim and invert elevations of all storm sewer facilities, including ponds and BMP's proposed to serve the tract. 15. Locations and elevations of all street high and low points. 16. Street grades shown. 17. Provide phasing plan for site grading. 7 Final Plat Application (!cmc!~;;;1.tt _______________ _ ____ _;;C;,;aic;;;Y o;;:>f.;;L,ake Elnw. □ □ □ □ □ □ □ □ □ □ 7. Water Supply, Public: Water mains shall be provided to serve the subdivision by extensi,;m of an existing community system wherever feasible. Service connections shall be stubbed to the property line. Extensions of the public water supply system shall be designed so as to provide public water in accordance with the engineering design standards as approved by the City Engineer and in accordance with the City's Comprehensive Water Plan. The Final Utility Plan shall indicate the location of all hydrants and valves. 8. Water Supply, Private: In areas where public water supply is not available, individual wells shall be provided on each lot, properly placed in relationship to the individual sewage disposal facilities. Well plans must comply with the State Well Code, as may be amended, and be submitted for the approval of the City Engineer. 9. Sewage Disposal, Public: Sanitary sewer laterals and service connections shall be installed in accordance with the design standards of the City as approved by the City Engineer. The Final Utility Plan shall provide the locations, grades, rim and invert elevations, and sizes of all proposed sanitary sewer facilities to serve the tract. Final Utility Plan continued: 10. Sewage Disposal, Private: All individual sewage treatment systems shall be installed in accordance with all applicable State, County, and City requirements. 11. Other information as required and outlined in the City Plan Sheet Format Requirements. D Final Street & Storm Sewer Plan: Sub: Reguired: Item: D D I. Appropriate identification of the drawing as a "final street & storm sewer plan." D D 2. Administrative information as required for the preliminary plat D D 3. Final Street and Stonn Sewer Plan, prepared and signed by a Minnesota licensed engineer, depicting the following information: D D 4. Layout of proposed streets showing the proposed lot lines, right- of-way widths, and proposed names of streets in conformance with the County Uniform Street Naming and Addressing System. 9 Final Plut Application lf~1;do_,;;;u1_, __ _ City of Lake Elmo. -------------------------'--"----· 0 0 4. Indicate how the proposed subdivision will relate to potential future subdivisions of adjacent properties (you may need to ghost plat development on adjacent properties to establish this relation). 0 Electronic files Sub: Required: Item: 0 0 1. A cd or flashdrive must be submitted which includes electronic files for the written statements regarding the proposal, the plat and all associated plans. Staff can generally work with most file formats (.jpg or .pdf files are preferred). Sub: Reg: Item: □ □ 4. □ □ □ □ □ □ □ □ □ □ □ □ □ □ □ □ Supplemental Information. Depending upon the submittal, the following items may also be required: Feasibility report(s) for proposed individual on-site sewer and water systems. Such reports will be required with any future plat; Supplemental Information continued: Proposed protective covenants; Ten (10) copies of a context diagram that graphically depicts how the development plan relates to its surrounding neighborhood or community context including the pedestrian, bike, and street (vehicular access) network (existing and potential); A Traffic Impact Study (TIS) ( 6 copies) prepared in accordance with State, County and/or City Engineering guidelines; A soil survey and report; Signed letters of intent indicating that all required off-site easements and off-site rights-of-way necessary for the project could be negotiated and obtained; A hydrological/groundwater report; Any other special natural area or environmental study or report pursuant to Lake Elmo Code as requested by the City, if such exists or is deemed necessary; 12 Final Plat Applic:ati,'!n Handow Cizv vf Lake Elmo □ □ Any other information required by Staff, Commissioners, or Council Members necessary to provide a complete review of tbe preliminary plat and associated plans 7. Additional items include: Sub: Reg: Item: □ □ 5. Variances: If you are requesting variances in any portion of the submitted Final Plat, the City asks that you list each of tbe requested variances and provide an explanation as to why each is necessary and cannot be avoided. Additionally, you must provide written answers to the following questions: (I) Identify the unusual hardship on tbe land tbat necessitates tbe variance request; and (2) Explain the nature of the proposed use of land and the existing use of land in the vicinity of the property; and (3) Estimate the number of persons to reside or work in tbe proposed subdivision; and (4) Indicate tbe anticipated effect of the proposed subdivision upon traffic conditions in the vicinity. Sub: Reg: Item: □ □ 6. Additional Applications: If your request involves a rezoning request, additional applications will be required. □ □ Zoning Map Amendment Application Upon City Council approval of Final Plat, and prior to any construction commencing, a pre- construction meeting must occur for botb grading and street utility construction. These meetings may be combined into one meeting provided all items on both check lists are completed. Pre- construction meetings may not occur before tbe City Council approves tbe Final Plat and Development Agreement. Checklist for Pre-Constructiou Conference for Grading I. 2. □ □ Payment of Development Fees Issuance of securities on City of Lake Elmo approved form 7 Number of copies, size, and other such administrative details may also be imposed when requiring additional information. 13 Final Plat Applica._li_o,_, f_I_w_ul_01_1t ______________ _ Ci(y of Lake Eb-no 3. 4. 5. 6. 7. 8. □ Copy of Certificate of Insurance for both Developer and General Contractor identifying City of Lake Elmo as additional insured on City of Lake Elmo approved form □ Copy ofNPDES card □ Grading specifications □ Proposed construction schedule □ List of subcontractors and contacts □ List of materials and suppliers Prior to grading operations commencing, contractor shall install all perimeter erosion control and other required erosion control best management practices and have the site inspected and approved by the City of Lake Elmo's Water Resource Manager. Checklist for Pre-Construction Conference for Streets and Utilities I. 2. 3. 4. 5. 6. 7. 8. 9. □ □ □ □ □ □ □ □ □ Payment of Development Fees Issuance of securities on City of Lake Elmo approved form Street and Utility Pre-Con Checklist continued: Copy of Certificate of Insurance for both Developer and General Contractor identifying City of Lake Elmo as additional insured on City of Lake Elmo approved form Approved construction plans and specifications. (Note: these may not be the same as the approved Final Plat Street and Utility Plans. Questions about construction plans and specifications should be directed to the City Engineer) Minnesota Department of Health Watermain Permit Minnesota Pollution Control Agency Sanitary Sewer Extension Permit Proposed construction schedule List of subcontractors and contacts List of materials and suppliers 14 Final!'fa!APP/iC(l(ion Han_d_o_111_. ________________ , ________ C"""i~v.ef~ State Statutes provide City staff with fifteen (I 5) business days to review an application to determine if it is complete. Applications found to be incomplete will be returned to the applicant. Please contact staff at (651) 747-3900 if you have any questions. Thank you! This handout last updated on 6/9/2016 15 Washington ~-a County PARCEL SEARCH APPLICATION PUBLIC WORKS DEPARTMENT SURVEY DIVISION 11660 Myeron Road North Stillwater, Minnesota 55082 PHONE (651) 430-4300 EMAIL Publicworks@co.washington.mn.us I Payment Date: I Parcel Search File No: Chec ks pa yab le to WASHING TON COUNTY ~I _Pa~y_m_e_n_t T_y~p~e_: -----~ REQUEST FOR SURROUNDING PROPERTY OWNERS AND ADDRESSES List of owner names and addres ses for parcels located withi n 350 feet of: Parcel Identification Number(s): City of Lake E lmo will mail out Property Owner Royal Developme nt Inc. Emai l afurlonoln)rovalclubmn.com Applicant (if different than owne r) Business (if applicable) Mailing labe ls Yes ✓ No # of sets of labels: Parcel Search Fees Property Address -City, State and Zip 11 455 20th Street N , Lake E lmo, MN 55042 Phone 651-505-9079 M a iling Addres s -City, State and Zip Date needed: Mail report Pick up report P hone 1st 25 parcels, including subject parcel ($50.00) $ ____ _ # of additional parcel s __ x .50 l sheet of 30 labels ($1.00/set) # of additional s heets of labels x 1.00 Postage, if parcel search is mailed ($2.00) Fe e, if parcel s earch is faxed ($2 .00) Amount due: Total # of parce ls ___ _ Total # of labels Completion date Service Rep $ ____ _ THIS INFORMATION WAS COMPILED FROM WASHINGTON COUNTY SURVEYOR MAPS AND COUNTY ASSESSOR DATA FILES. THE SURVEYOR'S OFFICE IS NOT RESPONSIBLE FOR ANY INACCURACIES IN THE INFORMATION RELIED UPON IN THIS PARCEL SEARCH. A n Eq ual Employ m e nt Opportunity/Affirma tive A c tio n E m p loyer J :\I.ANOUSE\lin:il\Ap pFomu\A1>ps\Parcel Se an:h App po.It' l'I It: CITY OF U\KEELMO City of Lake Elmo Escrow Agreement for Municipal Review Services Deposit Agreement THIS AGREEMENT is made this J1_ day of Qc.Job.,.r 201 tJ by the Applicant and Owner (hereinafter individually and collectively referred to as "Applicant") in favor of the City of Lake Elmo, a municipal corporation of Minnesota (hereinafter referred to as "City"). A. "Applicant" whose name and address is: Royal Development Inc. 11455 20th Street N ' Lake Elmo MN 55042 B. "Owner" whose name and address is: H.C. Golf Land. LLC. 941 Hillwind Rd NE STE 301 Fridley. MN 55432 RECITALS WHEREAS, the Applicant has applied to the City for approval for one or more of the following: (Circle One) D 1. Concept/ Sketch Plan D 2 Preliminary Plat [!] 3. Final Plat D 4. Planned Unit Development D 5. Open Space Development D 6. Conditional Use Permit D 7. Commercial Zoning / Use D 8. EAW Review WHEREAS, the App licant acknowled ges the receipt of benefit to the property, from the City's technical and compliance review of the application; and WHEREAS, under authority granted to it, including Minnesota Statutes Chapte r s 412 and 462 , the City will process the application on the condit ion that the App licant enter into this Deposit Agr ee ment, which agreement defines certain duties and respo nsibilities of the Applicant, as well as the City; and the Applican t shall provide cash to the City in the amount satisfactory to the City; and provide security to the City for the payment of all review costs incurred by the City. NOW THEREFORE, the City and Applicant agree as follows: 1. Requirement. The Applicant is required to make the necessary deposits prior to the process of municipal planning, public works, legal & engineering review commences. 2. Review Process. Applicant acknowledges and agrees that the City shall commence to review and process the review request checked above at such a time that this Agreement is executed by all parties and the cash required for the specific review is deposited and posted by the City's Finance Department. The City may provide a review completion schedule to the Applicant at the time of deposit. The City reserves the right to modify the schedule based on the completeness of the application, the need for additional information for review, or revisions to the application that may occur during the scheduled review. 3. Use of Deposited Funds. The City may draw upon the deposits to pay the costs it incurs in connection with reviewing the application. The City shall determine .all of its costs, including both administrative and consulting services, at the rates charged by the City or its consultants, determined according to the City's adopted fee schedule. A copy of the current administrative and consulting rates is attached as Exhibit "A", which rates are subject to change by the City, without notice to the Applicant. Exhibit "A" should not be construed as an exhaustive list of consultants and Applicants shall be responsible for all other consulting fees related to the application. The City shall provide Applicant with the applicable rates for consultants used in the review prior to commencement. This Agreement does not pertain to ancillary charges incurred by reviewing of other governmental bodies, including but not limited to, Soil & Water Conservation Districts, Washington County Government, Water Shed, or any other unit of government that may, by right,have review authority. 4. Conditions of Deposit. The following stipulations and conditions shall apply to the deposit account for review services contemplated under this Agreement. a. Payment shall be made to City consultants, included but not limited to legal and planning, in the amounts billed to the City, according to consulting rates in effect at the time of the execution of the agreement. Such consulting deemed necessary for the proper review of the application shall be at a usual and customary rate as it relates to the subject matter of the application for payment as determined by the City. b. The City shall reimburse itself from deposit accounts for all costs and expense incurred by the City in connection with the implementation and enforcement of this Agreement. Reimbursement shall occur on a monthly basis and the City's Finance Department shall notify Applicant of the reimbursement via account reconciliation report. c. The City shall not be responsible for paying any interest on the money deposited under the Agreement. d. If in the discretion of both the City's Finance Department and the Community Development Department, there is deemed to be an inadequate balance in the deposit account to pay for all fees and costs incurred by the City, the City will notify the Applicant for the need for an additional deposit. The total of the additional deposit shall be calculated by City staff based on the amount of work yet to be completed in the review of the application. Applicant agrees to make the additional deposit within (10) days of a receipt of such notice. For purposes hereof, receipt of notice shall be deemed made upon the depositing of the notice in the U.S. Mail, postage paid. In the event, the Applicant fails to make the additional deposit with (10) days of receipt of the notice, the City will terminate its review process and not re-commence until the appropriate deposit is made and posted by the City's Finance Department. e. No applications will be processed or forwarded to the appropriate governing reviewing body by the City until all amounts due under this Agreement have been paid in full. 5. Positive Balance in Escrow Accounts. Upon the happening of any of the following events, the balance in the deposit account less outstanding fees shall be paid to the Applicant within (90) days of receipt by the City of a written request by the Applicant for payment: (1) completion of the development process; or (2) the application is withdrawn by the Application; (3) the applicant is denied by the City for any reason. 6. Deposit Amounts. The initial deposit amount contemplated for each the purposes described under the Agreement, which may be revised by the City from time to time, are set forth for Exhibit "B" attached hereto. 7. Accounting. If there has been activity in the account, the City will provide a monthly accounting of all expenses charged against the account or when requested by the Applicant. An accounting will also be provided when the City notices the need for an additional escrow deposit. 8. Terms of Breach. In the event of any terms of this Agreement are breached by the Applicant, including, but not limited to failure to make additional deposits when required by the City, the City may cease processing any application submitted by the Applicant or order the Applicant to cease any further development or progress under the terms of this Agreement, or both. Applicant indemnifies and holds the City harmless from any liability, claim, action or suit by or any obligation to the Applicant arising from or in connection with the City exercising or enforcing the terms and conditions of this Agreement or action on the Application. The Applicant shall pay all costs and expenses; including reasonable attorney fees and suit costs, incurred by the City arising from or in connection with the City any terms and conditions of this Agreement. 9. Validity. If any portion, section, subsection, sentence, clause, paragraph or phrase of this Agreement is for any reason held to be invalid, such invalidity shall not affect the validity of the remaining portion of this Agreement. 10. Binding Agreement. The parties mutually recognize and agree that all terms and conditions of this Agreement shall run with the land herein described and shall be binding upon the heirs, successors, administrators and assigns of the parties referenced in this Agreement. 11. Amendments. The terms of this Agreement shall not be amended without the written consent of the City and all parties hereto. [ Signature Page Follows] CITY OF LAKE ELMO By: Kristina Handt Its: City Administrator Attest: Julie Johnson, City Clerk STATE OF MINNESOTA ) 55. COUNTY OF WASHINGTON ) On this __ day of ______ _, 201 , before me a Notary Public within and for said County, personally appeared _________ and ___________ to me personally known, to be the person described in and who executed the foregoing instrument and acknowledged that he/ she/ they executed that same as his/ her/ their free act and deed. Notary Public Exhibit A Outlot T, The Royal Golf Club at Lake Elmo, PIO: 25.029.21.22.0001 Outlot J, The Royal Golf Club at Lake Elmo 2 nd Addition, PIO: 25.029.21.31.0041 The Royal Golf Club at Lake Elmo 3rd Addition Lot Block Area (sq. ft.) Lot Width Lot Depth 1 1 13,665 110.6 139.5 2 1 8,788 64.0 135.1 3 1 8,719 63.7 134.7 4 1 10,218 63.9 134.5 5 1 10,733 60.4 134.5 6 1 10,369 59.5 134.5 7 1 13,995 130.3 129.3 8 1 13,587 73.2 143.3 9 1 10,239 78.3 137.2 10 1 10,149 50.7 154.3 1 2 11,958 69.7 134.5 2 2 8,608 64.0 ,134.5 3 2 8,866 64.4 134.5 4 2 10,579 62.0 137.1 5 2 11,014 62.0 143.8 6 2 12,349 57.1 147.5 7 2 10,481 62.5 132.1 8 2 10,618 98.7 151.4 9 2 9,278 62.9 154.2 10 2 8,151 63.6 130.6 11 2 7,929 63.4 126.9 12 2 9,698 108.1 123.7 1 3 12,399 55.0 131.5 2 3 8,055 61.3 137 3 3 7,621 62.8 126.4 4 3 7,757 64.2 127 5 3 9,203 58.5 133.9 6 3 10,266 61.6 125 7 3 9,577 64.2 126.6 8 3 8,023 64.2 128.1 9 3 8,095 64.2 129.1 10 3 7,988 68.0 125.8 11 3 8,784 62.3 143.1 1 4 18,893 126.4 185.9 2 4 21,360 100.5 211.1 3 4 25,251 100.0 255.1 4 4 25,018 100.0 250.8 5 4 22,769 100.0 228.9 6 4 20,016 100.0 200.5 7 4 17,272 100.0 172.8 8 4 16,225 102.1 152.2 9 4 15,128 101.4 151.7 10 4 15,191 100.0 152.1 11 4 15,158 100.0 152.8 12 4 15,507 108.4 151.5 13 4 15,240 104.3 150.5 14 4 15,277 104.7 150.9 15 4 15,110 101.8 150.3 16 4 15,578 109.7 152 17 4 15,626 110.4 152 18 4 15,396 106.3 151.6 19 4 15,000 100.0 150 20 4 18,007 100.0 150 21 4 19,108 100.0 150 22 4 19,228 100.0 150 23 4 15,726 100.0 150 24 4 15,000 100.0 150 25 4 15,359 107.1 150.3 1 5 14,216 92.4 149.3 2 5 13,842 90.1 149.3 3 5 13,651 90.0 149.9 4 5 14,158 90.1 148.6 5 5 13,643 90.1 143 6 5 13,232 94.1 138.8 7 5 14,933 124.7 145.2 8 5 15,393 131.1 145 9 5 17,035 104.5 144.5 Total Lot 895,305 Outlot A 234,579 Outlot B 17,672 Outlot C 3,081,280 Total Outlot 3,333,531 Right of Way 288,324 TOTAL 4,517,160 Measured 4,517,160 Difference o Wetland Area 207,059 ~/ ✓ THE ROYAL CLUB October 15 , 2018 Mr. Ben Prchal Director of Planning City of Lake Elmo 3 800 Laverne Ave. N. Lake Elmo, MN 55042 Re: Final Plat/P.U.D. Narrative -The Royal Golf C lub at Lake Elmo Dear Mr. Prchal, H .C. Golf Land, LLC and Royal Development, Inc. is pleased to s ubmit herew ith our application for final plat and planned unit development approval for Phase III at The Royal Club at Lake Elmo. H.C. Golf Land and Royal Development woul d like to extend their sincere thanks to the City of Lake E l mo, its City Council, its Advisory Committees and its staff and consultants for their direction, cooperation and assistance in moving the RGC to this juncture. The following narrative will set out the basic elements of the p lat, address those information items requested in the appl ication forms and those items w hich will need collaboration between us as we move this plat to final acceptance. Owner H.C . Go lf Land, LLC is the current fee owner of the underly ing propetiy (Outlot T of The Royal Go lf Club at Lake Elmo and Outlet J , The Royal Golf Club at Lake Elmo 2 nd Addition). As soon as the final plat is recorded H.C. Golf Land, LLC wi ll retain ownership of Outlot C of the 3 rd Addition and transfer fee ownership of the lo ts/b locks to Royal Development, Inc., with Outlots A and B being transferred to the h o meowner's association or the City, as the City directs . Based on this current ownership and in tended immediate transfer, the "App licant" under the appl ication is Roya l Development, Inc. and the "Owner" is H.C. Golf Land, LLC. A ll additional documents should be prepared under the Royal Development, Inc. name as it is the developer and wi ll be fu lfilling the ob li gations as set forth in those agreements. ll Page ~ / .T THE ROYAL CLUB Existing Zoning The property has been zoned GCC (Golf Course Community) by the City of Lake Elmo. Plat Area/Ownership/Description The property is owned by H.C. Golf Land, LLC and is comprised of two parcels w ho se current P.I.D. 'sand legal descriptions are attached hereto as Exhibit "A". The property has been divided into lots , blocks and outlots for the development of our Phase III, w ith additional outlots reserved for future phases of d eve lopment. Residential -Contained in Blocks l , 2 , 3, 4 , a nd 5 are 67 residential home site lots consisting of 34 traditional s ingle family detached lots and 33 -"Villa" lots for detached s ing le- family townhomes which wi ll have Villa Association -maintained lawns and exteriors as further noted below. Outlets -The final plat contains three outlots designated as Outlets A, Band C. Residential Setbacks The setbacks for the residential lots are consistent with the approved preliminary plat. Dedicated Rights of Way Within the plat, RGC is dedicating rights of way to the public in the amount of 288,324 SF for our new residential streets. Density Consistent w ith the approved preliminary plat, the net residential density of all phases of The Royal C lub is calculated as 291 approved units and 187 net residential acres y ielding a density of 1.56 units/net acre. Development Phasing We are proposing to develop RGC in four phases with the current 67 lots denoted as Phase III. 2 1 Page ~/ ✓ THE ROYAL CLUB Development Schedule Site grading for Phase III will commence Fall of 2018 or Spring of 2019. As to the golf facilities, we have finished the reconstruction of the I 8-hole championship golf course, the practice range, s hort course, and renovation s of the old 3M clubhouse. The clubhouse has been fully renovated for both golf and as an event venue. Trail Phasing Consistent with preliminary plat, RGC will be constructing and dedicating well over 10,000 lineal feet of paved trail throughout the entire development. Community Impacts Because of the size, complexity and scope of The Royal Club at Lake Elmo, the project triggered the need to complete an Environmental Assessment Worksheet (EA W) to re v iew the impacts to traffic, public facilities, public safety and environmental issues. The EA W was completed in October of 2016 for public review. At its January 17 , 2017 meeting, the City Council adopted Resolution 2017-007 issuing a negative declaration on any further environmental study and accepting the findings of fact on the EAW. We believe community impacts have been fully reviewed. Additionally, all wetlands on the property have been dealt with pursuant to Wetland Conservation Act and VBWD rules and regulations and all activities thereon have received appropriate permits. Phase III Streets and Utilities Phase III street and utility construction will service the Phase Ill residential lots. Home Styles The Royal Golf Club community will feature a wide variety of high quality, custom-built homes in a variety of complimentary s tyles . Declarations of Protective Covenants Because of the variety of home styles and privately held common areas at RGC, we have created a Master Homeowners Association ("MHOA") whose m embership includes all 3I Page ~/ ✓- THE ROYAL CLUB residential lots in Phases I and II and will include all residential Phase III lots and all future phase residential lots. Its responsibilities will include such things as maintenance of private trails/ common area landscaping, open space and entry signage in addition to the maintenance of the future fitness /recreation center and the maintenance of property line-crossing retaining walls. The MHOA declaration will also contain the architectural standards consistent with preliminary plat conditions. Sub a ssoc iations for the Villa Home (Villa HOA'S) neighborhoods have been or will be formed depending on the villa builder's practices. These Villa HOA's will have responsibility for lawn/driveway and open space maintenance and the maintenance of the Villa home exteriors to assure a consistency in neighborhood appearance. Lastly, the MHOA will assume all architectural review responsibilities upon turnover of the MHOA from developer control to resident control consistent with the terms of Minnesota statutes. Landscape As a part of the Phase III development agreement, RGC and the City will enter into an agreement wherein RGC assumes planting res pons ibilities for trees required by the City as proposed in the landscape plan. Park Fees The development portion of RGC is 231.25 acres with a net buildable are of 186.92 acres. The appraised value of this property, as determined by an appraisal commissioned by the city , is $8,000 ,000. Per City of Lake Elmo policy, a park dedication of 10.0% or fee in lieu of land dedication of 10% of the value is r e quired with development. RGC and the city jointly have decided to not have city-owned parks within the development, thus obligating RGC for cash payments totaling $800,000.00 over the span of the development phases. RGC will receive credit against each phase's park fee for constructing trail s and appurtenant items s uch as turf establishment, retaining walls and ADA pedestrian ramps along with the dedication of the land for a 30-foot wide trail corridor. The RGC will provide the city with support calculations to determine the actual cash fee in Phase III to be paid with this application and in future phases as those phases are platted . 41 Page ~/ ✓- THE ROYA L CLUB Conservation/Ponding Maintenance Agreement RGC and the City have determined that there w ill be no s torm water pond in g faci li t ies constructed in Phase III. In future phases should C ity outlots lie within shoreland districts, conservation easements wi ll be entered into . Easement Vacation We are proposing to vacate the exis ting drainage and utility easements, as created and dedicated on the orig in a l Royal Go lf Club at Lake Elmo plat (l51 Addition), ly ing over Outlot T (see attached for details). With our 3rd Addition s ubmittal, we wi ll be re-platting this Outlot, and, in doing so, will be recreating new drainage and utility easements over the new parcels. The easement vacation is needed to avoid creating and 'stackin g' easements o n top of easements. The new easements w ill be the same s ize (or larger in some cases) as the vacated easements. Thus, the City does not lo se any drainage and utility easement areas. We also need to do this to keep the title clean for future owners/users of the parcels. SI Page ~/ ✓- THE ROYAL CLUB Our pledge to the City is to create a premium golf community with a national reputation of which a ll of Lake E lmo will be proud. We stand prepared to provide you with any further items you deem necessary as the development agreement and PUD take form and as we move forward with development activity. Sincerely, The Royal Golf Club at Lake Elmo By: H.C. Golf Land, LLC By: Its: 61 Page KI N G RO Y A L V A R D N O R T H BO U L E PAL M E R NOR T H ENVIRONMENTAL ◦ ENGINEERING ◦ SURVEYING THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADDITION DR I V E PA L M E R DR I V E NORTH LA N E NORTH KI N G L A N E NO R T H VICINITY MAP INSET 'B' (SEE SHEET 2 OF 3 SHEETS) INSET 'C' (SEE SHEET 3 OF 3 SHEETS) COURT ROYAL VARD NORT H BOULE P A L M E R N O R T H KINGS ENVIRONMENTAL ◦ ENGINEERING ◦ SURVEYING THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADDITION P A L M E R D R I V E D R I V E N O R T H NOR T H QU E E N S COUR T NO R T H VICINITY MAP INSET 'B' IN S E T L I N E (Se e S h e e t 3 o f 3 S h e e t s ) ENVIRONMENTAL ◦ ENGINEERING ◦ SURVEYING THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADDITION P A L M E R D R I V E NO R T H N O R T H D R I V E PALMER VICINITY MAP INSET 'C' IN S E T L I N E (Se e S h e e t 2 o f 3 S h e e t s )   PAGE 1 of 2  MEMORANDUM           Date:  November 19, 2018      To:  Ben Prchal, City Planner  Re: Royal Golf Club 3rd Addition – Final Plat     Ken Roberts, Planning Director    Engineering Review Comments  Cc:  Chad Isakson, P.E., Assistant City Engineer      From:  Jack Griffin, P.E., City Engineer          An engineering review has been completed for the Royal Golf Club 3rd Addition. Final Plat/Final Construction  Plans were received on October 31, 2018. The submittal consisted of the following documentation:     Royal Golf Club 3rd Addition Final Plat, Sheets 1‐3, not dated, prepared by Carlson McCain.   Royal Golf Club 3rd Addition Narrative, dated October 15, 2018.   Royal Golf Club 3rd Addition Construction Plans, Sheets 1‐24, dated October 5, 2018.   Royal Golf Club 3rd Addition Grading Plans, Sheets 1‐21, dated October 3, 2018.   Royal Golf Club 3rd Addition Landscape Plans, L1‐L7, dated October 9, 2018, by Pioneer Engineering.   Royal Golf Club 3rd Addition Specifications, dated October 5, 2018.      STATUS/FINDINGS:   Engineering review comments have been provided in two separate memos; one for Final Plat  approval, and one to assist with the completion of the final Construction Plans.  Please see the following review  comments relating to the Final Plat application.      FINAL PLAT: ROYAL GOLF CLUB 3RD ADDITION   Outlots A, B and C ownership have been shown on the final grading and construction plans as developer or  HOA owned as applicable. There are no Oulots to be dedicated to the City as part of this Phase.   Drainage and utility easements have been provided on the Final Plat and grading plans over all, or a  portion, of Outlots A and B as required. Drainage and utility easements for Outlot A has been shown on the  street and utility plans as required. The drainage and utility easement for Outlot B must be added to the  street and utility plans.   The Plat must be revised to include a 10‐foot drainage and utility easement over Outlot C, adjacent to the  north right‐of‐way line for Royal Boulevard and adjacent to the east right‐of‐way line for Palmer Drive.   All off‐site easements as required by the City Engineer and Public Works Director to complete any off‐site  improvements or to provide drainage and utility maintenance access must be provided in the City standard  form of easement agreement and signed by all parties prior to the release of the Final Plat for recording.  The following off‐site easements (golf course property) must be verified as existing or provided to the City.   Drainage and utility easements over the Golf Course adjacent to the rear yards of Lots 7‐14, Block 4.   Drainage and utility easements over the Golf Course adjacent to the rear yards of Lots 22‐25, Block 4.   The applicant has proposed temporary stormwater management provisions for the Royal Golf Club 3rd  Addition which will be removed and replaced with future development phases that will meet the storm  water management provisions approved with the Preliminary Plat.  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.   651.300.4261  Jack Griffin, P.E.                651.300.4264  Ryan Stempski, P.E.  651.300.4267  Chad Isakson, P.E.  651.300.4283    PAGE 2 of 2   The  Final  Plat  application  narrative  is  silent  regarding  the  plan  to  use  a  temporary  storm  water  management system. The narrative should be revised to fully address the temporary storm water  management  phasing,  maintenance,  and  replacement.  As  proposed, it  is  unknown  how  the  next  development phase will be constructed without interruption of the temporary system.   The  temporary  storm  sewer  and  sediment  basin  must  be  relocated in a manner that allows the  temporary  storm  water  management  to  remain  operational  until  the  permanent  storm  water  management system is operational.   Final Plat approval must be contingent upon the applicant obtaining a VBWD permit for the temporary  storm water management provisions. Any plan changes made to obtain the VBWD permit must be  resubmitted for City review and approval.   A City variance may be required to approve the Final Plat as the temporary storm water management  system does not meet all provisions of the City storm water ordinances (e.g. volume control).   Additional drainage and utility easements must be provided over the temporary storm sewer system  and temporary sediment basins located on Outlot C.   Additional  development  security  provisions should be  considered to address the  temporary storm  water management system and phasing.   Final Construction Plans and Specifications must be prepared in accordance with the City Engineering  Design Standards Manual dated March 2017, using City details, plan notes and specifications and meeting  City Engineering Design Guidelines.   Final  Construction  Plans  and  Specifications  must  be  revised  in accordance  with  the  Construction  Plan  engineering review memorandum dated November 19, 2018.    All easements as requested by the City Engineer and Public Works department shall be documented on the  Final Plat prior to the release of the Final Plat for recording.    The Final Plat shall not be recorded until final construction plan approval is granted.   No construction for Royal Golf Club 3rd Addition may begin until the applicant has received City Engineer  approval for the Final Construction Plans; the applicant has obtained  and  submitted  to  the  City  all  applicable permits, easements and permissions needed for the project; and a preconstruction meeting has  been held by the City’s engineering department.                      PAGE 1 of 2  MEMORANDUM           Date:  November 19, 2018      To:  Brian Brian Krystofiak, P.E., Carlson McCain, Inc.  Re:  Royal Golf Club 3rd Addition    Jim Felton, Royal Development LLC.    Construction Plan Review  Cc:  Ben Prchal, City Planner  Ken Roberts, Planning Director  Rob Weldon, Public Works Director       Chad Isakson, P.E., Assistant City Engineer     From:  Jack Griffin, P.E., City Engineer         An engineering review has been completed for the Royal Golf Club 3rd Addition. Final Plat/Final Construction Plans  were received on October 31, 2018. The submittal consisted of the following documentation:     Royal Golf Club 3rd Addition Final Plat, Sheets 1‐3, not dated, prepared by Carlson McCain.   Royal Golf Club 3rd Addition Narrative, dated October 15, 2018.   Royal Golf Club 3rd Addition Construction Plans, Sheets 1‐24, dated October 5, 2018.   Royal Golf Club 3rd Addition Grading Plans, Sheets 1‐21, dated October 3, 2018.   Royal Golf Club 3rd Addition Landscape Plans, L1‐L7, dated October 9, 2018, by Pioneer Engineering.   Royal Golf Club 3rd Addition Specifications, dated October 5, 2018.      STATUS/FINDINGS:   Engineering review comments have been provided to assist with the completion of the  Construction Plans.  When submitting revised plans and specifications, please provide a point by point response  letter that details all changes made to the plans.      ROYAL GOLF CLUB 3RD ADDITION FINAL CONSTRUCTION PLANS   The drainage and utility easement for Outlot B must be added to the street and utility plans.   Revise the street and utility plans to show the required 10‐foot drainage and utility easement over Outlot C,  adjacent to the north right‐of‐way line for Royal Boulevard and adjacent to the east right‐of‐way line for  Palmer Drive.   Relocate the temporary storm sewer and sediment basin to allow the temporary storm water management  system to remain operational until the permanent storm water management system is operational.    SANITARY SEWER AND WATERMAIN PLANS   Sheet 5. Revise sewer grade to 0.5% between MH‐11 and MH‐13.   Sheet 6. Revise Palmer Drive eye brow watermain to be 8‐inch diameter. Eliminate dead end main by  connecting to Palmer Drive watermain at each intersection. This is consistent with the City practice.   Sheet 6. Revise watermain along Kings Court to be on north side of the street per City standards.   Additional plan revisions may be required regarding hydrant and system valve placement, pending review  by the Public Works Director.  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.   651.300.4261  Jack Griffin, P.E.                651.300.4264  Ryan Stempski, P.E.  651.300.4267  Chad Isakson, P.E.  651.300.4283    PAGE 2 of 2    STROM SEWER PLANS   Sheet 10. Revise storm sewer pipe size to meet City minimum 15‐inch pipe from CBMH‐274 to CBMH‐273.   Sheet 10. Revise storm sewer pipe size to meet City minimum 15‐inch pipe from CBMH‐271A to CBMH‐271.   Sheet 11. Revise storm sewer pipe size to meet City minimum 15‐inch pipe from CBMH‐281 to CBMH‐280.   Sheet 13. Revise storm sewer pipe size to meet City minimum 15‐inch pipe from CBMH‐240 to CBMH‐239.    STREET PLANS   Sheets 14‐17. Add K‐value for all vertical curves. Revise curves as necessary to meet minimum City standards.   Sheet 15. Revise street grades along Palmer Drive. The City minimum 0.5% grade is used for back to back  grade runs with no vertical curve at the break. Increase each grade and add vertical curve.    SIGN / PAVEMENT MARKING / LIGHTING PLAN   Sheet 18. Remove one light pole from the Palmer Drive eyebrow and relocate the second light pole to the  middle of the two eyebrow intersections.   Sheet 18. Add no parking signs to the interior of the Palmer Drive eye brow (3‐signs).    Sheet 18. Add no parking signs to the sign schedule.   Sheet 19. Add no parking signs to the Kings Court and Queens Court cul‐de‐sacs (3‐signs each).   Sheet 19. Add a stop bar at the intersection of Lake Elmo Avenue and Royal Boulevard.    DETAILS/TYPICAL SECTIONS   Sheet 24. Typical Street Sections. Remove references to “saw and seal”. Revise bituminous mix to Type C.  The City practice has changed to require Type C bituminous wear course and eliminate saw & seal.   Sheet 24. Typical Street Section: Royal Boulevard entrance. Add “RTL” to designate the right turn lane.   Sheet 24. Bituminous Access Road. Revise minimum grades to 4% on each side of access road.    LANDSCAPE PLAN:   Remove all trees from the interior of all pond maintenance benches. The Landscape Plans must be revised  to accommodate maintenance access to all storm water and to avoid placement of trees within the BMP.    The landscape plans must be revised to show all underground utilities including water/sewer lot services and  revised to ensure trees maintain 10‐foot minimum offset from all utilities.           OWNED BY OTHERS (BUFFER MAY BE REQUIRED WITH FUTURE DEVELOPMENT) 10 17 16 15 14 13 11 9 7 18 5 4 6 8 12 3 2 1 M A N N I N G T R A I L N O R T H 20TH STREET NORTH 20TH STREET NORTH 20TH STREET NORTH 20TH STREET NORTH 20TH STREET NORTH M A N N I N G T R A I L N O R T H 10TH STREET (COUNTY STATE AID HIGHWAY NO. 10) LA K E E L M O A V E N U E N O R T H ( C O U N T Y S T A T E A I D H I G H W A Y N O . 1 7 ) LA K E E L M O A V E N U E N O R T H (C . S . A . H . N O . 1 7 ) LA K E E L M O A V E N U E N O R T H (C O U N T Y S T A T E A I D H I G H W A Y N O . 1 7 ) ROY A L MA S T E R S MASTE R S N O R T H PALMER D R I V E N O R T H LA T R O B E L A N E N O R T H LA T R O B E QUEENS COURT NORTH ANN I K A A V E N U E N O R T H EET R O Y A L B O U L E V A R D N O R T H VAR D NO R T H BOU L E ROYAL VARD NORTH BOULE RO Y A L VA R D NO R T H BO U L E STR E E T NOR T H MASTE R S STREET NOR T H RT NO R T H COU A N N I K A D R I V E N O R T H IKA D R I V E N O R T H ANN AN N I K A D R I V E N O R T H A N N I K A D R I V E N O R T H A N N I K A D R I V E AN N I K A AV E N U E EN NORT H STRQUE D R I V E PALM E R A R N I E W A Y ARNIE W A Y N LA N E NO R T H P A L M E R D R I V E R T H N O P A L M E R R T H N O D R I V E P A L M E R NO R T H D R I V E N O R T H KINGS COURT NORTH 10-9-18 HC GOLF COURSE DEVELOPMENT, LLC 11074 RADISSON ROAD NE BLAINE, MINNESOTA 55449 GROUNDCOVER PLAN c 7OF 10-9-18 JLT JLT Name Reg. No.Date Revisions Date Designed Drawn 2018 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson L1THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADD. LAKE ELMO, MINNESOTA NO R T H P A L M E R N O R T H D R I V E 10-9-18 HC GOLF COURSE DEVELOPMENT, LLC 11074 RADISSON ROAD NE BLAINE, MINNESOTA 55449 GROUNDCOVER PLAN c 7OF 10-9-18 JLT JLT Name Reg. No.Date Revisions Date Designed Drawn 2018 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson L2THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADD. LAKE ELMO, MINNESOTA P A L M E R R T H N O D R I V E KINGS COURT NORTH 10-9-18 HC GOLF COURSE DEVELOPMENT, LLC 11074 RADISSON ROAD NE BLAINE, MINNESOTA 55449 GROUNDCOVER PLAN c 7OF 10-9-18 JLT JLT Name Reg. No.Date Revisions Date Designed Drawn 2018 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson L3THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADD. LAKE ELMO, MINNESOTA LA K E E L M O A V E N U E N O R T H ( C O U N T Y S T A T E A I D H I G H W A Y N O . 1 7 ) QUEENS COURT NORTH ROYAL VARD NORT H BOULE P A L M E R D R I V E R T H N O KINGS COURT NORTH 10-9-18 HC GOLF COURSE DEVELOPMENT, LLC 11074 RADISSON ROAD NE BLAINE, MINNESOTA 55449 GROUNDCOVER PLAN c 7OF 10-9-18 JLT JLT Name Reg. No.Date Revisions Date Designed Drawn 2018 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson L4THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADD. LAKE ELMO, MINNESOTA 5 4 3 LA K E E L M O A V E N U E N O R T H ( C O U N T Y S T A T E A I D H I G H W A Y N O . 1 7 ) QUEENS COURT NORTH ROYAL VARD NORTH BOULE P A L M E R D R I V E R T H N O P A L M E R R T H N O D R I V E P A L M E R N O R T H D R I V E KINGS COURT NORTH DRY SWALE/POND (STATE SEED MIX 33-262 FORMERLY W4) NATIVE DRY PRAIRIE SOUTHEAST (STATE SEED MIX 35-621 FORMERLY U6) SOD (TYPICAL) 10-9-18 HC GOLF COURSE DEVELOPMENT, LLC 11074 RADISSON ROAD NE BLAINE, MINNESOTA 55449 GROUNDCOVER PLAN c 7OF 10-9-18 JLT JLT Name Reg. No.Date Revisions Date Designed Drawn 2018 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson L5THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADD. LAKE ELMO, MINNESOTA 5 4 3 LA K E E L M O A V E N U E N O R T H ( C O U N T Y S T A T E A I D H I G H W A Y N O . 1 7 ) LA T R O B E QUEENS COURT NORTH ROYAL VARD NORT H BOULE P A L M E R D R I V E R T H N O P A L M E R R T H N O D R I V E KINGS COURT NORTH 10-9-18 HC GOLF COURSE DEVELOPMENT, LLC 11074 RADISSON ROAD NE BLAINE, MINNESOTA 55449 GROUNDCOVER PLAN c 7OF 10-9-18 JLT JLT Name Reg. No.Date Revisions Date Designed Drawn 2018 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson L6THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADD. LAKE ELMO, MINNESOTA 10-9-18 HC GOLF COURSE DEVELOPMENT, LLC 11074 RADISSON ROAD NE BLAINE, MINNESOTA 55449 GROUNDCOVER PLAN c 7OF 10-9-18 JLT JLT Name Reg. No.Date Revisions Date Designed Drawn 2018 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson L7THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADD. LAKE ELMO, MINNESOTA Wenck | Colorado | Georgia | Minnesota | North Dakota | Wyoming Toll Free 800-472-2232 Web wenck.com To: Ben Prchal, City of Lake Elmo Planner From: Lucius Jonett, Wenck Landscape Architect Date: November 8, 2018 Subject: City of Lake Elmo Landscape Plan Review Royal Golf Club – 3rd Addition, Review #1 Submittals  Royal Golf Club 3rd Addition Final Plat, draft not signed  Royal Golf Club 3rd Addition Civil Site Plans, dated 10/05/2018, received 10/31/2018.  Royal Golf Club 3rd Addition Landscape Plans, dated 10/09/2018, received 10/31/2018. Location: Area between 10th Street and 20th Streets, east of Lake Elmo Avenue and west of Manning Trail on the former 3M Tartan Park properties. Land Use Category: Residential golf course community Planned Unit Development on 428.06 acres and will include 291 single-family residential lots, a lot for the clubhouse and facilities, and golf course. Surrounding Land Use Concerns: As required in the resolution of approval, there is a requirement that the developer work with the adjacent property owners (Homestead Development) to get an agreement in place for screening and that it be incorporated into the final landscape plans. Special Landscape Provisions in addition to Zoning Code: The Royal Golf Club Development and the City agreed that the number of trees required to be planted within the development for tree replacement and requirements per city ordinance was to be 2900 – as per the amendment to the development agreement attached. The development agreement also states that the number of trees can be reduced by woodland management or pollinator friendly techniques or the payment of $500 for parkland dedication requirements per 2.5- inch caliper inch tree not planted. Ben Prchal Planner City of Lake Elmo November 8, 2018 2 T:\6443 Lake Elmo\03 Royal Golf Club\05 3rd Addition\01 Plan Reveiw\2018-10-31\2018-11-08 Royal Golf Club 3rd Addition Landscape Plan Review.docx Tree Preservation: A tree survey/preservation plan has been previously submitted and approved with preliminary plat that does meet all requirements, including a tree inventory showing individual trees that are exempt, removed and saved. Entire Site Tree Preservation Phase 1 Total Caliper Inches On-Site: 138991.36 138991.36 Cal Inches Significant Inches Removed On-Site 58883.2 17034.3 Cal Inches Common Trees 19824.7 5347.2 Conifer/Evergreen Trees 15646.9 2775.9 Hardwood Trees 23411.6 8911.2 Tree Removal Limits (30% Significant Inches Removed On-Site) 41697.41 41697.41 Cal Inches Subtract Common Tree Removals 19821.7 5347.2 Subtract Conifer/Evergreen Tree Removals 15646.9 2775.9 Subtract Hardwood Tree Removals 23411.6 8911.2 Removals in excess of 30% allowance -17182.79 24663.11 Cal Inches Removals in Excess of Allowance 17182.7 0 Cal Inches Hardwood Tree Replacement (1/2 the dia inches removed) 8591.35 0.00 Cal Inches Tree replacement needed 8591.35 0.00 Cal Inches Tree Replacement Required @ 2.5" per Tree 3437 0 # of Trees Tree replacement is required because more than thirty (30) percent of the diameter inches of significant trees surveyed will be removed. Ben Prchal Planner City of Lake Elmo November 8, 2018 3 T:\6443 Lake Elmo\03 Royal Golf Club\05 3rd Addition\01 Plan Reveiw\2018-10-31\2018-11-08 Royal Golf Club 3rd Addition Landscape Plan Review.docx Landscape Requirements: The 3rd addition landscape plans do meet the code required number of trees. Master Plan Master Plan 1st Addition 2nd Addition 3rd Addition Required Approved Required Required Required Street frontage 35,961 7,942 10,163 8,360 Lineal Feet Lake Shore 0 Lineal Feet Stream Frontage 0 Lineal Feet Total Linear Feet 35,961 7,942 10,163 8,360 Lineal Feet /50 Feet = Required Frontage Trees 720 159 204 168 Trees Development or Disturbed Area - SF Development or Disturbed Area 146 37 38 37 Acres /5 = Required Development Trees 730 185 190 185 Trees Code Required Number of Trees 1,450 344 394 353 Required Mitigation Trees 3,437 PUD Agreement Required # of Trees 2,900 Qualified* Trees Proposed to Date 1,943 419 632 658 *Ornamental and builder trees not included in tree count to satisfy 2,900 tree requirement per the PUD agreement. 1. A minimum one (1) tree is proposed for every fifty (50) feet of street frontage. 2. A minimum of five (5) trees are proposed to be planted for every one (1) acre of land that is developed or disturbed by development activity. The master landscape plans meet the minimum of twenty-five percent (25%) of the required number of trees shall be deciduous shade trees and a minimum of twenty-five percent (25%) of the required number of trees be coniferous trees. Master Plan Qty % Composition Deciduous Shade Tree 1190 61% Coniferous Tree 753 39% Ornamental Trees* 42 Builder Trees* 888 Tree Count 2831 Phase 1 Qty % Composition Deciduous Shade Tree 239 57% Coniferous Tree 180 43% Ornamental Trees* 0 Builder Trees* 202 Tree Count 621 Ben Prchal Planner City of Lake Elmo November 8, 2018 4 T:\6443 Lake Elmo\03 Royal Golf Club\05 3rd Addition\01 Plan Reveiw\2018-10-31\2018-11-08 Royal Golf Club 3rd Addition Landscape Plan Review.docx Phase 2 Qty % Composition Deciduous Shade Tree 425 67% Coniferous Tree 207 33% Ornamental Trees* 24 Builder Trees* 158 Tree Count 790 Phase 3 Qty % Composition Deciduous Shade Tree 340 52% Coniferous Tree 318 48% Ornamental Trees* 26 Builder Trees* 206 Tree Count 864 *Ornamental and builder trees not included in tree count to satisfy 2,900 tree requirement per the PUD agreement. Total Composition Qty % Composition Deciduous Shade Tree 1004 59% Coniferous Tree 705 41% Ornamental Trees* 50 Builder Trees* 566 Tree Count 5106 A. A landscape plan has been submitted that meets all requirements. Findings: 1. Submitted landscape plans are consistent with the approved preliminary plat, and plan and agreement approved and executed between the Homestead HOA and Royal Golf club regarding screening. 2. Black hills spruce and white pine trees have mature diameters of approximately 20’-30’ and 30’-40’ respectively. When the tree symbols are show to scale, there are several locations on sheet L4 where the trees at full diameter will overlap the buildings. See attached figure. 3. There is on tree on L4 that is located on the edge of driveway pavement that will need to be relocated. See attached figure. 4. Future irrigation plans will need to meet City requirements. Ben Prchal Planner City of Lake Elmo November 8, 2018 5 T:\6443 Lake Elmo\03 Royal Golf Club\05 3rd Addition\01 Plan Reveiw\2018-10-31\2018-11-08 Royal Golf Club 3rd Addition Landscape Plan Review.docx Recommendation: It is recommended that a condition of approval for the Royal Golf Club – 3nd Addition landscape plans include: 1. Adjust the location and spacing of the trees that overlap the buildings when shown at mature diameter and resubmit a revised landscape plan. 2. Adjust the location of the tree that is on the edge of the driveway and resubmit a revised landscape plan. Sincerely, Lucius Jonett, PLA (MN) Wenck Associates, Inc. City of Lake Elmo Municipal Landscape Architect LA K E E L M O A V E N U E N O R T H ( C O U N T Y S T A T E A I D H I G H W A Y N O . 1 7 ) QUEENS COURT NORTH ROYAL VARD NORT H BOULE P A L M E R D R I V E R T H N O KINGS COURT NORTH 10-9-18 HC GOLF COURSE DEVELOPMENT, LLC 11074 RADISSON ROAD NE BLAINE, MINNESOTA 55449 GROUNDCOVER PLAN c 7OF 10-9-18 JLT JLT Name Reg. No.Date Revisions Date Designed Drawn 2018 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson L4THE ROYAL GOLF CLUB AT LAKE ELMO 3RD ADD. LAKE ELMO, MINNESOTA