HomeMy WebLinkAbout#10 - Private Development Security Reductions STAFF REPORT
DATE: February 7, 2018
CONSENT
ITEM #: 10
AGENDA ITEM: Private Development Projects – Approve Security Reductions for Easton
Village 2nd Addition and Easton Village 3rd Addition
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator
Emily Becker, Planning Director
Chad Isakson, Assistance City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve security reductions for the Easton Village
2nd Addition and Easton Village 3rd Addition?
PROPOSAL DETAILS/ANALYSIS: Staff has received and processed requests to reduce the
development security in accordance with the various development projects. These requests have been
reviewed and the following reductions are being recommended for approval:
Current Security Amount Proposed Security Amount
1. Easton Village 2nd Addition: $ 702,776 $371,223
2. Easton Village 3rd Addition: $1,104,400 $627,894
Work within each of these developments have progressed in accordance with the respective development
agreement and to the extent necessary to support a reduction in the security as detailed in the attached
Security Reduction Worksheets.
FISCAL IMPACT: It is the City’s goal to retain at all times during the subdivision improvements a
security amount that is adequate to ensure completion of all elements of the improvements as protection to
the City tax payers against the potential of developer default. With this reduction, the remaining security
amount held by the City remains sufficient to complete the remaining improvements.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent
Agenda, the security reductions for the Easton Village 2nd Addition and Easton Village 3rd Addition as
detailed in this report and supporting documentation. If removed from the consent agenda, the
recommended motion for the action is as follows:
“Move to approve security reductions for the Easton Village 2nd Addition and Easton Village 3rd
Addition as detailed in the attached Security Reduction Worksheets.”
ATTACHMENTS:
1. Security Reduction Worksheet – Easton Village 2dn Addition.
2. Security Reduction Worksheet – Easton Village 3rd Addition.
EASTON VILLAGE 2ND ADDITION October 31, 2017
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading $238,969 $298,711.25 $298,711
Grading $38,286 $47,858 $47,858
Sanitary Sewer $54,276 $67,845 $50,884
Watermain $60,848 $76,059 $57,045
Storm Sewer $54,920 $68,650 $34,325
Streets and Sidewalks $226,308 $282,885 $141,443
Trails $12,570 $15,713
Surface Water Facilities $0 $0 included in Grading Agreement
Street Lighting $48,000 $60,000 By Xcel Energy
Street Signs and Traffic Control Signs $700 $875
Private Utilities (electricity, natural gas, telephone, and cable)
Landscaping $46,008 $57,510
Tree Preservation and Restoration NA NA included in Grading Agreement
Wetland Mitigation and Buffers NA NA LOC Through VBWD
Monuments $1,900 $2,375
Erosion Control $15,406 $19,257 included in Grading Agreement
Misc. $0 $0 None
Record Drawings $3,000 $3,750
TOTALS $562,221 $702,776 RELEASED AMOUNTS:$0 $331,553 $0 $0 $0 $0
CUMMULATIVE AMOUNTS:$0 $331,553
SECURITY AMOUNT REMAINING:$702,776 $371,223
DATE:10/17/2017 2/7/2018
Time of Performance:
REDUCTIONS
EASTON VILLAGE 3RD ADDITION October 31, 2017
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading $196,245 $245,306 $245,306
Sanitary Sewer $118,179 $147,724 $110,793
Watermain $128,435 $160,544 $120,408
Storm Sewer $118,267 $147,834
Streets and Sidewalks $157,590 $196,988
Trails $14,600 $18,250
Surface Water Facilities $0 $0 included in Grading Agreement
Street Lighting $12,000 $15,000 By Xcel Energy
Street Signs and Traffic Control Signs $1,850 $2,313
Private Utilities (electricity, natural gas, telephone, and cable)
Landscaping $98,573 $123,216
Tree Preservation and Restoration NA NA included in Grading Agreement
Wetland Mitigation and Buffers NA NA LOC Through VBWD
Monuments $2,800 $3,500
Erosion Control $29,982 $37,477 included in Grading Agreement
Misc. $0 $0 None
Record Drawings $5,000 $6,250
TOTALS $883,520 $1,104,400 RELEASED AMOUNTS:$476,507 $0 $0 $0 $0 $0
CUMMULATIVE AMOUNTS:$476,507
SECURITY AMOUNT REMAINING:$627,894
DATE:2/7/2018
Time of Performance:
REDUCTIONS