HomeMy WebLinkAbout#17 - Wildflower 3rd Addition Final Plat & PUDSTAFF REPORT DATE: 3/20/2018 AGENDA ITEM: 17 TO: City Council FROM: Emily Becker, Planning Director ITEM: Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plans REVIEWED BY: Jack Griffin, City Engineer BACKGROUND: Robert Engstrom Companies is requesting approval of final plat, final PUD development plans for the third phase of the Wildflower at Lake Elmo PUD development. The final plat includes 25 single family residential lots located to the east of the second phase and to the northwest of the first phase. Staff is recommending approval of the request subject to compliance with the conditions listed in this report. PROPOSAL DETAILS/ANALYSIS: Applicant: Robert Engstrom Companies; 4801 West 81st Street, #101, Bloomington, MN Property Owners: Robert Engstrom Companies; 4801 West 81st Street, #101, Bloomington, MN Location: Outlot B, Wildflower at Lake Elmo 2nd Addition, and Outlot P, Wildflower at Lake Elmo 1st Addition Request: Application for lot Final Plat and Final Planned Unit Development (PUD) Plan approval for the third phase of the Wildflower PUD development. The final plat includes 25 single-family residential lots, and an outlot for future development. Existing Land Use/ Vacant outlot and MDR/PUD. Zoning: Surrounding: North – vacant outlot and MDR/PUD zoning –; west - Wildflower 2nd Addition and MDR/PUD zoning and Lake Elmo Avenue; south – offices, business park land – VMX – Village Mixed Use; east – Wildflower outlot and open space/Field of St. Croix II subdivision open space – RR and OP zoning. Comprehensive Plan: Village Medium Density Residential (2.5-4.99 units per acre)/Village Open Space Overlay History: The property is within the Village Planning Area boundary and municipal sewer service area. The site was historically been used for farming activities. A large portion of the site is located in a FEMA Flood District. The City approved a Comprehensive Plan Amendment in 2014 that removed portions of the site from the open space land category. The City approved a PUD Concept Plan for the property on June 17, 201 2 4, and a preliminary plat and preliminary PUD plans on April 7, 2015. Wildflower 1st Addition received final plat and PUD plan approval on 7/21/15 and Wildflower 2nd Addition received final plat and PUD plan approval on December 6, 2016. A PUD amendment was processed on June 6, 2017. Deadline for Action: Application Complete – 2/12/2018 60 Day Deadline – 4/13/2018 Extension Letter Mailed – No 120 Day Deadline – NA Regulations: Chapter 153 – Subdivision Regulations Article 10 – Urban Residential Districts (MDR) Article 16 – Planned Unit Development Regulations §150.270 Storm Water, Erosion, and Sediment Control Robert Engstrom Companies is requesting approval of a final plat and final PUD plan associated with the second phase of the Wildflower Planned Unit Development (PUD). The proposed final plat will replat the Outlot P, Wildflower at Lake Elmo 1st Addition, 7.89 acres, and Outlot B, Wildflower at Lake Elmo 2nd Addition, 3.62 acres, in to 25 single-family residential lots, of which 12 will be the “garden villa” homes while the remaining 13 will be conservancy lots located on Prairievew Trail. In addition to the 25 single family homes, the final plat and PUD plans include one outlot. Outlot A is 8.3697 acres in size and will be redeveloped into residential lots in the future. The twelve garden villa lots average 0.1607 aces in size with the smallest lot being 0.1405 acres in size and the largest 0.1758 acres in size; the 13 conservancy single family lots average 0.29 acres in size, with the smallest being 0.2975 acres in size and largest being 0.6083 the acres in size. The lots sizes and dimensions are consistent with the preliminary plat and PUD Plans. Plat Summary: Development area Outlots C of 2nd Addition: 3.62 acres Outlot P of 1st Addition: 7.89 acres Residential lots: 25 (12 villa, 13 conservancy) Outlot for future development (Outlot A): 8.3697 acres R/W area: 3.5237 acres Average garden villa lot size: 0.16 acres Average conservancy lot size: 0.29 acres Parkland: 0 acres Wetland and wetland buffers: 0 acres Grading. The site was graded with the first phase development, so no grading plans were included in the final plat submittal. Stormwater. Stormwater issues were discussed with the approval of Wildflower 2nd Addition Final Plat. Among these issues were the Wildflower stormwater pond depth and non-functioning infiltration basins in the Village Preserve development. The Valley Branch Watershed District has indicated that the infiltration basins in the Village Preserve Development have been corrected and that further investigation is needed in to what actions need to be taken at Wildflower. Street Names. Street names shall be given the suffix “N” prior to recording of final plat. 3 Engineering Review. The City Engineer has reviewed the final plat submittal and has prepared a memorandum for the Commission and Council’s review. The comments in the City Engineer’s review memorandum dated March 1, 2018 should be addressed prior to releasing the plat for recording. Some key issues outlined in this report include: • Payment for sanitary and watermain pipe oversizing should be addressed in the development agreement. • This addition proposes a sanitary lift station to be owned and operated by the City to provide sanitary sewer service for the 13 lots along Prairieview Trail. Per the conditions of Preliminary Plat approval, the sanitary sewer lift station will be designed by the City’s engineering consultant, at the developer’s costs, to ensure conformance with the City’s minimum design standards and consistency with other lift station equipment in the City, including SCADA control systems. • As an alternative, City staff would consider allowing the construction of a low pressure system using individual grinder stations and a 2-inch forcemain to service these lots, contingent upon the individual grinder stations meeting City recommendations to ensure longer lasting equipment is provided to each property owner. Landscape Plan. A revised landscape plan has been submitted for review, but has not been approved. Approval of the landscape plan should be a condition prior to releasing the plat for recording. Protective Easement. A condition of preliminary plat was to protect all open space with protective easements. An protective easement is being prepared to protect Outlot A from any future development. This should be a condition of that needs to be addressed prior to releasing the plat for recording. Parkland Dedication. The 1st Addition Development Agreement indicated that all parkland dedication was satisfied within the first phase. Timeline. The applicant’s narrative indicates the following timeline: Utilities to begin April of 2018 and completed June of 2018 with small utilities in August of 2018; street construction to be done July of 2018; and landscaping installation complete by September of 2018. PUD Amendment. On December 6, 2017, the Council approved a PUD amendment to amend the Wildflower at Lake Elmo PUD Agreement. The PUD Amendment allowed for the following, which affects 3rd Addition: • Conservation and Prairie Lots will have setbacks consistent with LDR zoning. • Driveway locations will be flexible on Lot 4, Block 3 and Lot 4, Block 5 in 3rd Addition. This is subject to City review of individual building permits for unforeseen conflicts or safety issues, and any changes to street curbing as a result of modified driveway locations must occur prior to the installation of the final lift of asphalt being installed. • Up to 6% impervious coverage is allowed beyond the 50% impervious coverage maximum for the courtyard lots with use of pervious pavers. Preliminary Plat Conditions. The final plat is in conformance with the preliminary plat. The preliminary plat and PUD plans were approved with conditions. Staff has provided comments on the status of each in bold italics: 4 Preliminary Plat Conditions – With Staff Update Comments (updated information in bold italics): 1) No lots within a FEMA flood zone shall be approved as part of a final plat until such time that the City’s Floodplain Management Map has been amended to remove these lots. As an alternative to amending this map, the developer must provide documentation that all structures will be built above the regulatory flood protection elevation, that any public infrastructure will also meet Floodplain Ordinance requirements, and that the proposed storm water ponds may be constructed within the floodplain area. Comments: This condition will apply to the final plat and all subsequent stages. The Valley Branch Watershed District has indicated that it will undertake a study to amend the FEMA flood delineations to lower the flood levels in this area to match those identified in the Goetschel Pond study. There are no buildable lots depicted on the final plat that are located in a flood district. 2) Prior to any grading activity, the developer shall submit to the City temporary grading easements from the owner of the lots adjacent to Layton Avenue within the Brookman Addition in order to construct the improvements within this right-of-way as documented in the preliminary construction plans. Comments: These easements have been secured and grading was completed within this area. 3) The developer has requested the inclusion of public art within common areas and public property throughout Wildflower development. Prior to the placement of any art on publicly owned property or public rights-of-way, the developer and City shall enter into an agreement that clarifies the individuals or entities responsible for maintenance, upkeep and removal of any public art. No public art shall be lit in a manner that conflicts with the City’s Lighting Ordinance. Comments: This is a condition that will apply to any placement of public art within the development, including that installed in phase 1, the stamping of poetry into sidewalks and sculpture in the right of way. A landscape license agreement shall be executed to include public art as a landscape element and shall be executed prior to building permits in the third phase. 4) Prior to the submission of a final plat for any portion of the Wildflower PUD, the developer shall work with the City to determine the appropriate park dedication calculations for the entire development area. Comments: The development agreement for the first phase indicated that all park dedication was satisfied with the first phase of the development. 5) The applicant must enter into a separate grading agreement with the City prior to the commencement of any grading activity in advance of final plat and plan approval. The City Engineer shall review any grading plan that is submitted in advance of a final plat, and said plan shall document extent of any proposed grading on the site. Comments: The site grading was completed with the first phase of the development 6) The utility construction plans shall be updated to incorporate the recommendations of the City Engineer as described in a February 18, 2015 memorandum to the City concerning the appropriate location and size of sewer services through the PUD planning area, including any requested oversizing of these facilities to service adjacent properties, prior to the submission of a final plat. Comments: The supplemental plans included in the final plat submission address the previous review comments. The City Engineer approved the supplemental plans. This condition has been met. 5 7) The developer shall minimize the number of rain gardens within public rights-of-way consistent with the review comments from the City Engineer. Any such storm water infiltration features shall be subject to review and approval by the City Engineer. Comments: All rain gardens as previously proposed have been eliminated from the plans. 8) The preliminary development plans must be revised to comply with City Street standards as referenced in the City Engineer’s review memorandum dated February 18, 2015. Comments: The plans have been updated to meet City standards and were approved as part of the PUD. 9) The City approves all requests for flexibility from City Zoning and Subdivision requirements with the exception of the street standards noted in the preceding condition. Comments: The revised plans address this condition. 10) The applicant is encouraged to incorporate elements from the Lake Elmo Theming Study into the open space areas within the subdivision. Comments: The final plans do not include any specific references to the City’s theming study. This condition was not a mandatory requirement. 11) The preliminary landscape plan shall be updated to address the review comments from the City’s landscape architecture consultant as noted in a review letter dated February 4, 2015. Comments: The Preliminary Landscape Plans dated 5/28/15 generally meet the City’s requirements for landscaping, however the Landscape Architect’s review comments have not been fully addressed. The developer has since submitted an amended plan for a portion of the first addition landscaping which have been approved, subject to the landscape requirements for the entire site. A third phase plan has been submitted and approval of the plan shall be required prior to recording the final plat of the 3rd Addition. 12) All center median planting areas as depicted on the preliminary plat and plans shall be owned by the City of Lake Elmo and maintained by the Homeowners Association. The applicant shall enter into a maintenance agreement with the City that clarifies the individuals or entities responsible for any landscaping installed in areas outside of land dedicated as public park, trails, or open space on the final plat. The developer has entered into a landscape license agreement that meets this condition for the first phase which have been amended to address the public art. A similar agreement will be required with the third addition and will be a condition of approval. The agreement shall be executed prior to issuance of building permits in the third phase. 13) The Final Plat and Plans must address the requested modifications outlined in the City Engineer’s review memorandum dated February 18, 2015. Comments: The final plans have addressed these comments. 14) Prior to recording the Final Plat for any portion of the area shown in the Preliminary Plat, the Developer shall enter into a Developers Agreement acceptable to the City Attorney that delineates who is responsible for the design, construction, and payment of public improvements. Comments: A development agreement will be entered in to with the 3rd Addition. 15) The developer shall provide an easement over or dedicate in a separate outlot all trails to be dedicated for public use. Any such trails shall be considered a park land dedication provide said 6 trails are constructed by the developer with other public improvements within the subdivision. Comments: There are no trails proposed with the 3rd Addition. 16) The City will not approve a final plat for any portion of Wildflower until such time that the City has approved construction plans and received financial security related to the construction of the public improvement project to connect the 39th Street Sewer to the 30th Street lift station. Comments: This condition has been met and no longer applies. 17) The developer must follow all the rules and regulations of the Wetland Conservation Act, and adhere to the conditions of approval for the Valley Branch Watershed District Permit. Comments: The developers plan have been reviewed and approved by the Watershed District and grading work has been completed in accordance with this permit. 18) The developer shall maintain access to the Smith property (11514 Stillwater Boulevard North) during construction of the first development phase. Said access shall, at a minimum, be capable of supporting emergency management vehicles and be consistent with City access driveway standards. The existing driveway easement shall be vacated prior to the recording of the final plat. Comments: The driveway easement from the Smith property providing access to Stillwater Boulevard has been vacated. Easements to the City and Mr. Smith have expired upon the recording of the 2nd Addition Final Plat. Replacement easements were a condition of 2nd Addition Final Plat recording. 19) The developer shall establish a legally binding agreement to prevent further residential or commercial development of all outlots that are planned for open space or conservation uses within the preliminary plat. Comments: This condition has been met for the first phase and is was addressed in the second phase to protect Outlot A. Platting of future phases will require such an easement over Outlot P as indicated in the preliminary plat. There are no oulots that require a conservation easement within 3rd Addition. Planning Commission Review. The Planning Commission held a public hearing and reviewed the 3rd Addition Final Plat at its March 12, 2018 meeting. No one from the public spoke at the public hearing, though a number of inquiries regarding the final plat and PUD plans were received by Staff, as well as concern that the phasing was consistent with that indicated with the approved Preliminary Plat. The Planning Commission had initial concern about the grinder pump option in lieu of the lift station as proposed in the City Engineer memorandum, as experience with grinder pumps has been that they can get clogged up. However, after discussion with the City Engineer and assurance that the grinder pumps would need to be of good quality and that the two inch pipe would be maintained by the City, this concern was mitigated. The cost of the grinder pumps would be passed on to the homeowner, whereas the cost of lift station maintenance would be passed on through taxes. It was concluded that this decision should be left up to the City Engineer and developer. The Planning Commission recommended approval 6-0. RECOMMENDED CONDITIONS OF APPROVAL: Staff is recommending conditions as part of this final plat review to address issues highlighted in this report that include conditions of the preliminary plat that have not been fully addressed by the applicant. The City Engineer’s review memorandum dated March 1, 2018 identifies a number of 7 issues that need to be addressed by the developer in order for the City to deem the final plans complete. Based on the above Staff report and analysis, Staff is recommending approval of the final plat and final PUD development plans for phase two with the following conditions: Recommended Conditions of Approval: 1) The comments in the City Engineer’s review memorandum dated March 1, 2018 shall be addressed prior to releasing the plat for recording. Final construction plans shall be reviewed and approved by the City Engineer prior to the recording of the Final Plat. All changes and modifications to the plans requested by the City Engineer in a memorandum dated March 1, 2018 and any future reviews shall be incorporated into these documents before they are approved. 2) Prior to the execution of the Final Plat by City officials, the Developer shall enter into a Developer’s Agreement acceptable to the City Attorney and approved by the City Council that delineates who is responsible for the design, construction, and payment of the required improvements for the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Development Plans with financial guarantees therefore. 3) All easements as requested by the City Engineer and Public Works Department shall be documented on the Final Plat prior to the execution of the final plat by City Officials. 4) A Common Interest Agreement concerning management of the common areas of Wildflower at Lake Elmo 3rd Addition and establishing a homeowner’s association shall be submitted in final form to the Community Development Director before a building permit may be issued for any structure within this subdivision. 5) The applicant shall also enter into a landscape license/public art agreement and maintenance agreement with the City that clarifies the individuals or entities responsible for any landscaping and public art installed in areas outside of land dedicated as public park and open space on the final plat. 6) The landscape plan shall be reviewed and approved by the City prior to releasing the final plat for recording. 7) Street signs and no parking signs shall be installed on City Streets within the development prior to any building permits being issued. 8) Street names shall be given the suffix “N” prior to recording of final plat. 9) That the Developer adhere to the Alley Snow and Ice Removal Agreement regarding snow and ice removal from the Courtyard Alleys. DRAFT FINDINGS Staff is recommending that the Planning Commission consider the following findings with regards to the proposed Wildflower Final Plat and Final PUD Plans 8 1) That all the requirements of City Code Section 153.07 related to the Final Plan and Final Plat have been met by the Applicant. 2) That the proposed Final Plat for Wildflower at Lake Elmo 3rd Addition consists of the creation of 25 single-family detached residential structures. 3) That the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan is consistent with the Preliminary Plat and Plans as approved by the City of Lake Elmo on April 7, 2014. 4) That the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan is consistent with the Lake Elmo Comprehensive Plan and the Future Land Use Map for this area. 5) That the Wildflower at Lake Elmo 3rd Addition Final Plat generally complies with the City’s Urban Medium Density Residential zoning district, with the exceptions as noted in the approved Preliminary PUD Plans and PUD Agreement. 6) That the Wildflower at Lake Elmo 3rd Addition Final Plat complies with all other applicable zoning requirements, including the City’s landscaping, storm water, sediment and erosion control and other ordinances, except as noted in this report or attachment thereof. 7) That the Wildflower at Lake Elmo 3rd Addition Final Plat complies with the City’s subdivision ordinance. 8) That the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan complies with the City’s Planned Unit Development Ordinance. 9) That the Wildflower at Lake Elmo 3rd Addition Final Plat is consistent with the City’s engineering standards with the exceptions noted by the City Engineer in his review comments to the City dated March 1, 2018 and as otherwise identified in future reviews. RECOMMENDATION: Staff and the Planning Commission recommend approval of the Final Plat and Final Development Plans for Wildflower at Lake Elmo 3rd Addition with the 8 conditions of approval as listed in the Staff report. Suggested motion: “Move to adopt Resolution 2018-025 approving the final plat and PUD development plans for the Wildflower at Lake Elmo 3rd Addition with 9 conditions based on the findings listed in the staff report.” ATTACHMENTS: 1. Application and narrative 2. City Engineer Review Comments – 3/1/2018 3. Final Plat 4. Final Landscape Plan 5. Resolution 2018-025 651-747-3900 3800 Laverne Avenue North Lake Elmo, MN 55042 Date Received: ___________________ Received By: ____________________ Permit #: ________________________ LAND USE APPLICATION □ Comprehensive Plan □ Zoning District Amend □ Zoning Text Amend □ Variance*(see below) □ Zoning Appeal □ Conditional Use Permit (C.U.P.) □ Flood Plain C.U.P. □ Interim Use Permit (I.U.P.) □ Excavating/Grading □ Lot Line Adjustment □ Minor Subdivision □ Residential Subdivision Sketch/Concept Plan □ PUD Concept Plan □ PUD Preliminary Plan □ PUD Final Plan □ Wireless Communications Applicant: _____________________________________________________________________________________________ Address: ______________________________________________________________________________________________ Phone # _______________________________________ Email Address:___________________________________ Fee Owner: ___________________________________________________________________________________________ Address: ______________________________________________________________________________________________ Phone # _______________________________________ Email Address:___________________________________ Property Location (Address): ______________________________________________________________________________ (Complete (long) Legal Description: ________________________________________________________________________ _____________________________________________________________________________________________________ PID#: ________________________________________________________________________________________________ Detailed Reason for Request: _____________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ *Variance Requests: As outlined in Section 301.060 C. of the Lake Elmo Municipal Code, the applicant must demonstrate practical difficulties before a variance can be granted. The practical difficulties related to this application are as follows: _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ In signing this application, I hereby acknowledge that I have read and fully understand the applicable provisions of the Zoning ordinance and current administrative procedures. I further acknowledge the fee explanation as outlined in the application procedures and hereby agree to pay all statements received from the City pertaining to additional application expense. Signature of applicant:_______________________________________Date:_________________________________________ Signature of fee owner:______________________________________Date:_________________________________________ Wildflower at Lake Elmo 3rd Addition – Written Statements    2.a.) Owner: Robert Engstrom Companies    4801 West 81st Street, Suite 101    Minneapolis, MN 55437  Authorized Agents or Representatives:    Bob Engstrom    Paul Engstrom  Engineer & Surveyor:    John Molinaro & Peter Hawkinson    Pioneer Engineering, P.A.    2422 Enterprise Dr.     Mendota Heights, MN 55120  2.b.) Address:  Unassigned: Intersection of Wildflower Dr. & Swallowtail Lane     Unassigned: End of Currently Constructed Prairieview Trail   Current Zoning: PUD   Parcel Size: 19.88 acres; 866,126 ft2   Property Identification #’s: 12.029.21.34.0078 & 12.029.21.32.0008   Current Legal Description: Outlot P of Wildflower at Lake Elmo 1st Addition      Outlot B of Wildflower at Lake Elmo 2nd Addition  2.c.)   i) Name of Final Plat: Wildflower at Lake Elmo 3rd Addition   ii) Table  Bl o c k  #  Lo t  #  Si z e  (a c )   Wi d t h  at  Fr o n t   Se t b a c k *  (s f )   Av e r a g e  De p t h   (s f )   1 1 0.4319 120 179  1 2 0.3403 104 185  1 3 0.3717 82 162  1 4 0.4229 80 151  1 5 0.5020 88 159  1 6 0.4851 77 156  1 7 0.4795 86 186  1 8 0.5449 90 215  1 9 0.5892 93 227  1 10 0.5954 129 237  2 1 0.6083 109 240  2 2 0.3923 86 199  2 3 0.2975 86 151  3 1 0.1653 60 120  3 2 0.1653 60 120  3 3 0.1515 55 120  3 4 0.1774 65 120  4 1 0.1654 62 120  4 2 0.1405 51 120  4 3 0.1405 51 120  4 4 0.1654 62 120  5 1 0.1653 60 120  5 2 0.1653 60 120  5 3 0.1515 55 120  5 4 0.1758 65 120  *Width is at the non‐garage side of courtyard lots  (Blocks 3, 4 and 5)   iii) Final Area Calculations:    Park: 0    Trails: 0    Other: 0    Estimated Value of Dedicated Area: 0   iv) Final Area of Wetlands & Buffers    Wetlands: 0    Buffers: 0   v) Final Proposed right‐of‐ways: 3.5237 acres; 153,492 ft2  vi) Proposed legal descriptions for items not on Plat: NONE  2.d.) Addressing Issues since Preliminary Plat:   All items that have arisen have been addressed in the Final Platting Process.  2.e.) Density:    3rd Addition Lot Area: 7.99 acres   3rd Addition Lot #: 25   Density: 3.13 lots/acre  2.f.) Proposed infrastructure improvements & phasing:   1 Phase Development   Continuation of installed Wildflower at Lake Elmo 1st & 2nd improvements.  2.g.) Neighboring Properties Issues Addressed:   Developer has personally addressed issues with neighbors.  2.h.) Nearby Land Issues/Disturbances to wetlands or Natural Areas:   The project developed a Stormwater Management Plan with the review of the City of Lake  Elmo & the Valley Branch Watershed District to address and improve the watershed drainage  issues.  2.i.) Justification: Development is in conformance with approved Preliminary Plat.  2.j.) Lakeshore Access: NONE  2.k.) Parks & Open Space: Park and Open space dedication was completed with 1st Addition of Project.  2.l.) Development Timeline:   Begin Utilities: April ‐2018   Complete Utility Construction: June – 2018   Complete Street Construction: July – 2018   Complete Small Utility Construction: August – 2018   Complete Landscaping Installation: September ‐ 2018        PAGE 1 of 2  MEMORANDUM         Date:  March 1, 2018      To:  Emily Becker, Planning Director  Re:  Wildflower at Lake Elmo 3rd Addition – Final Plat   Cc:  Chad Isakson, P.E., Assistant City Engineer    Engineering Review Comments  From:  Jack Griffin, P.E., City Engineer          An engineering review has been completed for Wildflower at Lake Elmo 3rd Addition. Final Plat/Final Construction  Plans were received on February 14, 2018. The submittal consisted of the following documentation prepared by  Pioneer Engineering, or as noted:   Wildflower at Lake Elmo 3rd Addition Final Plat, printed February 9, 2018.   Wildflower at Lake Elmo 3rd Addition Construction Plans dated February 9, 2018.   Storm Sewer Design Calculations dated April 3, 2015.      STATUS/FINDINGS:   Engineering review comments have been provided in two separate memos; one for Final Plat  approval, and one to assist with the completion of the final Construction Plans.  Please see the following review  comments relating to the Final Plat application.      FINAL PLAT AND EASEMENTS: WILDFLOWER AT LAKE ELMO 3RD ADDITION   The Final Plat shall not be recorded until final construction plan approval is granted.   All easements as requested by the City Engineer and Public Works department shall be documented on the  Final Plat prior to the release of the Final Plat for recording.   Drainage and utility easements are required over each storm sewer outfall pipe, extending east from the  Wildflower 3rd Addition Plat, to the Outlot J storm water pond.   Small utility corridor easements, 10‐feet wide, should be provided along both sides of Prairieview Trail. Theses  easements are shown along all proposed lots but are also needed along all Outlots not owned by the City.   Wildflower at Lake Elmo 3rd Addition includes trunk watermain (12‐inch diameter) pipe oversizing along  Sunflower  Lane,  connecting  to  the  existing  12‐inch  watermain  in  the  Village  Preserve  subdivision  to  the  existing watermain along CSAH 14. Payment for pipe oversizing from the City standard 8‐inch pipe should be  addressed in the development agreement.     SANITARY LIFT STATION OPTIONS   This addition to Wildflower at Lake Elmo proposes a sanitary lift station to be owned and operated by the City  to provide sanitary sewer service for 13 lots along Prairieview Trail. Per the conditions of Preliminary Plat  approval,  the  sanitary  sewer  lift  station  will  be  designed  by  the  City’s  engineering  consultant,  at  the  developer’s costs, to ensure conformance with the City’s minimum design standards and consistency with  other lift station equipment in the City, including SCADA control systems.   As an alternative, City staff would consider allowing the construction of a low pressure sewer system using  individual grinder stations and a 2‐inch forcemain to service these lots, thereby removing the need for a larger  lift station to be owned and operated by the City. This consideration would be contingent upon the individual  grinder stations meeting City recommendations (similar to those specified by the City on recent projects) to  ensure longer lasting equipment is provided to each property owner.     FOCUS ENGINEERING, inc.  Cara Geheren, P.E.   651.300.4261  Jack Griffin, P.E.                651.300.4264  Ryan Stempski, P.E.  651.300.4267  Chad Isakson, P.E.  651.300.4283      PAGE 2 of 2  FINAL CONSTRUCTION PLANS & SPECIFICATIONS   Final Construction Plans and Specifications must be prepared in accordance with the City Engineering Design  Standards  Manual  dated  March  2017,  using  City  details,  plan  notes  and  specifications  and  meeting  City  Engineering Design Guidelines.   Final  Construction  Plans  and  Specifications  must  be  revised  in accordance  with  the  Construction  Plan  engineering review memorandum dated March 1, 2018.    No construction for Wildflower at Lake Elmo 3rd Addition may begin until the applicant has received City  Engineer  approval  for  the  Final  Construction  Plans  and  Specifications;  the  applicant  has  obtained  and  submitted  to  the  City  all  applicable  permits,  easements  and  permissions  needed  for  the  project;  and  a  preconstruction meeting has been held by the City’s engineering department.  CIVIL ENGINEERS LAND PLANNERS LAND SURVEYORS LANDSCAPE ARCHITECTS CIVIL ENGINEERS LAND PLANNERS LAND SURVEYORS LANDSCAPE ARCHITECTS CIVIL ENGINEERS LAND PLANNERS LAND SURVEYORS LANDSCAPE ARCHITECTS CIVIL ENGINEERS LAND PLANNERS LAND SURVEYORS LANDSCAPE ARCHITECTS CIVIL ENGINEERS LAND PLANNERS LAND SURVEYORS LANDSCAPE ARCHITECTS c OFWILDFLOWER 3RD ADDITION LAKE ELMO, MINNESOTA ROBERT ENGSTROM COMPANIES 4801 WEST 81ST STREET, SUITE 101 Name Reg. No.Date Revisions Date Designed Drawn 2015 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS MINNEAPOLIS, MINNESOTA 55437-1111 I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson 1. XX-XX-XXXX Revisions LANDSCAPE PLAN 3L12-9-2018 jlt jlt/tml2-9-18 c OFWILDFLOWER 3RD ADDITION LAKE ELMO, MINNESOTA ROBERT ENGSTROM COMPANIES 4801 WEST 81ST STREET, SUITE 101 Name Reg. No.Date Revisions Date Designed Drawn 2015 Pioneer Engineering, P.A. Mendota Heights, MN 55120 2422 Enterprise Drive (651) 681-1914 Fax: 681-9488www.pioneereng.com LANDSCAPE ARCHITECTSLAND SURVEYORSLAND PLANNERSCIVIL ENGINEERS MINNEAPOLIS, MINNESOTA 55437-1111 I hereby certify that this plan was prepared by me or under my direct supervision and that I am a duly Licensed Landscape Architect under the laws of the State of Minnesota 44763 Jennifer L. Thompson 1. XX-XX-XXXX Revisions LANDSCAPE PLAN 3L22-9-2018 jlt jlt/tml2-9-18 1 Resolution 2018-025 CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2018-025 A RESOLUTION APPROVING A FINAL PLAT AND FINAL PLANNED UNIT DEVELOPMENT (PUD) PLAN FOR THE WILDFLOWER AT LAKE ELMO 3RD ADDITION PLANNED RESIDENTIAL DEVELOPMENT WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing under the laws of the State of Minnesota; and WHEREAS, Robert Engstrom Companies, 4801 West 81st Street, #101, Bloomington, MN has submitted an application to the City of Lake Elmo (“City”) for a Final Plat and Final PUD Plan for the Wildflower at Lake Elmo 3rd Addition planned residential development, a copy of which is on file in the City of Lake Elmo Community Development Department; and WHEREAS, the City approved the Wildflower at Lake Elmo General Concept Plan on June 17, 2014; and WHEREAS, the City approved the Wildflower at Lake Elmo Preliminary Plat and Preliminary PUD Plan on April 7, 2015; and WHEREAS, the proposed Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan includes 25 single family residential lots within a planned development on Outlot O, Wildflower at Lake Elmo; and WHEREAS, the Lake Elmo Planning Commission held public hearing on March 12, 2018 to consider the Final Plat and Final PUD Plan request; and WHEREAS, the Lake Elmo Planning Commission adopted a motion recommending approval of the Final Plat and Final PUD Plan subject to 9 conditions of approval on March 12, 2018; and WHEREAS, the Lake Elmo Planning Commission has submitted its report and recommendation concerning the Final Plat and Final PUD Plan as part of a memorandum to the City Council for the March 20, 2018 Council Meeting; and WHEREAS, the City Council reviewed the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan at its meeting held on March 20, 2018 and made the following findings of fact: 1) That all the requirements of City Code Section 153.07 related to the Final Plan and Final Plat have been met by the Applicant, with the exceptions noted in the staff report. 2 Resolution 2018-025 2) That the proposed Wildflower at Lake Elmo 3rd Addition Final Plat consists of the creation of 25 single-family detached residential structures. 3) That the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan is consistent with the Preliminary Plat and Plans as approved by the City of Lake Elmo on April 7, 2014. 4) That the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan is consistent with the Lake Elmo Comprehensive Plan and the Future Land Use Map for this area. 5) That the Wildflower at Lake Elmo 3rd Addition Final Plat generally complies with the City’s Urban Medium Density Residential zoning district, with the exceptions as noted in the approved Preliminary PUD Plans. 6) That the Wildflower at Lake Elmo 3rd Addition Final Plat complies with all other applicable zoning requirements, including the City’s landscaping, storm water, sediment and erosion control and other ordinances, except as noted in this report or attachment thereof. 7) That the Wildflower at Lake Elmo 3rd Addition Final Plat complies with the City’s subdivision ordinance. 8) That the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan complies with the City’s Planned Unit Development Ordinance. 9) That the Wildflower at Lake Elmo 3rd Addition Final Plat is consistent with the City’s engineering standards with the exceptions noted by the City Engineer in his review comments to the City dated March 1, 2018 and as otherwise identified in future reviews. NOW, THEREFORE, BE IT RESOLVED THAT the City Council does hereby approve the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Plan subject to the following conditions: 1) The comments in the City Engineer’s review memorandum dated March 1, 2018 shall be addressed prior to releasing the plat for recording. Final construction plans shall be reviewed and approved by the City Engineer prior to the recording of the Final Plat. All changes and modifications to the plans requested by the City Engineer in a memorandum dated March 1, 2018 and any future reviews shall be incorporated into these documents before they are approved. 2) Prior to the execution of the Final Plat by City officials, the Developer shall enter into a Developer’s Agreement acceptable to the City Attorney and approved by the City Council that delineates who is responsible for the design, construction, and payment of the required improvements for the Wildflower at Lake Elmo 3rd Addition Final Plat and Final PUD Development Plans with financial guarantees therefore. 3 Resolution 2018-025 3) All easements as requested by the City Engineer and Public Works Department shall be documented on the Final Plat prior to the execution of the final plat by City Officials. 4) A Common Interest Agreement concerning management of the common areas of Wildflower at Lake Elmo 3rd Addition and establishing a homeowner’s association shall be submitted in final form to the Community Development Director before a building permit may be issued for any structure within this subdivision. 5) The applicant shall also enter into a landscape license/public art agreement and maintenance agreement with the City that clarifies the individuals or entities responsible for any landscaping and public art installed in areas outside of land dedicated as public park and open space on the final plat. 6) The landscape plan shall be reviewed and approved by the City prior to releasing the final plat for recording. 7) Street signs and no parking signs shall be installed on City Streets within the development prior to any building permits being issued. 8) Street names shall be given the suffix “N” prior to recording of final plat. 9) That the Developer adhere to the Alley Snow and Ice Removal Agreement regarding snow and ice removal from the Courtyard Alleys. Passed and duly adopted this 20th day of March, 2018 by the City Council of the City of Lake Elmo, Minnesota. ___________________________________ Mike Pearson, Mayor ATTEST: ____________________________________ Julie Johnson, City Clerk