HomeMy WebLinkAbout#21 - OV Phase 4 Plans & Specs STAFF REPORT
DATE: April 17, 2018
REGULAR
ITEM #: 21
AGENDA ITEM: Old Village Phase 4 Street and Utility Improvements – Resolution Approving
Plans and Specifications and Ordering Advertisement for Bids
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Rob Weldon, Public Works Director
Chad Isakson, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve the plans and specifications and order
advertisement for bids for the Old Village Phase 4 Street and Utility Improvements?
BACKGROUND: On February 20, 2018 the City Council ordered the preparation of the plans and
specifications for the Old Village Phase 4 Street and Utility Improvements. The improvements include the
extension of lateral sanitary sewer mains along 32nd Street North, east of Lake Elmo Avenue, and along 36th
Street North/Layton Avenue North. The improvements include the reconstruction of the existing streets
with concrete curb and gutter, the addition of storm sewer improvements to improve drainage to the extent
possible within the project limits and right-of-way, the replacement of the aged watermain, and a sanitary
sewer service stub extended to the property line for each benefitting property. The project also consists of
the installation of a regional storm sewer outfall pipe as another extension of the City’s regional downtown
storm sewer system and considers the addition of a trail extension along 36th Street North to connect Lion’s
Park to the VFW Park.
The scope of improvements remains consistent with the preliminary plans that were presented to the City
Council on February 20th, 2018. Park improvements were added to the scope of improvements based on
staff direction and as part of the project restoration.
PROPOSAL DETAILS/ANALYSIS: The plans and specifications have been completed for the
improvements and are ready to be advertised for contractor bids. A bid date has been scheduled for May
10, 2018. Once received, bids will be reviewed by staff and with recommendations to be presented to
council on May 15, 2018 to award a contract.
FISCAL IMPACT: The estimated total cost for the Old Village Phase 4 Street and Utility Improvements
is $2,152,000. The improvements are proposed to be partially assessed against the benefitting properties
consistent with the City’s Special Assessment Policy. The project is funded through the issuance of general
obligation bonds and special assessments.
Approval of this motion does not commit the council to the project costs. Once contractor bids are received,
the actual construction costs will be known and the council will be asked to consider entering into a contract
to complete the work.
RECOMMENDATION: Staff is recommending that the City Council approve Resolution 2018-045
approving the plans and specifications and ordering the advertisement for bids for the Old Village Phase 4
Street and Utility Improvements. The recommended motion for the action is as follows:
“Move to approve Resolution No. 2018–045, approving the plans and specifications and ordering the
advertisement for bids for the Old Village Phase 4 Street and Utility Improvements.”
ATTACHMENTS:
1. Resolution approving the plans and specifications and ordering the advertisement for bids for the
Old Village Phase 4 Street and Utility Improvements.
2. Location Map.
3. Project Schedule.
4. Project Plans and Specifications available for review at City Hall.
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2018-045
A RESOLUTION APPROVING PLANS AND SPECIFICATIONS AND
ORDERING ADVERTISEMENT FOR BIDS FOR THE
OLD VILLAGE PHASE 4 STREET AND UTILITY IMPROVEMENTS
WHEREAS, pursuant to a resolution passed by the City Council on the 20th day of February
2018, the City Engineer, together with SEH, Inc., has prepared plans and specifications for the Old
Village Phase 4 Street and Utility Improvements and has presented such plans and specifications to the
Council for approval.
NOW, THEREFORE, BE IT RESOLVED,
1. Such plans and specifications, a copy of which is on file at Lake Elmo City Hall, and made a part
hereof, are hereby approved.
2. The City Clerk shall prepare and cause to be inserted in the official paper and posted online with
Quest Construction Data Network (QuestCDN.com) an advertisement for bids upon the making
of such improvements under such approved plans and specifications. The advertisement shall be
published for at least 21 days, shall specify the work to be done, and shall state that sealed bids
provided to the City Clerk prior to the specified bid date and time and accompanied by a bid bond
or cashier’s check made payable to the City of Lake Elmo in an amount not less than 5% of the
amount of such bid will be considered.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE SEVENTEENTH DAY OF APRIL,
2018.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
(Seal) Mayor
ATTEST:
________________________________
Julie Johnson
City Clerk
Old Village Capital Improvement Plan
Phasing Plan; Schedule and
Assessment Methodology
SEPTEMBER 6, 2016 FOCUS ENGINEERING, inc.
OLD VILLAGE CIP – PHASING PLAN
PHASE 3
PHASE 4
PHASE 5
PHASE 7
PHASE6
PHASE 6
PHASE 4
PHASE 3
NOT
INCLUDED
NOT
INCLUDEDNOT INCLUDED
NOT
INCLUDED
PROJECT SCHEDULE
CITY OF LAKE ELMO
OLD VILLAGE PHASE 4: STREET AND UTILITY IMPROVEMENTS
PROJECT NO. 2017.157
DECEMBER 2017
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
SEPTEMBER 5, 2017 Council authorizes preliminary design and preparation of the Feasibility Report.
FEBRUARY 20, 2018 Council orders the preparation of Plans and Specifications.
APRIL 17, 2018 Presentation of Feasibility Report. Council accepts Report and calls Improvement
Hearing and Assessment Hearing.Approve Plans and Specifications and Order
Advertisement for Bids.
MAY 10, 2018 Receive Contractor Bids.
MAY 15, 2018 Public Improvement Hearing and Final Assessment Hearing. Council Orders the
Improvement (requires 4/5th vote); Adopts the Final Assessments. Council accepts
Bids and awards Contract.
JUNE 5, 2018 Conduct Pre‐Construction Meeting and issue Notice to Proceed.
•OCTOBER 27, 2018 Substantial Completion.
•JUNE 21, 2019 Final Completion.