HomeMy WebLinkAbout#11 - 2018 Seal Coat Project - Copy STAFF REPORT
DATE: May 15, 2018
CONSENT
ITEM #: 11
AGENDA ITEM: 2018 Seal Coat Project – Accept Bids and Award Contract
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Rob Weldon, Public Works Director
Amanda Groh, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept bids and award a contract for the 2018
Seal Coat Project?
PROPOSAL DETAILS/ANALYSIS: Bids were received, publicly opened, and read aloud at City Hall
on Thursday, May 3, 2018. FOCUS Engineering, Inc. has prepared and attached the Tabulation of Bids
and a Letter of Recommendation for the award of the contract. The City received three (3) bids for this
project, with Pearson Bros, Inc. providing the lowest bid. Staff is recommending that Pearson Bros, Inc.
be awarded the contract in the amount of $147,103.06, which includes the amount of $54,480.46 for the
City of Lake Elmo, the amount of $54,507.60 for West Lakeland Township, and the amount of
$38,115.00 for Denmark Township.
The project will be completed jointly with West Lakeland Township and Denmark Township with each
Township reimbursing Lake Elmo their portion of the construction cost in the bid award amount of
$92,622.60 (63%). Each Township will also pay Lake Elmo $3,000 for engineering and administration
fees once the Lake Elmo City Council accepts the bids and awards the construction contract.
Construction observation services will be contracted directly by each jurisdiction for the work performed
on their streets.
FISCAL IMPACT: $54,480.46.
The post-bid construction estimate for Lake Elmo is $54,480.46 (37%). The total engineering design,
bidding and construction services is estimated to be $8,500 less $6,000 to be reimbursed by West
Lakeland Township and Denmark Township. The Lake Elmo total post-bid project cost is therefore
estimated to be $56,980.46 to be paid through the General Fund (Fund No. 101-430-3120-42250).
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the consent
agenda, Resolution No. 2018-048 accepting the bids and awarding a Contract to Pearson Bros, Inc. If
removed from consent agenda, the recommended motion for this action is as follows:
“Move to approve Resolution No. 2018-048 Accepting the Bids and Awarding a Contract to Pearson
Bros, Inc. in the Bid amount of $147,103.06 for the 2018 Seal Coat Project; which includes $54,480.46
for the City of Lake Elmo, $54,507.60 for West Lakeland Township, and $38,115.00 for Denmark
Township.”
ATTACHMENTS:
1. Resolution No. 2018-048 Accepting Bids and Awarding Contract.
2. Engineer’s Letter of Award Recommendation and Tabulation of Bids.
3. Project Schedule.
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2018-048
A RESOLUTION ACCEPTING THE BIDS AND AWARDING A
CONTRACT FOR THE 2018 SEAL COAT PROJECT
WHEREAS, pursuant to an advertisement for bids for the 2018 Seal Coat Project, bids were
received, opened, and tabulated according to law, and bids were received complying with the
advertisement; and
WHEREAS, bids were tabulated, checked and summarized to verify that all requirements of the
submittals were met; and
WHEREAS, the project engineer reviewed the bids and has provided a letter recommending the
award of the contract to the lowest responsible bidder, Pearson Bros, Inc. in the amount of
$147,103.06.
NOW, THEREFORE, IT IS HEREBY RESOLVED,
1. That the Mayor and City Clerk are hereby authorized and directed to enter into a Contract
in the accordance with the above ordered Project, in the amount of the Contractor’s lowest
responsible bid, and according to the plans and specifications thereof approved by the City
Council.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids, except that the deposits of the successful bidder and the next
two lowest bidders shall be retained until a contract has been signed.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE FIFTEENTH DAY OF
MAY 2018.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
Mayor
(Seal)
ATTEST:
________________________________
Julie Johnson
City Clerk
May 3, 2018
Jack Griffin, P.E.
City Engineer
City of Lake Elmo
3880 Laverne Avenue North, Suite 100
Lake Elmo, Minnesota 55042
2018 Seal Coat Project
City of Lake Elmo, Minnesota
Project No. 2018.109
Dear Mr. Griffin,
Attached is a complete tabulation of Bids for the 2018 Seal Coat Project. Bids were received at City Hall at
3:00 PM on Thursday, May 3, 2018.
Contractor Base Bid
Allied Blacktop Company
City of Lake Elmo $55,857.20
Denmark Township $39,501.00
West Lakeland Township $57,535.80
TOTAL: $152,894.00
Astech Corporation
City of Lake Elmo $70,297.70
Denmark Township $50,935.50
West Lakeland Township $74,190.90
TOTAL: $195,424.10
Pearson Bros, Inc.
City of Lake Elmo $54,480.46
Denmark Township $38,115.00
West Lakeland Township $54,507.60
TOTAL: $147,103.06
We recommend that you award the Contract to the lowest responsible bidder for the Project to Pearson
Bros, Inc. in the total amount of $147,103.06. This includes the amount of $54,480.46 for the City of Lake
Elmo, the amount of $38,115.00 for West Lakeland Township, and the amount of $54,507.60 for Denmark
Township.
Please contact me with any questions you may have.
Sincerely,
Amanda E Groh, P.E.
Project Engineer
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
TABULATION OF BIDS
2018 SEAL COAT PROJECT
CITY OF LAKE ELMO, WEST LAKELAND TWP & DENMARK TWP
PROJECT NO. 2018.109
BIDS OPENED: MAY 3, 2018, AT 3:00 PM
ITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL
NO.DESCRIPTION QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
CITY OF LAKE ELMO
1 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK AND CRS-2P EMULSIFIED ASPHALT 43,310 SY 1.14$ 49,373.40$ 1.47$ 63,665.70$ 1.09$ 47,207.90$
2 4" DOUBLE SOLID YELLOW PAVEMENT MARKING 3,070 LF 0.90$ 2,763.00$ 1.00$ 3,070.00$ 1.00$ 3,070.00$
3 4" SINGLE SOLID LINE WHITE PAVEMENT MARKING 6,824 LF 0.45$ 3,070.80$ 0.50$ 3,412.00$ 0.44$ 3,002.56$
4 HANDICAP PAVEMENT MARKING 2 EA 325.00$ 650.00$ 75.00$ 150.00$ 600.00$ 1,200.00$
55,857.20$ 70,297.70$ 54,480.46$
DENMARK TOWNSHIP
5 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK AND CRS-2P EMULSIFIED ASPHALT 34,650 SY 1.14$ 39,501.00$ 1.47$ 50,935.50$ 1.10$ 38,115.00$
CITY OF WEST LAKELAND
6 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK AND CRS-2P EMULSIFIED ASPHALT 50,470 SY 1.14$ 57,535.80$ 1.47$ 74,190.90$ 1.08$ 54,507.60$
TOTAL 152,894.00$ 195,424.10$ 147,103.06$
Pearson Bros, Inc.Allied Blacktop Company Astech Corporation
PROJECT SCHEDULE
CITY OF LAKE ELMO
2018 SEAL COAT PROJECT
PROJECT NO. 2018.109
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
APRIL 5, 2018 Placement of Advertisement for Bids.
–Oakdale-Lake Elmo Review. Publication on April 11
– Quest CDN. Publication on April 11
MAY 3, 2018 Receive Contractor bids.
MAY 15, 2018 Council accepts bids and awards Contract. Approve JSA with WLT
JUNE 13, 2018 Conduct Pre-construction meeting and Issue Notice to Proceed.
JUNE 14, 2018 Contractor begins Work.
AUGUST 17, 2018 Substantial Completion of Work; including sweeping of excess aggregate and
pavement markings.
SEPTEMBER 14, 2018 Final Completion of Work; including punchlist and final documentation.