HomeMy WebLinkAbout#12 - Easton Village 1st Security Reduction STAFF REPORT DATE: May 15, 2018 CONSENT ITEM #: 12 AGENDA ITEM: Easton Village 1st Addition – Accept Improvements and Approve Reduction of Security SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Emily Becker, Planning Director Rob Weldon, Public Works Director ISSUE BEFORE COUNCIL: Should the City Council accept the improvements and approve security reductions for Easton Village 1st Addition? PROPOSAL DETAILS/ANALYSIS: Staff has received and processed a request to accept the improvements and to reduce the development security for Easton Village 1st Addition. This request has been reviewed and the following reduction is being recommended: Current Security Amount Proposed Security Amount 1. Easton Village 1st Addition: $ 1,248,878 $ 771,771 The Easton Village 1st Addition public improvements have been completed in accordance with the development agreement dated August 6, 2015 with the exception of Landscaping, and Tree Preservation and Restoration. The improvements are in the warranty period per the attached Certificate of Completion. A security amount of 25% of the original security will be retained until the warranty period has expired. Landscaping Improvements will be accepted separately and with different warranty dates. FISCAL IMPACT: It is the City’s goal to retain at all times during the subdivision improvements a security amount that is adequate to ensure completion of all elements of the improvements as protection to the City tax payers against the potential of developer default. RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda, accept the improvements and approve the security reductions for Easton Village 1st Addition as detailed in the respective worksheet. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to accept the improvements and approve security reduction for Easton Village 1st Addition as detailed in the respective Security Reduction Worksheet”. ATTACHMENTS: 1. Easton Village 1st Addition – Engineers Certificate of Acceptance. 2. Security Reduction Worksheets – Easton Village 1st Addition. EASTON VILLAGE 1ST ADDITION Time of Performance:  June 30, 2016 DEVELOPMENT AGREEMENT AMOUNTS CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6 Grading $728,739 $910,924 100%$910,924 Sanitary Sewer $293,960 $367,450 75%$275,588 Watermain $303,289 $379,111 75%$284,333 Storm Sewer (w/pond structures) $585,943 $732,429 75%$366,214 $183,107 Streets $526,489 $658,111 75%$329,056 $164,528 Sidewalks/Trails $98,777 $123,471 75%$61,736 $30,868 Surface Water Facilities NA NA Street Lighting NA NA Street Signs and Traffic Control Signs $5,600 $7,000 75%$5,250 Private Utilities (electricity, natural gas, telephone, and cable)NA Landscaping $110,781 $138,476 75%$69,238 Tree Preservation and Restoration $164,435 $205,544 75%$102,772 Wetland Mitigation and Buffers NA NA Monuments $30,000 $37,500 75%$28,125 Erosion Control $68,678 $85,848 75%$64,386 Miscellaneous Facilities NA NA Record Drawings $6,500 $8,125 75%$6,094 TOTALS $2,923,191 $3,653,989 RELEASED AMOUNTS:$559,921 $1,845,189 $477,107 $0 $0 $0 $685,766 CUMMULATIVE AMOUNTS:$559,921 $2,405,110 $2,882,218 SECURITY AMOUNT REMAINING:$3,094,068 $1,248,878 $771,771 DATE:8/2/2016 12/20/2016 5/15/2018 REDUCTIONS