HomeMy WebLinkAbout#17 - Old Village Phase 4 Accept Bids and Award Contract STAFF REPORT
DATE: May 15, 2018
REGULAR
ITEM #: 17
AGENDA ITEM: Old Village Phase 4 Street, Drainage, and Utility Improvements – Accept Bids
and Award Contract
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Rob Weldon, Public Works Director
Chad Isakson, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept bids and award a contract for the Old
Village Phase 4 Street, Drainage and Utility Improvements?
BACKGROUND: On February 20, 2018 the City Council ordered the preparation of the plans and
specifications for the Old Village Phase 4 Street, Drainage and Utility Improvements. The improvements
include the extension of lateral sanitary sewer mains along 32nd Street North, east of Lake Elmo Avenue,
and along 36th Street North/Layton Avenue North. The improvements include the reconstruction of the
existing streets with concrete curb and gutter, the addition of storm sewer improvements to improve
drainage to the extent possible within the project limits and right-of-way, the replacement of the aged
watermain, and a sanitary sewer service stub extended to the property line for each benefitting property.
The project also consists of the installation of a regional storm sewer outfall pipe as another extension of
the City’s regional downtown storm sewer system and considers the addition of a trail extension along 36th
Street North to connect Lion’s Park to the VFW Park.
The scope of improvements remains consistent with the preliminary plans that were presented to the City
Council on February 20th, 2018. Park improvements were added to the scope of improvements based on
staff direction and as part of the project restoration.
PROPOSAL DETAILS/ANALYSIS: Bids will be received, publicly opened, and read aloud on
Thursday, May 10, 2018. The Tabulation of Bids and engineer’s recommendation for the award of the
contract will be presented to the City Council at the meeting.
As a part of this award Staff is requesting Council to provide the City Administrator authorization to
purchase individual grinder stations from a supplier in the not-to-exceed amount of $50,000 and enter into
a material testing contract in the not-to-exceed amount of $20,000. Additionally, staff is recommending
that the City Council approve a supplemental task order with SEH to provide construction observation
services in an amount not to exceed $160,000. Each of these items are budgeted in the total cost figures
presented below and are necessary to complete the project.
The City Council approved the Plans and Specifications for the Old Village Phase 4 Street, Drainage, and
Utility Improvements on April 17, 2018 and authorized staff to advertise the Project for bids. The Project
was advertised on QuestCDN.com and in the Oakdale-Lake Elmo Review in accordance with the Minnesota
Competitive Bidding requirements.
FISCAL IMPACT: Approval of this resolution commits the council to enter into a construction contract
for the project. The estimated total cost for the Old Village Phase 4 improvements is $2,152,000 with the
street and drainage improvements estimated at $1,086,000; the sanitary sewer improvements estimated at
$460,000; the watermain improvements estimated at $374,000; and the park and trail improvements at
$232,000. The street, drainage, and sanitary improvements are proposed to be assessed against the
benefitting properties consistent with the City’s Special Assessment Policy and the Old Village Sewer
Assessment Policy.
RECOMMENDATION: Staff is recommending that the City Council approve a resolution accepting bids
and awarding a contract per the engineer’s recommendation as presented at the meeting, for the Old Village
Phase 4 Street, Drainage and Utility Improvements. Staff is also recommending that the City Council
authorize the City Administrator to purchase individual grinder stations from a supplier in the not-to-exceed
amount of $50,000, enter into a material testing contract in the not-to-exceed amount of $20,000, and
authorize a supplemental task order with SEH to provide construction observation services in an amount
not to exceed $160,000. The recommended motions for these actions are as follows:
“Move to approve Resolution No. 2018–058, accepting bids and awarding a contract per the engineer’s
recommendation as presented at the meeting for the Old Village Phase 4 Street, Drainage, and Utility
Improvements.”
and
“Move to authorize the City Administrator to purchase individual grinder stations from a supplier in
the not-to-exceed amount of $50,000; to enter into a material testing contract in the not-to-exceed
amount of $20,000; and to approve a supplemental task order with SEH to provide construction
observation services in an amount not to exceed $160,000.”
ATTACHMENTS:
1. Resolution Accepting Bids and Awarding a Contract for the Old Village Phase 4 Street, Drainage,
and Utility Improvements.
2. Project Schedule.
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2018-058
A RESOLUTION ACCEPTING BIDS AND AWARDING A CONTRACT
FOR THE OLD VILLAGE PHASE 4 STREET, DRAINAGE, AND UTILITY
IMPROVEMENTS
WHEREAS, pursuant to an advertisement for bids for the Old Village Phase 4: Street,
Drainage, and Utility Improvements, bids were received, opened, and tabulated according to law,
and bids were received complying with the advertisement; and
WHEREAS, bids were tabulated, checked and summarized to verify that all
requirements of the submittal were met; and
WHEREAS, the project engineer reviewed the bids and has provided a letter
recommending the award of the contract to the lowest responsible bidder, , for
the amount of $ .
NOW, THEREFORE, BE IT RESOLVED,
1. That the Mayor and City Clerk are hereby authorized and directed to enter into a Contract
in the accordance with the above ordered Project, in the amount of the Contractor’s
lowest responsible bid, and according to the plans and specifications thereof approved by
the City Council.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids, except that the deposits of the successful bidder and the
next two lowest bidders shall be retained until a contract has been signed.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE FIFTEENTH DAY OF
MAY, 2018.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
(Seal) Mayor
ATTEST:
________________________________
Julie Johnson
City Clerk
PROJECT SCHEDULE
CITY OF LAKE ELMO
OLD VILLAGE PHASE 4: STREET AND UTILITY IMPROVEMENTS
PROJECT NO. 2017.157
DECEMBER 2017
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
SEPTEMBER 5, 2017 Council authorizes preliminary design and preparation of the Feasibility Report.
FEBRUARY 20, 2018 Council orders the preparation of Plans and Specifications.
APRIL 17, 2018 Presentation of Feasibility Report. Council accepts Report and calls Improvement
Hearing and Assessment Hearing.Approve Plans and Specifications and Order
Advertisement for Bids.
MAY 10, 2018 Receive Contractor Bids.
MAY 15, 2018 Public Improvement Hearing and Final Assessment Hearing. Council Orders the
Improvement (requires 4/5th vote); Adopts the Final Assessments. Council accepts
Bids and awards Contract.
JUNE 5, 2018 Conduct Pre-Construction Meeting and issue Notice to Proceed.
•OCTOBER 27, 2018 Substantial Completion.
•JUNE 21, 2019 Final Completion.