Loading...
HomeMy WebLinkAbout#10 - I-94 Lift Station CO3 STAFF REPORT DATE: June 19, 2018 CONSENT ITEM# 10 AGENDA ITEM: I-94 Lift Station (No. 1) and Sanitary Sewer Improvements - Change Order No. 3 SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Rob Weldon, Public Works Director Chad Isakson, Project Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 3 for the I-94 Lift Station (No. 1) and Sanitary Sewer Improvements? BACKGROUND: RL Larson Excavating, Inc. was awarded a construction contract to complete the I-94 Lift Station (No. 1) and Sanitary Sewer Improvements on May 2, 2017. Construction remains in progress with some site work and restoration remaining. PROPOSAL DETAILS/ANALYSIS: RL Larson Excavating, Inc. has submitted a change order to revise the substantial completion date from November 17, 2017 to July 27, 2018 and revises the final completion date from December 15, 2017 to August 17, 2018. The extended construction contract completion period was needed to allow for the delay in ordering and delivery of the revised lift station pumps previously approved by the City as Change Order No. 1 and weather conditions turning in early November 2017 preventing further roadway improvements being constructed. Also, a change order is needed to address additional work items requested by the City to be completed by the contractor, including sanitary sewer manhole extensions and additional pavement surface to enhance access and maintenance at the lift station site. This change order also addresses quantity overruns mainly associated with rebuilding the shoulder and turn lane on Hudson Boulevard. Poor soils were discovered during the construction causing an overrun of roadway materials. FISCAL IMPACT: None. This change order increases the contract amount by $62,338.80 for a total contract amount of $889,332.22. With this change the project remains below the feasibility project budget but is $29,500 over the project amount that the City bonded for. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 3 for the I-94 Lift Station (No. 1) and Sanitary Sewer Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 3 for the I-94 Lift Station (No. 1) and Sanitary Sewer Improvements, thereby revising the substantial completion date from November 17, 2017 to July 27, 2018; revising the final completion date from December 15, 2017 to August 17, 2018; and increasing the contract amount by $62,338.80”. ATTACHMENTS: 1. Change Order No. 3. CONTRACT CHANGE ORDER FORM CHANGE ORDER NO. DATE: TO: UNIT Amount of Original Contract $ Sum of Additions/Deductions approved to date (CO No. 1, 2) $ Contract Amount to date $ Amount of this Change Order   (ADD)   (DEDUCT)   (NO CHANGE)$ Revised Contract Amount $ The Contract Period for Completion will be   (UNCHANGED)  (INCREASED)  (DECREASED)days APPROVED BY ENGINEER:  FOCUS ENGINEERING APPROVED BY CONTRACTOR DATE DATE APPROVED BY OWNER:  CITY OF LAKE ELMO, MINNESOTA DATE DATE 245 This Document will become a supplement to the Contract and all provisions will apply hereto. The Contract Documents are  modified as follows upon execution of this Change Order.  BYENGINEER 809,129.70 17,853.72 826,983.42 62,338.80 889,322.22 INCREASE/(DECREASE) RL Larson Excavating, Inc., 2255 12th Street SE, St. Cloud, MN 56304 I‐94 LIFT STATION (NO. 1) AND SANITARY SEWER IMPROVEMENTS PROJECT NO. 2016.134 3 June 19, 2018 ITEM $62,338.80 NET CONTRACT CHANGE $62,338.80 CITY OF LAKE ELMO, MINNESOTA BYBY CHANGE ORDER DESCRIPTION / JUSTIFICATION: This Change Order revises the substantial completion date from November 17, 2017 to July 27, 2018 and revises the final  completion date from December 15, 2017 to August 17, 2018. The extended construction contract completion period was  needed to allow for the delay in ordering and delivery of the revised lift station pumps previously approved by the City as  Change Order No. 1 and weather conditions turning in early November 2017 preventing further roadway improvements being  constructed. The City is requesting the contractor to complete additional work on the I‐94 Lift Station Improvement project. Additional  pavement at the lift station site has been requested by Public Works for access, maintenance, and operation purposes. In  addition, two sanitary sewer manholes need to be raised to match the field graded ditch section and to meet City standards. This change order also addresses quantity overruns mainly associated with rebuilding the shoulder and turn lane on Hudson  Boulevard. Poor soils were discovered during the construction causing an overrun of roadway materials. Attachments  (list documents supporting change):Itemization DESCRIPTION OF PAY ITEM QTY UNIT PRICE **See attached itemization** 6/13/2018 FOCUS Engineering, inc.CHANGE ORDER FORM CHANGE ORDER NO. 3 I‐94 LIFT STATION (NO. 1) AND SANITARY SEWER IMPROVEMENTS CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2016.134 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 LS 1 $30,000.00 $30,000.00 0.00 $0.00 1.00 $30,000.00 2 LS 1 $6,300.00 $6,300.00 0.00 $0.00 1.00 $6,300.00 3 LS 1 $33,000.00 $33,000.00 0.00 $0.00 1.00 $33,000.00 4 EA 5 $315.00 $1,575.00 2.00 $630.00 7.00 $2,205.00 5 SY 1,500 $4.00 $6,000.00 10.00 $40.00 1,510.00 $6,040.00 6 SY 30 $10.00 $300.00 ‐20.90 ‐$209.00 9.10 $91.00 7 LF 80 $10.00 $800.00 3.00 $30.00 83.00 $830.00 8 LF 180 $10.00 $1,800.00 0.00 $0.00 180.00 $1,800.00 9 LF 1,770 $4.00 $7,080.00 ‐3.00 ‐$12.00 1,767.00 $7,068.00 10 REMOVE AND DIPSOSE OF EXISTING STORM SEWER PIPE LF 175 $10.00 $1,750.00 ‐2.00 ‐$20.00 173.00 $1,730.00 11 EA 7 $500.00 $3,500.00 0.00 $0.00 7.00 $3,500.00 12 LF 20 $10.00 $200.00 ‐20.00 ‐$200.00 0.00 $0.00 13 EA 1 $55.00 $55.00 0.00 $0.00 1.00 $55.00 14 EA 1 $130.00 $130.00 0.00 $0.00 1.00 $130.00 15 EA 4 $160.00 $640.00 0.00 $0.00 4.00 $640.00 16 LF 1,300 $2.50 $3,250.00 447.00 $1,117.50 1,747.00 $4,367.50 17 EA 2 $4,200.00 $8,400.00 1.00 $4,200.00 3.00 $12,600.00 18 EA 5 $1,500.00 $7,500.00 0.00 $0.00 5.00 $7,500.00 19 EA 2 $1,605.00 $3,210.00 0.00 $0.00 2.00 $3,210.00 20 LF 445 $45.00 $20,025.00 ‐2.00 ‐$90.00 443.00 $19,935.00 21 LF 920 $46.00 $42,320.00 0.00 $0.00 920.00 $42,320.00 22 LF 55 $117.00 $6,435.00 0.00 $0.00 55.00 $6,435.00 23 LF 356 $56.00 $19,936.00 0.00 $0.00 356.00 $19,936.00 24 LF 20 $93.00 $1,860.00 56.00 $5,208.00 76.00 $7,068.00 25 EA 1 $3,317.00 $3,317.00 0.00 $0.00 1.00 $3,317.00 26 EA 5 $1,025.00 $5,125.00 0.00 $0.00 5.00 $5,125.00 27 EA 7 $3,500.00 $24,500.00 1.00 $3,500.00 8.00 $28,000.00 28 VF 12 $120.00 $1,440.00 8.66 $1,039.20 20.66 $2,479.20 29 EA 1 $4,200.00 $4,200.00 0.00 $0.00 1.00 $4,200.00 30 CY 50 $20.00 $1,000.00 20.00 $400.00 70.00 $1,400.00 31 CY 50 $50.00 $2,500.00 20.00 $1,000.00 70.00 $3,500.00 32 LF 1,792 $1.35 $2,419.20 0.00 $0.00 1,792.00 $2,419.20 33 LS 1 $350,000.00 $350,000.00 0.00 $0.00 1.00 $350,000.00 34 LS 1 $53,000.00 $53,000.00 0.00 $0.00 1.00 $53,000.00 35 LS 1 $28,000.00 $28,000.00 0.00 $0.00 1.00 $28,000.00 36 EA 3 $750.00 $2,250.00 0.00 $0.00 3.00 $2,250.00 37 EA 2 $1,650.00 $3,300.00 0.00 $0.00 2.00 $3,300.00 38 LF 60 $44.00 $2,640.00 ‐14.00 ‐$616.00 46.00 $2,024.00 39 LF 20 $20.00 $400.00 ‐20.00 ‐$400.00 0.00 $0.00 40 LF 32 $47.00 $1,504.00 0.00 $0.00 32.00 $1,504.00 41 EA 2 $1,064.00 $2,128.00 0.00 $0.00 2.00 $2,128.00 42 LF 120 $33.00 $3,960.00 ‐60.00 ‐$1,980.00 60.00 $1,980.00 43 EA 4 $350.00 $1,400.00 ‐2.00 ‐$700.00 2.00 $700.00 44 CY 6 $70.00 $420.00 0.00 $0.00 6.00 $420.00 45 LS 1 $5,000.00 $5,000.00 0.00 $0.00 1.00 $5,000.00 46 SY 450 $15.75 $7,087.50 57.00 $897.75 507.00 $7,985.25 47 CY 450 $35.00 $15,750.00 112.21 $3,927.35 562.21 $19,677.35 48 SY 130 $2.00 $260.00 ‐130.00 ‐$260.00 0.00 $0.00 49 CY 125 $12.00 $1,500.00 ‐35.04 ‐$420.48 89.96 $1,079.52 50 TON 700 $20.00 $14,000.00 612.00 $12,240.00 1,312.00 $26,240.00 51 TON 450 $89.00 $40,050.00 85.00 $7,565.00 535.00 $47,615.00 52 LF 80 $37.00 $2,960.00 10.00 $370.00 90.00 $3,330.00 53 SF 130 $10.50 $1,365.00 ‐65.00 ‐$682.50 65.00 $682.50 54 EA 1 $800.00 $800.00 ‐0.75 ‐$600.00 0.25 $200.00 55 SF 12 $51.00 $612.00 ‐12.00 ‐$612.00 0.00 $0.00 56 EA 1 $500.00 $500.00 0.00 $0.00 1.00 $500.00 57 EA 1 $350.00 $350.00 1.00 $350.00 2.00 $700.00 58 LF 1 $1,000.00 $1,000.00 0.00 $0.00 1.00 $1,000.00 59 EA 1 $360.00 $360.00 0.00 $0.00 1.00 $360.00 60 SF 9 $55.00 $495.00 0.00 $0.00 9.00 $495.00 61 EA 6 $100.00 $600.00 0.00 $0.00 6.00 $600.00 62 LF 1,000 $1.26 $1,260.00 553.00 $696.78 1,553.00 $1,956.78 63 EA 2 $500.00 $1,000.00 0.00 $0.00 2.00 $1,000.00 64 HR 5 $140.00 $700.00 4.00 $560.00 9.00 $1,260.00 65 SY 6,600 $1.74 $11,484.00 490.00 $852.60 7,090.00 $12,336.60 66 SY 100 $2.60 $260.00 ‐100.00 ‐$260.00 0.00 $0.00 67 AC 1.3 $210.00 $273.00 0.06 $12.60 1.36 $285.60 68 EA 5 $180.00 $900.00 ‐5.00 ‐$900.00 0.00 $0.00 69 EA 7 $52.00 $364.00 ‐1.00 ‐$52.00 6.00 $312.00 70 LF 200 $3.15 $630.00 ‐200.00 ‐$630.00 0.00 $0.00 TOTALS ‐ BASE CONTRACT $809,129.70 $35,992.80 $845,122.50 INLET PROTECTION DITCH CHECK 4" SOLID LINE WHITE EPOXY PAVEMENT MESSAGE, RIGHT TURN ARROW THERMOPLASTIC (GROUND IN) STREET SWEEPING EROSION CONTROL BLANKET TEMPORARY HYDROMULCH SEEDING ADJUST GATE VALVE BOX HYDRANT EXTENSION EXTEND VALVE BOX SIGN PANEL, TYPE C OFF ROAD STRUCTURE MARKER B618 CONCRETE CURB AND GUTTER 4" CONCRETE MEDIAN 6" CONCRETE PEDESTRIAN RAMP TRUNCATED DOME PANELS ADJUST MANHOLE CASTING COMMON EXCAVATION (DRIVEWAY AND STREET PATCHES) GEOTEXTILE FOR ROAD STABILIZATION SELECT GRANULAR BORROW AGGREGATE BASE, CLASS 6 TYPE SP 9.5 BITUMINOUS WEARING COURSE MIXTURE (2,B) 18" CM DRIVEWAY CULVERT 18" CM APRON RIPRAP CLASS III LIFT STATION SITE GRADING BITUMINOUS DRIVEWAY PAVEMENT (LIFT STATION) SALVAGE AND REINSTALL STORM SEWER STRUCTURE SALVAGE AND REINSTALL STORM SEWER PIPE PERFORATED PVC EDGE DRAIN 18" RCP STORM SEWER, CLASS V 18" RCP FLARED END SECTION WITH TRASH GUARD TELEVISING LIFT STATION STANDBY GENERATOR BYPASS PUMPING SALVAGE AND REINSTALL APRON 4' DIAMETER SANITARY SEWER MANHOLE 4' DIAMETER EXCESS MANHOLE DEPTH MANHOLE LINER REMOVAL OF UNSTABLE FOUNDATION MATERIAL ROCK FOUNDATION BORROW 15" PVC, SDR 35 SANITARY SEWER PIPE, 15' ‐ 20' DEEP 16" PVC, C900 SANITARY SEWER PIPE, 0' ‐ 10' DEEP 16" DIP, CL 50 SANITARY SEWER PIPE, 0' ‐ 10' DEEP 16" SANITARY SEWER OUTSIDE DROP 15" X 6" WYE BRANCH REVISED CONTRACT AMOUNT REMOVE AND DISPOSE OF EXISTING SANITARY SEWER MANHOLE REMOVE AND DISPOSE OF EXISTING EDGE DRAIN REMOVE AND DISPOSE OF EXISTING SIGN SALVAGE AND REINSTALL MAILBOX ITEM DESCRIPTION OF PAY ITEM UNIT CHANGE ORDER NO. 3 REMOVE AND DISPOSE OF EXISTING CONCRETE PAVEMENT ORIGINAL CONTRACT CONNECT TO EXISTING SANITARY SEWER SERVICE MOBILIZATION TRAFFIC CONTROL PRECAST CONCRETE JERSEY BARRIERS SILT FENCE CONNECT EXISTING PIPE TO NEW MANHOLE TREE REMOVAL REMOVE AND DISPOSE OF EXISTING BITUMINOUS PAVEMENT REMOVE AND DISPOSE OF EXISTING CONCRETE CURB AND GUTTER REMOVE AND DISPOSE OF EXISTING GUARDRAIL REMOVE AND DISPOSE OF EXISTING SANITARY SEWER PIPE SAWING BITUMINOUS PAVEMENT CORE DRILL CONNECTION TO EXISTING STRUCTURE SALVAGE AND REINSTALL SIGN 15" PVC, SDR 35 SANITARY SEWER PIPE, 0' ‐ 10' DEEP 15" PVC, SDR 35 SANITARY SEWER PIPE, 10' ‐ 15' DEEP CHANGE ORDER NO. 1 CO1‐1 EA 3 5,951.24$            $17,853.72 0 $0.00 3 $17,853.72 TOTALS ‐ CHANGE ORDER NO. 1 $17,853.72 $0.00 $17,853.72 CHANGE ORDER NO. 3 CO3‐1 LS 9,400.00$            $0.00 1.00 $9,400.00 1.00 $9,400.00 CO3‐2 LS 3,900.00$            $0.00 1.00 $3,900.00 1.00 $3,900.00 CO3‐3 LF 4.60$                   $0.00 200.00 $920.00 200.00 $920.00 CO3‐4 TN 30.00$                 $0.00 14.00 $420.00 14.00 $420.00 CO3‐5 TN 22.00$                 $0.00 40.00 $880.00 40.00 $880.00 CO3‐6 CY 52.00$                 $0.00 10.00 $520.00 10.00 $520.00 CO3‐7 CY 42.00$                 $0.00 80.00 $3,360.00 80.00 $3,360.00 CO3‐8 CY 34.00$                 $0.00 24.00 $816.00 24.00 $816.00 CO3‐9 LS 1,800.00$            $0.00 1.00 $1,800.00 1.00 $1,800.00 CO3‐10 AC 4,500.00$            $0.00 0.20 $900.00 0.20 $900.00 CO3‐11 LS 1,635.00$            $0.00 1.00 $1,635.00 1.00 $1,635.00 CO3‐12 LS 1,795.00$            $0.00 1.00 $1,795.00 1.00 $1,795.00 TOTALS ‐ CHANGE ORDER NO. 3 $0.00 $26,346.00 $26,346.00 TOTALS ‐ CHANGE ORDER NO. 3 $62,338.80 $889,322.22 ADD 2' SECTION COMMON EXCAVATION (SHOULDER / TURN LANE) TOPSOIL STRIPING SEEDING ADD 1' SECTION AGGREGATE BASE, CLASS 6 (SHOULDER / TURN LANE) COMMON EXCAVATION (LIFT STATION SITE) REVISE PUMP DESIGN MOBILIZATION TRAFFIC CONTROL REMOVE PAVEMENT MARKING AGGREGATE BASE CLASS 5 (LIFT STATION SITE)