HomeMy WebLinkAbout#18 Eden Park Storm Sewer Repair STAFF REPORT DATE: 6/19/2018 REGULAR ITEM #: 18 MOTION TO: City Council FROM: Rob Weldon, Public Works Director AGENDA ITEM: Eden Park Storm Sewer Repair REVIEWED BY: Kristina Handt, City Administrator Chad Isakson, Asst. City Engineer BACKGROUND: The Eden Park Neighborhood of Lake Elmo is bordered by 20th St. N to the south, open space to the north, Lake Elmo Ave to the west, and Downs Lake to the east. On Lisbon Ave. within Eden Park, storm water runoff is collected and discharged to Downs Lake. Over time, the discharge/outfall pipe to Downs Lake has become blocked with debris resulting in pipe failure and subsequent washout of the pipe, manhole structure and surrounding landscape. ISSUE BEFORE COUNCIL: Should the council approve repairs to the storm water discharge/outfall pipe and structure on Lisbon Ave. in the Eden Park Neighborhood? PROPOSAL DETAILS/ANALYSIS: Engineering and Public Works have created a repair plan and quote package to address the storm sewer repair and restoration of existing landscape. Since the discharge point of the pipe is located a significant distance from the road, access will the gained through side yards of two adjoining properties over an existing easement. Staff has initiated property owner engagement and both property owners support the project. The scope of the project will largely replace the existing storm water pipe and structure in kind. Some tree removal will be necessary to access the work area. After completion of pipe work the area will be graded and seeded, this will include disturbed yard areas of both adjoining properties. FISCAL IMPACT: Not to exceed $30,000 funded through CIP Storm Sewer System Improvements. OPTIONS: • Approve Eden Park Storm Sewer Repair • Deny Eden Park Storm Sewer Repair RECOMMENDATION: “Motion to approve repairs of Eden Park Storm sewer for an amount not to exceed $30,000 to C. W. Houle Inc.” Page 2 ATTACHMENTS: • Repair Quote Package • C.W. Houle Inc. - Quote • Dahn Construction - Quote Table of Contents for Eden Park Storm Sewer Repair    March 5, 2018               CITY OF LAKE ELMO, MINNESOTA  EDEN PARK STORM SEWER REPAIR  PROJECT NO. 2018.117                  TABLE OF CONTENTS       TITLE                                                                                                                                PAGES    Cover & Table of Contents  1    Construction Contract  2     Quote Proposal  2    Improvement Plan  1      Specification Sections  18 City of Lake Elmo, Minnesota General Conditions for Small Contracts Page 1 of 2 State of Minnesota Washington County CONSTRUCTION CONTRACT FOR THE EDEN PARK STORM SEWER REPAIR This Contract, made this ________ day of _____________________ 2018, by the City of Lake Elmo, Minnesota (herinafter called the “Owner”) and _____________________ (hereinafter called the “Contractor”). WITNESSETH that the parties hereto agree as follows: (A) The Contractor shall provide all labor, services, materials, equipment and machinery, transportation, tools, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals, including profit and overhead, necessary for the performance, testing, start-up, and completion of the work as described herein: IN WITNESS WHEREOF, the parties hereto have executed this contract as of the date first above written. (Contractor) (City of Lake Elmo) DESCRIPTION OF WORK: Contractor shall replace a storm sewer pipe per the plan and subsequent specifications as attached to the quote package dated March, 2018. Actual quantities will be measured and paid per the unit price provided in the quote form completed by the Contractor. No additional work in excess of the estimated quantities listed on the quote form will be paid unless approved by the City of Lake Elmo, prior to the work being completed. All work shall be completed within the specified time frame and under the terms and conditions provided within this Construction Contract, and in accordance with the “General Conditions” shown in this contract. The contractor shall complete the proposed work by September 30, 2018. The Owner will make payment for the whole contract upon acceptance by the Owner of all work required hereunder and in compliance with all the terms and conditions of this contract. TOTAL PROJECT COST (INSERT FROM QUOTE FORM): __________________________________ City of Lake Elmo, Minnesota General Conditions for Small Contracts Page 2 of 2 GENERAL CONDITIONS I. CHANGES IN WORK. - The Owner may at any time, make changes in the drawings and specifications, within the general scope thereof. If such changes cause an increase or decrease in the amount due under this contract or in the time required for its performance, an equitable adjustment will be made, and this contract will be modified accordingly by a “Contract Change Order”. No charge for any extra work or material will be allowed unless the same has been ordered on such contract change order by the Owner and the price therefore stated in the order. II. INSPECTION OF WORK. - All materials and workmanship will be subject to inspection, examination, and test, by the Owner, who will have the right to reject defective material and workmanship or require its correction. III. COMPLETION OF WORK. - If the Contractor refuses or fails to complete the work within the time specified in paragraph B of this contract, or any extension thereof, the Owner may terminate the Contractor’s rights to proceed. In such event the Owner may take over the work and prosecute the same to completion by contract or otherwise, and the Contractor will be liable for any excess cost occasioned the Owner thereby; and the Owner may take possession of and utilize in completing the work such materials and equipment as may be on the site of the work and necessary therefore. If the Owner does not terminate the right of the Contract to proceed, the Contractor will continue the work, in which event, actual damages for delay will be impossible to determine, and in lieu thereof, the Contractor may be required to pay to the Owner the sum of $100 as liquidated damages for each calendar day of delay, and the Contractor will be liable for the amount thereof: Provided, however, that the right of the Contractor to proceed will not be terminated because of delays in the completion of the completion of the work due to unforeseeable causes beyond the Contractor’s control and without Contractor’s fault or negligence. IV. RELEASES. - Prior to final payment, the Contractor will submit evidence that all payrolls, material bills, and other indebtedness connected with the work have been paid as required by the Owner. V. OBLIGATION TO DISCHARGE LIENS. - Acceptance by the Owner of the completed work performed by the Contractor and payment therefore by the Owner will not relieve the Contractor of obligation to the Owner (which obligation is hereby acknowledged) to discharge any and all liens for the benefit of subcontractors, laborers, material-person, or any other persons performing labor upon the work or furnishing material or machinery for the work covered by this contract, which have attached to or may subsequently attach to the property, or interest of the Owner. VI. NOTICES AND APPROVAL IN WRITING. - Any notice, consent, or other act to be given or done hereunder will be valid only if in writing. VII. CLEANING UP. - The Contractor shall keep the premises free from accumulation of waste material and rubbish and at the completion of the work shall remove from the premises all rubbish, implements and surplus materials. VIII. WARRANTY. - Contractor warrants and guarantees that title to all work, materials, and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to Owner no later than the time of payment free and clear of all Liens. If within one year after completion of the work, any work is found to be defective, Contractor shall promptly, without cost to the Owner, correct such defective work as approved by the Owner. IX. IDEMNIFICATION. - Contractor shall defend and indemnify the city against claims brought or actions filed against the city or any of its officers, employees or agents for property damage, bodily injury or death to third persons, arising out of or relating to contractors work under the contract. X. WORKERS’ COMPENSATION INSURANCE. - Contractor shall provide a certificate of insurance showing evidence of workers’ compensation coverage or provide evidence of qualification as a self-insurer of workers’ compensation. XI. LIABILITY INSURANCE REQUIREMENTS. – A certificate of insurance acceptable to the City shall be filed with the City prior to the commencement of the work. The certificate and the required insurance policies shall contain a provision that the coverage afforded under the contract will not be canceled or allowed to expire until at least 30 days prior written notice has been given to the city. Contractor shall maintain commercial general liability (CGL) insurance with a limit of not less than $1,000,000 each occurrence and an aggregate limit of not less than $2,000,000. The CGL insurance shall cover liability arising from premises, operations, independent contractors, subcontractors, products-completed operations, personal injury and advertising injury, and contractually-assumed liability. The city shall be named as an additional insured under the CGL. Contractor shall maintain automobile liability insurance, and if necessary, umbrella liability insurance with a limit of not less than $1,000,000 each accident and an aggregate limit of not less than $2,000,000. The insurance shall cover liability arising out of any auto, including owned, hired, and non-owned autos. QUOTE PROPOSAL FOR  EDEN PARK STORM SEWER REPAIR  PROJECT NO. 2018.117  CITY OF LAKE ELMO, MINNESOTA  ITEM  NO. ITEM  UNIT  QUANTITY   UNIT PRICE    TOTAL AMOUNT   1  MOBILIZATION  LS  1        2  CLEARING AND GRUBBING  SY  200      3  REMOVE AND DISPOSE OF EXISTING  STORM SEWER PIPE (ALL SIZES, INCLUDING  FES)  LF  120      4 REMOVE AND DISPOSE OF EXISTING  STORM SEWER MANHOLE EA  1      5 REMOVE AND DISPOSE OF WOVEN WIRE  FENCE LF  40      6  15” RC PIPE SEWER, DES 3006  LF  120      7  CONST DRAINAGE STRUCTURE TYPE 406  (W/ CASTING) (INCLUDES DIAMETER  SIZING AND CONNECT TO EXISTING 12‐ INCH RCP)  EA  1      8  15” FES W/ TRASHGUARD  EA  1      9  CLASS 3 RIP RAP  CY  4      10  SEEDING  SY  200      11 EROSION CONTROL BLANKET CATEGORY  3N SY  200      12  IMPORT BORROW MATERIAL TO FILL  ERODED CHANNEL AND RE‐ESTABLISH  COVER OVER PIPE (LV)  CY  170      13  IMPORT TOPSOIL (LV) (6‐INCH DEPTH)  CY  65      14  SODDING TYPE LAWN  SY  100      TOTAL EDEN PARK STORM SEWER REPAIR  PROJECT       $  The quantities herein are approximate only. Payment will be made for the actual quantities of work ordered and installed. We have examined the site of the work and are acquainted with all conditions affecting the construction of the work. We understand and agree that the City may chose to award the project to the lowest responsible quote or in the best interest of the City. The City reserves the right to reject any or all quotes, to waive any informalities in any Quote, and to omit any part of the above work. We agree that if this Proposal is accepted, we will execute a Contract in the form attached to this bid package. If we are awarded the Contract, we will complete the work by September 30, 2018. Respectfully submitted, Firm Name Signature Signed by Title Contact Phone Number Address 400A STANDARD DRAWING NO. LAKE ELMO CITY OF LAKE ELMO MARCH 2017 406 STANDARD DRAWING NO. LAKE ELMO CITY OF LAKE ELMO MARCH 2017 411 STANDARD DRAWING NO. LAKE ELMO CITY OF LAKE ELMO MARCH 2017 Lake Elmo Developer Master 3111‐1  Revision date: March 2017  SECTION 3111 – CLEARING AND GRUBBING SCOPE:  Under  this  Section  of  the  Specifications  shall  be  included  the Clearing  and  Grubbing  operation  within  the  construction limits and areas for excavation and grading.  EXECUTION  1. CLEARING.  The  clearing  operation  shall  consist  of  cutting  and  removing  the  trees,  shrubs,  bushes,  windfalls, and other vegetation designated for removal and within the construction limits. Trees not  designated for removal shall be protected and saved from damage. Tree removal shall be only allowed in  accordance with the City approved Tree Preservation and Replacement Plans.  2. GRUBBING. The grubbing operation shall consist of removing and disposing of the stumps, roots, and  other  remains.  Unless  otherwise  permitted,  stumps  shall  be  removed  completely.  If  any  stumps  are  permitted to remain, they shall be cut off not more than six inches above ground.  3. TREE PRESERVATION. Trees not designated for removal shall be protected and saved from damage during  construction. All trees shall be protected by placing brightly colored high density polyethylene safety  fence around or along the trees. The protective fencing must be placed to protect the critical root zone of  the trees. Should any damage happen to occur to the trunks or branches of trees along the project, the  damage shall be treated in accordance with nursery approved methods. Any broken branches shall be  trimmed as per Engineer's direction. All bruise and cut wounds shall be treated with asphalt base tree  paint.  Removal of tree fence may result in a Stop Work Order.  4. DISPOSAL OPERATIONS. All timber, stumps, roots, and other debris or byproducts resulting from the  clearing and grubbing operations shall be disposed of by the Contractor in accordance with the provisions  of  MnDOT  Specification  2104.3C  as  applied  to  combustible  materials,  subject  to  the  additional  requirements and limitations set forth herein.  All Elmwood timber, stumps, roots, and debris, together with the bark and any byproducts with adhering  bark of Elm tree origin, that are not disposed of within the right‐of‐way by burning or burying shall be  disposed of in accordance with MnDOT Specification 2101.3D2. All timber, stumps, roots, and debris from  oak wilt infested trees of the Red Oak family shall be disposed of in accordance with MnDOT Specification  2101.3D2.  If  any  wood  is  run  through  a  chipping  machine,  the  wood  chips  shall  be  recovered,  removed,  and  disposed of properly. Materials shall not be left on‐site unless otherwise approved by the Engineer.  END OF SECTION  Lake Elmo Developer Master 3123‐1  Revision date: March 2017  SECTION 3123 – TRENCH EXCAVATION AND BACKFILLING SCOPE:  This Section of the Specifications shall include the excavation, trenching, and backfill required for the underground  utility systems.  EXECUTION:  1. CONSTRUCTION REQUIREMENTS.  A. Trench  Preparation.  The  sewer  or  watermain  excavation  and  trench  preparation  shall  be  in  accordance  with  Article  2600.3B,  Excavation  and  Preparation  of Trench  in  the  City  Engineer  Association of Minnesota Standard Specifications. The Earth Foundation Bedding Method as shown  in the Standard Detail Drawings shall be used for all pipe installation (excluding PVC sanitary sewer)  where groundwater or unstable material does not create a problem. PVC sanitary sewer shall be  installed in accordance with the Granular Material Bedding Method Standard Detail. Where unstable  material prevents use of standard bedding methods, the Contractor shall install Granular Bedding or  Trench Stabilization Rock as directed by the Engineer.  B. Backfilling. Backfill of the utility trenches shall be in accordance with the following methods. Utilize  Type  “B”  backfilling  methods  within  any  street  or  roadway  and  shoulders  and  also  within  all  driveways. Utilize Type “D” backfilling methods in the ditches or open areas where roadways or  proposed housepads will not be affected.  Mixtures  of  gravel  meeting  the  Granular  Material  Gradation  Classifications  for  those  zones  as  outlined in the Standard Utility Specification shall be spread in three‐inch layers and hand tamped or  compacted by approved mechanical methods to a density of 95% of Standard Proctor Density by the  Mn/DOT “Specified Density Method.” Care shall be taken to deposit the material simultaneously on  both sides of the pipe for the full width of the trench. At the top of the encasement zone, the  backfill shall be well compacted by using mechanical tamping equipment in such manner so as not  to damage the pipe joints or shift the pipe alignment. The Contractor may not use water to obtain  compaction at the pipe zone.  All surplus and unusable or waste material shall be disposed of in conformance with Mn/DOT 2105.  Backfilling shall not be done in freezing weather except by permission of the Engineer, and it shall  not be made with frozen material nor where the material already in the trench is frozen. After  backfilling  has  been  accomplished,  the  Contractor  shall  be  responsible  for  furnishing  backfill  or  surfacing  material  as  necessary  and  filling  settlement  depressions  resulting  from  inadequate  compaction or any other construction defect until the acceptance of the Work.  In areas receiving Type “B” backfilling, settlement after one year of one inch or more from finish  grade shall be considered evidence of inadequate compaction and the area shall be restored at the  Contractor’s expense.  Lake Elmo Developer Master 3123‐2  Revision date: March 2017  1. Type “B” Backfilling. Type ”B” backfilling consists of placing suitable materials excavated from  the trench in succeeding 12 inch thick layers from a point 12 inch from the top of the pipe.  Each 12 inch thick layer shall be compacted before additional backfill material is placed in the  excavation.  The top 12 inch of this backfill shall be compacted with the use of a sheepsfoot roller or  approved similar compaction equipment. Only approved mechanical tamping or compacting  will be allowed. Use of bucket compaction or wheel rolling will not be permitted.  The  density  of  the  backfilled  material  after  compaction  shall  be  95%  of  Standard  Proctor  Density from the encasement zone to three feet below the surface and 100% of Standard  Proctor Density in the upper three feet. One test for each 500 feet, or fraction thereof, of pipe  installed is required. A minimum of one test daily when backfilling is required. The testing shall  be repeated for each three‐foot vertical lift. Additional testing may be required where deemed  necessary in the opinion of the Engineer.  If the existing moisture content of the backfill material below three feet of subgrade is greater  than 3 percentage points above the optimum moisture content, the soil shall be compacted to  a minimum density of 3 pounds per cubic feet less than the standard Proctor curve at that  moisture content. At no time shall the density be less than 90 percent of the standard Proctor  density. This modification of the compaction specification shall at no time be used or applied to  the upper 3 feet of the subgrade or the aggregate base. This modification of the compaction  specification  may not be used without prior written approval from the City Engineer. This  modification of the compaction specification will not be allowed to be used if the contractor  does not implement appropriate construction techniques to dry or keep dry all backfill material  prior to the written request.  Suitable backfill material may contain any mixture of loam, clay, sand, or course gravel, but  shall be free of stones, boulders, chunks, or lumps with any dimension greater than eight  inches and shall contain no ashes, refuse, rubbish, roots, frozen material, or vegetation or  organic material that would cause settlement. In any case, where rocks are present in the  backfill material, adequate sand shall also be present and mixed in to fill all voids.  2. Type  “D”  Backfilling.  The  backfill  material  shall  be  free  from boulders,  rock,  concrete  and  bituminous chunks, and clay lumps more than one‐foot in any dimension and shall contain no  stumps,  rubbish,  decayed  vegetation,  or  frozen  materials  and  other  similar  articles  where  presence in the backfill would cause excessive settlement. The backfill may be placed in three‐ foot layers and compacted by wheel type equipment weighing not less than six tons.  If the compaction of the backfill material is specifically authorized by the Engineer to be done  by flooding the trench, the Contractor shall exercise due precautions so as not to float the pipe  or permit water to enter the pipe, causing mud to be deposited in the pipe. The Contractor  shall be wholly responsible for neglect of his workmen in carrying out the proper precautions.  If the existing moisture content of the backfill material below three feet of subgrade is greater  than 3 percentage points above the optimum moisture content, the soil shall be compacted to  a minimum density of 3 pounds per cubic feet less than the standard Proctor curve at that  moisture content. At no time shall the density be less than 90 percent of the standard Proctor  density.  This  modification  of  the  compaction  specification  may not  be  used  without  prior  written approval from the City Engineer. This modification of the compaction specification will  not be allowed to be used if the contractor does not implement appropriate construction  techniques to dry or keep dry all backfill material prior to the written request.    Lake Elmo Developer Master 3123‐3  Revision date: March 2017  The density obtained in Type “D” trench backfilling shall be 95% of Standard Proctor Density  above the pipe encasement zone. One test for each 500 feet, or fraction thereof, of pipe  installed is required. The testing shall be repeated for each three‐foot vertical lift.  C. Trench Limits.  When the trench excavation limits exceed the right‐of‐way/easement boundaries  and/or  there  are  obstructions  (trees,  private/public  utilities, etc.) that need to be left in place  undamaged, the contractor will be responsible for adjusting the trench limits accordingly to protect  these items shown on the plans, or as directed by the Engineer.   D. TRENCH SAFETY. The Contractor shall be responsible for trench/stockpiling safety at all times during  the construction process. Further, the Contractor shall backfill all trench excavations at the end of  the work day and for weekends. If the Engineer concurs that a trench  location  may  be  left  unbackfilled overnight or on weekends, then the Contractor shall be responsible for securing the  trench area in accordance with OSHA regulations and guidelines (e.g., safety fencing, etc.).    END OF SECTION  Lake Elmo Developer Master 3124‐1  Revision date: March 2017  SECTION 3124 – EXCAVATION AND EMBANKMENT SCOPE:  This Work shall consist of constructing roadway excavations and embankments as shown on the Plans, and in  accordance with MnDOT Specification 2105.  PRODUCTS:  1. MATERIALS.  Granular  borrow  material  shall  be  in  accordance  with  the  requirements  of  MnDOT  Specification 2105.  EXECUTION:  1. EXCAVATION shall conform to the planned grades and cross sections. All topsoil and organic material shall  be removed below the typical section.  2. EMBANKMENTS shall be constructed from approved excess excavation material. Compaction shall be as  follows:  A. 100% Standard Proctor Density in the upper three feet of the planned subgrade. One test for each  500 feet, or fraction thereof, of roadway prepared is required with a minimum of one test each work  day.  B. 95% Standard Proctor Density below three feet from the planned subgrade. One test for each 500  feet, or fraction thereof, of roadway prepared is required with a minimum of one test each work  day. The testing shall be repeated for each three‐foot vertical lift.  3. TOPSOIL shall be salvaged and placed to a six‐inch minimum depth on all disturbed areas outside the  finished roadway.  END OF SECTION  Lake Elmo Developer Master  3292‐1  Revision date:  March 2017   SECTION 3292 – TURF ESTABLISHMENT AND RESTORATION SCOPE:  Under this Section of the Specifications shall be included the general clean‐up and restoration of areas disturbed  by construction, and the temporary and permanent turf establishment measures for seeding and sodding.  GENERAL REQUIREMENTS:  1. RESTORATION OF PAVED SURFACES If the Project requires cutting through a sidewalk, trail, street or  private property, the Contractor will be required to restore these areas within five working days after  completing the work or installation.  PRODUCTS:  1. FERTILIZER Commercial fertilizer, analysis 23‐0‐30, MnDOT Specification 3881, shall be spread at the rate  of 350 pounds per acre.  2. TOPSOIL. The topsoil shall meet MnDOT Specification 3877, for the applicable area to be restored. Unless  otherwise called for on the Plans, the top soil shall meet MnDOT Specification 3877‐A Common Topsoil  Borrow with at least 6.0% organic matter.  3. SEED  The  grass  seed  mixtures  shall  meet  MnDOT  Specification  3876, for the applicable area to be  restored. Unless otherwise called for on the Plans, the grass seed shall meet MnDOT Specification 3876,  Seed Mixture 25‐141 applied at a rate of 70 pounds per acre. In high maintained areas such as residential  and commercial lawns, Seed Mixture 25‐151 shall be applied at a rate of 120 pounds per acre. The seed  mixture for temporary erosion control shall comply with MnDOT Specification 3876, Seed Mixture series  21‐112 as applicable and only with prior approval by the Engineer.  4. SOD All sod shall meet the requirements of MnDOT Specification 3878 for the applicable area to be  restored. Unless otherwise called for on the Plans, the sod shall meet MnDOT Specification 3878.2A Lawn  Sod,  a  premium  quality  sod  for  use  in  high  maintained  areas,  such  as  lawns.  Native  Sod,  MnDOT  Specification 3878.2E, an average to high density sod with low maintenance requirements, may be used  in ditch bottoms and at pipe inlets or outlets.  5. WOOD FIBER BLANKET The erosion control blanket shall be MnDOT 3885 Category 3, Type 2S (netting on  both sides), and shall be made of wood fiber material. Straw fiber material will not be allowed.  6. MULCH Type 3 Mulch meeting the requirements of MnDOT Specification 3882.  7. HYDRAULIC EROSION CONTROL PRODUCTS. Type Bonded Fiber Matrix. (BFM) meeting the requirements  of MnDOT Specification 3884, dyed green.  EXECUTION:  1. TURF  ESTABLISHMENT  The  requirements  and  operations  for  tilling,  fertilizing,  seeding,  sodding  and  mulching shall be in accordance with MnDOT Specification 2575. Seed or sod restoration shall be applied  as designated on the Plans.  Boulevards shall be graded upon completion of curb work and graded to allow for placement of six inches  of topsoil and two rows of sod. Beyond the sod the Contractor shall place heavy duty silt fence along each  lot line and seed the remaining boulevard and disturbed areas. When a platted lot is not adjacent to the  boulevard  the  entire  boulevard  shall  be  restored  with  quality  lawn  sod.  Seeding  shall  be  completed  beyond designated sod limits.   Lake Elmo Developer Master  3292‐2  Revision date:  March 2017   2. SOIL PREPARATION Finished grades shall slope uniformly between elevations shown and shall meet flush  with walks and pavement. Allow for the thickness of sod, as applicable. The finished Work shall be true,  smooth and sightly.  Topsoil shall be spread smooth but shall not be compacted. Topsoil shall be raked free of lumps and rocks  to provide a smooth, mowable surface. Sticks, stones, and trash over one inch, shall be removed. The  surface  shall  be  finished  to  the  designated  slope  and  contour. The  topsoil  shall  be  loosened  and  thoroughly pulverized by discing to a depth of six inches.   Fertilizer shall be spread and worked into the top six inches of soil during preparation. Apply fertilizer in  two passes at approximately right angles to each other, each pass placing approximately half of the  fertilizer.   3. SEEDING  Seeding  shall  be  done  between  April  1  and  June  1  or  between  July  20  and   September 20, except as otherwise may be allowed by the Engineer. Reseeding will be required as may be  necessary to obtain a satisfactory stand of grass. Sow seed (for lawn areas) uniformly at the seed mixture  specified application rate, adjusting for the certified purity and germination.   Seeds  are  to  be  sown  by  hand  operated  or  machine  operated  mechanical  seeder,  which  shall  continuously  mix  the  seeds  to  prevent  segregation.  Seeding  shall  be  performed  in  two  passes  at  approximately right angles, each pass placing approximately half of the seed. Immediately after the seed  has been sown, the entire area shall be raked lightly and rolled lightly to pack the soil firmly around the  seed.  4. WOOD  FIBER  BLANKET  Erosion  control  fabric  shall  be  placed  on  all slopes at 3:1 or greater, where  indicated on the plans, and in ditches. Erosion control fabric shall be placed over newly seeded areas  within 24 hours of seeding. Install in accordance with the manufacturer's instructions, including spacing  anchors.  5. MULCH Seeded areas shall be mulched and disc‐anchored with the specified mulch type, except where  plastic netting or hydraulic erosion control products for stabilization are specified. Mulch shall be spread  by mechanical means to provide a uniform distribution at the target application rate. When poor mulch  distribution occurs The Contractor will be required to remulch areas where coverage is too light and  remove excess where coverage is too heavy, as determined by the Engineer.  6. SODDING Sod operations shall not be started until all necessary equipment, supplies, and labor forces are  available to sufficiently place the sod without avoidable delays. Immediately before the sod is laid, the  prepared bed shall be sprinkled until all of the loose material is moist. Sodding shall be done only when  soil and weather conditions are favorable. The sod strips shall be carefully placed by hand beginning at  the toes of the slopes and progressing upwards, the length of the strips as nearly as practical at right  angles to the direction of the flow of the surface water. All joints shall be tightly butted and the end joints  shall  be  staggered  at  least  12  inches.  After  sod  has  been  placed,  the  sod  shall  be  pressed  into  the  underlying soil by rolling or tamping. The sod shall be pegged with suitable wood stakes as necessary to  keep it in place.  7. MAINTENANCE The Contractor shall water and maintain seeded and sodded areas on a timely basis as the  need arises and without the Engineer having to so order. Seed, Mulch, Erosion Control Fabric and Sod  shall be maintained until final acceptance of the improvements by the City. The Contractor shall promptly  replace all sod that dries out, or is damaged, displaced, or weakened, or is heavily infected by weed  growth.  Seeded  areas  shall  be  reseeded  as  necessary  to  establish  a  permanent  vegetative  cover  acceptable to the City.  END OF SECTION  Lake Elmo Developer Master 3340‐1  Revision date: March 2017  SECTION 3340 – STORM DRAINAGE UTILITIES SCOPE:  Under this Section shall be included the complete construction of a storm sewer extension within the street right‐ of‐way  or  easement.  The  sewer  shall  be  laid  as  shown  on  the  Plans,  including  manholes  and  all  necessary  excavation and backfilling, as required.  GENERAL REQUIREMENTS:  1. MATERIALS  TO  BE  FURNISHED.  All  material  required  for  the  construction  shall  be  furnished  by  the  Contractor and all materials shall be new, of first grade, and shall be products of reputable manufacturers  known to the trade.  Prior to ordering precast manhole or catch basin components, the Contractor shall submit for review  manhole and catch basin detail books in order that verification can be made that the materials to be  supplied  are  in  conformance  with  the  design  concept  of  the  Project  and  in  compliance  with  the  information given in the Contract Documents.  PRODUCTS:  1. STORM SEWER PIPE. Reinforced Concrete Pipe shall conform to ASTM Specification C76 with Bureau of  Reclamation R‐4 joint.  2. CORRUGATED METAL PIPE CULVERT shall have 2‐2/3 inch by 1/2 inch corrugations and shall conform to  the applicable requirements of AASHTO M36, as shown on the Mn/DOT Standard Plate No. 3040F.  Coupling bands shall be the same base metal and coating as the pipe. Bands shall have the same thickness  as the pipe. Bands shall be 10‐1/2 inch minimum width.  Corrugated metal aprons shall conform to the requirements shown on Mn/DOT Standard Plate No. 3123J.  3. MANHOLE AND CATCH BASIN STRUCTURES. The Contractor shall use precast sections whenever possible.  If the Contractor must construct the manholes and catch basins using segmental block, the following shall  apply:  Block work shall be laid up in good workmanlike manner to the dimensions shown. All block shall be  wetted thoroughly with water just before laying, and headers and vertical joints shall be broken from  course  to  course.  Each  horizontal  course  shall  be  completed  before  starting  the  next  course  above.  Horizontal joints shall be not more than 1/2 inch thick and vertical joints on inside face not more than 3/8  inch thick. All joints shall be completely filled with mortar. All joints on inside shall be plastered smooth  with mortar, thickness to be not less then 1/4 inch at any point.  All Work shall be covered when not being worked upon. Masonry shall be kept at a temperature above  freezing until mortar has attained sufficient strength and set so that it will not be damaged by freezing. In  freezing  weather,  all  materials  shall  be  heated  before  laying  and  shall  be  protected  as  necessary  to  prevent damage after laying. No Work shall be done in unsuitable weather, unless suitable protection is  provided.  The blocks shall be radial blocks and shall conform to the radius of the manhole as detailed. The blocks  shall have a vertical groove with one inch radius on both ends. The batter blocks for the tapered tops shall  be a minimum of five inches in thickness and the blocks used in the four‐foot diameter manhole section  shall be a minimum of six inches in thickness.  Lake Elmo Developer Master 3340‐2  Revision date: March 2017  The manhole depth to which the six inch thickness blocks may be used shall not exceed 12 feet. Below  this point, the block thickness shall be increased to 10 inch for manholes up to 20 feet in depth, and for  manholes deeper than 20 feet, the block thickness shall be not less than 12 inches. A flat slab top may be  required instead of a tapered top. Precast adjusting rings shall be used to form the upper eight inches of  the structure.  4. MANHOLE/CATCH  BASIN  STEPS.  Manholes  and  catch  basins  shall  be  furnished  with  aluminum  steps,  polypropylene plastic reinforced, or approved equal, and shall be in accordance with Mn/DOT Standard  Plate No. 4180. Steps shall be located over the downstream pipe.  5. MANHOLE CASTINGS. Manhole casting shall be Neenah Catalog No. R‐1642 Type “B” solid cover with  concealed pickholes, or equal. Casting covers shall have no positioning lugs.  6. CATCH BASIN CASTINGS. Catch basin casting and grate shall be as follows:  Surmountable Concrete Curb and Gutter ‐ Neenah Catalog No. R‐3501‐TB  B618 Concrete Curb and Gutter ‐ Neenah Catalog No. R‐3067‐V  Ditch or Yard Area Inlet ‐ Neenah Catalog No. R‐4342  EXECUTION:  1. ALIGNMENT AND GRADE. All pipe shall be laid and maintained to the required lines and grades, with  manholes, catch basins, and special structures at the required locations. No deviation from line or grade  shall be made without the written consent of the Engineer.  2. PIPELAYING.  The  alignment  of  pipe  between  manholes  shall  be  such  as  to  permit  the  entire  inside  circumference being seen from any manhole to the next adjacent manhole. Piping that does not conform  to line and grade shall be relaid at the Contractor’s expense.  Laser Beam Grade Control: When the Contractor uses laser beam control for grade and alignment, the  Contractor shall verify grades using provided grade stakes. Any discrepancies found between the laser  beam  elevation  and  grade  stake  elevation  shall  be  immediately  brought  to  the  Engineer’s  attention  before continuing pipe installation. If the Contractor fails to follow the steps, the Contractor shall be  responsible for any removal and reinstallation of pipe as necessary to conform to the line and grade  shown on the plans.   Pipe shall be laid against the grade of the sewer. The spigot end of the pipe shall be inserted full depth  into the bell, and when completed, each line of pipe shall have a uniform and smooth invert.  Joints for all sewers shall be made watertight. As soon as the joint is made, the bell depression shall be  filled with granular bedding material which shall be pressured under and around the joint, by hand, in  such a way as to protect it from sagging or being disturbed.  Joint ties shall be installed on the last three joints at all end section locations.  The interior of all pipe shall, as the work progresses, be cleaned of all dirt and superfluous materials. The  exposed end of the pipe shall be protected with suitable temporary covers. Pipe laid in place shall be  protected from injury and disturbance.  3. MANHOLE AND CATCH BASIN INSTALLATION. Manholes and catch basins shall be constructed as detailed  and set plumb with a maximum deviation of  0.1‐foot from vertical.  Lake Elmo Developer Master 3340‐3  Revision date: March 2017  Catch basins and manholes shall be constructed on a minimum 6 inch thickness of granular bedding  material. If additional stabilization is required, a minimum 6 inch thickness of 1 1/2” crushed rock or  washed rock shall be used as directed by the Engineer.  The adjusting rings and the castings shall be set in a bed of mortar, and the exterior of the adjusting rings  shall be given a 1/2‐inch mortar covering. The joints of the adjusting rings shall be completely filled with  mortar and the interior joints struck smooth. Infi‐Shield external watertight gasket shall be installed on all  manholes and catch basins.  All rows of steps shall be set vertical through the height of the manholes.  Precast manholes over seven feet deep shall have a 1’‐0” or 1’‐4” manhole section installed under the  cone section to allow for height adjustment.  4. MANHOLES AND CATCH BASINS. The Contractor shall be responsible for keeping all new and existing  manholes and catch basins clean and free of dirt at all times. Storm sewer structures within 10 feet of  watermain are to have water tight connections per Minnesota Department of Health requirements.  The  Contractor  shall  adjust  all  castings  located  within  the  street  section  including  existing  castings.  Adjustments shall be as follows:  Non‐Inlet Castings:  .04 feet below finished grade  Inlet Castings:  .10 feet below gutter line grade  Castings  located  in  the  bituminous  section  shall  be  coated  with  a  material  which  allows  removal  of  bituminous material applied to the casting lid. Castings shall have a wooden cut‐out or other approved  material placed over the structure during the paving operation. The cut‐out shall allow pavement to be  placed around the structure causing a uniform lip after rolling conforming to the information given above.  The top of the castings shall be adjusted to the finished elevation just prior to paving.  Upon  completion  of  compacting  bituminous  pavement,  all  manhole and  valve  box  covers  shall  be  removed and surfaces, lift holes, and casting lips cleaned of all bituminous materials.  Interim adjustment of castings to the surface will be required to allow for access during lengthy periods of  work suspension. Cuts in the bituminous pavement resulting from interim adjustments shall be restored  with a minimum compacted thickness of three inches of bituminous mixture. In conjunction with final  adjustments,  patches  from  interim  adjustments  shall  be  removed in  their  entirety  and  the  roadway  structure restored to the plan thicknesses.   Infi‐shield external seals shall be installed on the outside surface adjustment ring area covering all rings.  Installation shall be in accordance with manufacturer recommendations. Primer shall be applied to areas  where attaching non‐hardening butyl mastic to casting flanges and cone section. Inspection tab shall be  attached to manhole lid before backfilling.  5. RIP RAP. Rip Rap shall be hand placed and conform to MnDOT 3601, Class III. The Contractor shall hand  place Class III rip rap at the locations as shown on the Plans and as directed by the Engineer.  6. GEOTEXTILE FILTER. Contractor shall place MnDOT Type IV (Specification 3733) geotextile filter under all  rip rap and extend three feet under the culvert apron.  7. TRASHGUARDS. Trashguards shall be installed on all flared end sections.  END OF SECTION