HomeMy WebLinkAbout#08 - Water System Evaluation STAFF REPORT
DATE: June 5, 2018
CONSENT
ITEM #: 8
AGENDA ITEM: 2018 Water System Evaluation Update – Authorize AE2S Task Order
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Rob Weldon, Public Works Director
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve a Task Order for Advanced Engineering
and Environmental Services, Inc. (AE2S) to update the water system distribution model and perform an
updated water system evaluation?
PROPOSAL DETAILS/ANALYSIS: The City Engineer is recommending that the City retain
Professional Engineering Services to conduct a Water System Evaluation Update to incorporate water
system improvements, including developer installed improvements, into the City water distribution model
and evaluating the water system performance.
Significant water system improvements have been constructed and placed online by the City since the last
water model update. The model needs to be kept current so that the model may be utilized to evaluate future
performance and system needs based on planned growth and development. The study will specifically
evaluate the timing for a new water supply well and the timing for a new elevated storage tank in response
to the loss of Well No. 1, and the updated 2040 Comprehensive land use plan and staging plan. The
hydraulic studies will identify the preliminary design information for these water system components
including an updated trunk watermain size evaluation.
FISCAL IMPACT: $20,334 to be paid from the Water Core Fund.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the consent
agenda, Task Order No. 6 for AE2S to perform a 2018 Water System Evaluation Update in the not to
exceed amount $20,334. If removed from the consent agenda, the recommended motion for this action is
as follows:
“Move to approve Task Order No. 6 for AE2S to perform a 2018 Water System Evaluation Update in
the not to exceed amount $20,334.”
ATTACHMENTS:
1. Advanced Engineering and Environmental Services (AE2S) – Task Order No. 6.
TASK ORDER No. 6 – WATER DISTRIBUTION SYSTEM 2018 UPDATE
Page 1 of 3
TASK ORDER No. 6
CITY OF LAKE ELMO, MINNESOTA – ADVANCED ENGINEERING AND ENVIRONMENTAL SERVICES, INC.
PROFESSIONAL ENGINEERING SERVICES AGREEMENT
In accordance with ARTICLE 1 of the Master AGREEMENT between the City of Lake Elmo (“CITY”) and
Advanced Engineering and Environmental Services, Inc. (“ENGINEER”), dated __________________,
2012 (“AGREEMENT”), the ENGINEER agrees to provide Professional Engineering Support Services as
follows:
WATER DISTRIBUTION SYSTEM 2018 MODEL UPDATE
PROJECT OVERVIEW:
Update the existing water distribution system hydraulic model to incorporate recent developments
and City projects. Evaluate the impacts of removing Well #1. Develop a strategic plan for expansion of
the water supply and distribution system, as necessary to responsibly and cost-effectively
accommodate future growth in Lake Elmo.
This project will specifically evaluate the timing of new well capacity and the impact of new and
proposed developments on the Lake Elmo Water distribution system. It will establish development
parameters that can be used to determine when new capacity is required. The project will also evaluate
trunk pipe sizing, wells and storage needs to supply the planned service area and determine the timing
for the necessary improvements.
The future approach is flexible and will be developed in collaboration with Fo cus Engineering, and in
the best interest of the City of Lake Elmo.
SERVICES TO BE PROVIDED BY ENGINEER: AE2S shall provide the following Professional Engineering
Services:
Update Existing Water Model
1. Update the computer model (InfoWater) to accurately reflect recent changes to the water
distribution system.
2. Remove Well #1 from the system.
Evaluate Timing Needs for New Well
3. Model existing water system based on historic demand and current rate of development. The
goal is to understand the timing needs for a new well.
Evaluate Future Improvements
4. Model the system based on future land use plan as developed for the City’s comprehensive
plan. Verify trunk pipe sizing, wells and storage to supply the planned service area and
determine the timing of the facilities going on line.
TASK ORDER No. 6 – WATER DISTRIBUTION SYSTEM 2018 UPDATE
Page 2 of 3
Technical Memorandum
5. Prepare a Technical Memorandum documenting the analysis and recommendations outlined in
this Task Order No. 6.
Items not included in the proposed scope are as follows:
1. Analysis of existing water quality.
2. Analysis of capacity of existing or proposed wells.
3. Model calibration using pressure gages and hydrant flow testing.
CITIES RESPONSIBILITIES: The City (or its consultants) will provide the following:
Any changes/updates to the water distribution system that have been implemented in the past
two years (since the model was last updated);
Provide information related to pressure zone changes;
Provide construction plans, for any new projects constructed in the last two years.
Provide construction plans, including pipe invert elevations, shop drawings and pressure
settings for new pressure reducing valve installation;
Provide information on current number of RECs in newly developed areas;
Provide information on proposed rate of development in newly developed areas;
Prepare and present findings to city staff and council.
TIMES FOR RENDERING SERVICES: ENGINEER shall perform its services and provide deliverables in
accordance with the following schedule:
Work shall be completed by July 27, 2018.
Note that the proposed project schedule is dependent on timely receipt of information required from
the Owner.
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by ENGINEER under this TASK ORDER shall be the City Engineer. Project
correspondence must be addressed to:
Jack Griffin, P.E., City Engineer
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, MN 55042
651.300.4264
Email: Jack.griffin@focusengineeringinc.com
TASK ORDER No. 6 – WATER DISTRIBUTION SYSTEM 2018 UPDATE
Page 3 of 3
COMPENSATION: Compensation to ENGINEER shall be on an hourly rate basis using the hourly billing
rates provided in the ENGINEER’s Proposal for the work, in a not to exceed amount of.
AE2S proposes to provide the professional services for Water Distribution System 2018 Update
consistent with the Scope of Services outlined above on an estimated hourly (plus expenses) basis not
to exceed. An outline of the primary scope items is provided in the following table.
Phase 1 Professional
Fees (Total)
Update Existing Model $3,038
Evaluate Timing Needs for New Well $5,446
Evaluate Future Improvements
Evaluate Demands $748
Verify Pipe Sizing, Wells and Storage $6,732
Prepare Summary Report $4,370
Total Professional Services = $20,334
Payment for Services shall be in accordance with ARTICLE 3.2 of the Master AGREEMENT. Invoices
should be sent to the attention of the City Engineer.
ATTACHMENTS: The following documents are incorporated by reference: NA
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Task Order, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT. ENGIN EER is
authorized to begin performance of services upon receipt of a copy of this Task Order signed by CI TY.
The Effective Date of this Task Order is ___________________________, 2018.
ADVANCED ENGINEERING AND CITY OF LAKE ELMO, MINNESOTA
ENVIRONMENTAL SERVICES, INC.
By _________________________________ By _________________________________
Grant L. Meyer, P.E. City Administrator
Client Program Leader