HomeMy WebLinkAbout#07 - Boulder Ponds Security Reductions STAFF REPORT
DATE: July 17, 2018
CONSENT
ITEM #: 7
AGENDA ITEM: Private Development Projects – Approve Security Reductions for Boulder
Ponds 1st Addition and Boulder Ponds 5th Street Improvements
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator
Emily Becker, Planning Director
Chad Isakson, Assistance City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve security reductions for the Boulder Ponds
1st Addition and Boulder Ponds 5th Street Improvements?
PROPOSAL DETAILS/ANALYSIS: Staff has received and processed requests to reduce the
development security in accordance with the various development projects. These requests have been
reviewed and the following reductions are being recommended for approval:
Current Security Amount Proposed Security Amount
1. Boulder Ponds 1st Addition: $945,215 $ 60,719
2. Boulder Ponds 5th Street: $384,066 $213,173
Work within each of these developments have progressed in accordance with the respective development
agreement and to the extent necessary to support a reduction in the security as detailed in this report.
In addition, the City is holding $3,125 until 5 additional trees are planted following construction of the
home on each property, and $1,000 for some minor plantings needed along the 5th Street median.
FISCAL IMPACT: It is the City’s goal to retain at all times during the subdivision improvements a
security amount that is adequate to ensure completion of all elements of the improvements as protection to
the City tax payers against the potential of developer default. With this reduction, the remaining security
amount held by the City remains sufficient to complete the remaining improvements.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent
Agenda, the security reductions for the Boulder Ponds 1st Addition and Boulder Ponds 5th Street
Improvements as detailed in this report and supporting documentation. If removed from the consent agenda,
the recommended motion for the action is as follows:
“Move to approve security reductions for the Boulder Ponds 1st Addition and Boulder Ponds 5th Street
Improvements as detailed in the attached Security Reduction Worksheets.”
ATTACHMENTS:
1. Security Reduction Worksheet – Boulder Ponds 1st Addition.
2. Security Reduction Worksheet – Boulder Ponds 5th Street Improvements.
BOULDER PONDS 1ST ADDITION Time of Performance: October 31, 2016
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading $116,600 $116,600 100%$116,600
Grading $68,194 $85,243 100%$42,621 $42,621
Sanitary Sewer $405,451 $506,813 75%$380,110
Watermain $349,674 $437,092 75%$327,819
Streets $1,084,327 $1,355,409 75%$677,704 $338,852
Surface Water Facilities $721,027 $901,284 75%$450,642 $225,321
Erosion Control $48,406 $60,508 75%$45,381
Sidewalks/Trails Included in Streets Included in Streets
Street Lighting NA NA By Xcel Energy
Street Signs and Traffic Control Signs Included in Streets Included in Streets
Landscaping $204,302 $255,378 50%$127,689 $60,719 $3,125
Tree Preservation and Restoration NA NA
Wetland Mitigation and Buffers NA NA LOC Through VBWD
Monuments $4,700 $5,875 75%$4,406
Miscellaneous Facilities NA NA
Record Drawings $2,500 $3,125 75%$2,344
TOTALS $2,888,581 $3,727,326 RELEASED AMOUNTS:$1,995,497 $606,794 $179,819 $60,719
$881,371 CUMMULATIVE AMOUNTS:$1,995,497 $2,602,291 $2,782,111 $2,842,830
SECURITY AMOUNT REMAINING:$1,731,829 $1,125,035 $945,215 $884,496
DATE:12/15/2015 8/2/2016 12/20/2016 7/17/2018
REDUCTIONS
Holding for 5 trees
to be planted with Lots
BOULDER PONDS 5TH STREET NORTH Time of Performance: October 31, 2017
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading NA NA Included in Boulder Ponds 1st Addition
Sanitary Sewer $46,600 $58,250 $43,688
Watermain $64,000 $80,000 $60,000
Storm Sewer (w/pond structures) $97,300 $121,625 $91,219
Streets $287,700 $359,625 $269,719
Sidewalks/Trails $71,000 $88,750 $66,563
Surface Water Facilities NA NA
Street Lighting NA NA
Street Signs and Traffic Control Signs $11,600 $14,500 $10,875
Private Utilities (electricity, natural gas, telephone, and cable)NA
Landscaping $100,753 $125,941 $93,456 $1,000
Tree Preservation and Restoration NA NA
Wetland Mitigation and Buffers NA NA
Monuments NA NA
Erosion Control NA NA
Miscellaneous Facilities NA NA
Record Drawings NA NA
TOTALS $678,953 $848,691 RELEASED AMOUNTS:$103,688 $360,938 $170,893
$212,173 CUMMULATIVE AMOUNTS:$103,688 $464,625 $635,518
SECURITY AMOUNT REMAINING:$745,004 $384,066 $213,173
DATE:2/21/2017 9/5/2017 7/17/2018
REDUCTIONS
Holding for 5th Street
median plantings