HomeMy WebLinkAbout#04 - Central Greenway Trail Corridor STAFF REPORT
DATE: 1/8/18
REGULAR
FROM: Ben Prchal, City Planner
AGENDA ITEM: Central Greenway Regional Trail Update
REVIEWED BY: Rob Weldon, Public Works Director
Parks Commission (12.17.2018)
BACKGROUND:
The City and Washington County Staff have been working towards planning the best route for the trail
through Lake Elmo. During the design process, two primary groups were established, a community work
group consisting of residents and commission members and a technical work group consisting of staff
members. There were also multiple open houses for individuals who were not part of either group to
provide feedback. After taking input from both groups and the open houses Staff believes, at this time
that formal preparation of material for review by the Metropolitan Council should begin.
ISSUE BEFORE CITY COUNCIL:
Would the Council like to approve the letter, amend the letter, or not provide a letter at all?
PROPOSAL DETAILS/ANALYSIS:
Washington County would like to receive a letter of support from the City for the Central Greenway Trail.
Attached with this report are maps which outline the proposed route (interim and final). The proposed
route hits the objectives of the City by going past the school as well as downtown Lake Elmo. This trail
will provide residents the ability to travel from the south end of the City all the way to the north on a
dedicated road separated trail. There would also be the possibility of other trails to branch off and bring
users to different areas within the City. Those however, would be a City lead initiative. Washington
County has asked the City to provide a letter of support for the project. The more support that the trail
can receive the better it will look when it goes in front of the reviewing agencies. The Parks Commission
has also voted to support the trail as it has been presented.
FISCAL IMPACT:
The City is expected to cover 25% of the cost burden to construct the trail. There is the possibility for grants
to cover portions of the cost. Staff believes that the City Council should not provide funding unless grants
are applied for before the expenses are split. Staff believes this will provide the City with the best
opportunity to receive funding. The funding will be scheduled after the planning process and approval has
been given by Met Council. The following numbers are based off of a different trail alignment but
reasonably serve as a place holder.
The 2019 – 2023 CIP has cost expenditures broken out for two years, 2021 and 2022 with the total trail cost
coming to $1,592,961.
Expected City Cost for 2021 - $206,829
Expected City Cost for 2022 - $191,400
RECOMMENDATION:
“Motion to provide the letter of support as it has been presented”
ATTACHMENTS:
• Central Greenway Regional Trail Map(s)
• Letter of Support
Figure 19: Central Greenway Regional Trail Lake Elmo Segment Map.
Section III: Development Concept
22 Central Greenway Regional Trail Master Plan:Lake Elmo Segment \\ Draft December 10, 2018
LAKE ELMO
PARK RESERVE
SUNFISH
LAKE PARK
GiWX
GlWX
?ÇA@
!"b$
GnWX
GsWX ?öA@
GoWX
GqWX
GqWX
GoWX
GlWX
%&h(
GoWX
GoWX
GnWX
GeWX
Sf
GoWX
CITY OF LAKE ELMO
CITY OF
PINE SPRINGS
CITY OF OAK
PARK HEIGHTS
CITY OF BAYTOWN
WEST LAKELAND
TOWNSHIP
CITY OF AFTON
CITY OF WOODBURY
CITY OF OAKDALE
Horseshoe Lake
Jane Lake
Lake Elmo
Eagle
Point
Lake
Lake
Bielenberg DrSettlers Ridge PkwyTamarack Rd
RadioDrWoodburyDrWeirDr50th St N
InterlachenPkwyHadleyAveNHudson Ave
H u d s on Rd
Johns DrHelmoAveNHudson Blvd
4th St N Manni
ngAveNLakeElmoAveN30th St N
34th St N
N
15th St N
County Rd 7143rd St
N
50th St N
OlsonLak
e
T
r
N20th St NKeatsAveN
Commer ce DrIdealAveN 39th St N
ManningAveS47th St NDemontrevill
e
Tr N
40th St N
ManningTrNNeal Ave S
Stillwate r Blvd N StillwaterBlvdB2
R1
R2
R3
R4
R5
R6
B1
R3A
Existing Public Trails (6-10’ wide)
Existing Private Trails (6-10’ wide )
Existing County Soft Surface Trials (6’ wide)
Existing County/Regional Trails (8-10’ wide)
Gateway State Trail (10’ wide)
County Parks
City Parks
Trail Sub Segments
Regional Trail (on new trail)
Regional Trail (on existing trail)
Regional Trail Railroad Crossing Alternate
Interim Regional Trail (on existing local trail)
Interim Regional Trail (on future local trail)
0 0.25 0.5 miNORTH
61Central Greenway Regional Trail Master Plan:Lake Elmo Segment \\Draft December 10, 2018 DOWNTOWN LAKE ELMOLAKE ELMO PUBLIC LIBRARYLAKE ELMO PARK RESERVESUNFISH LAKE PARKGiWXGlWX?ÇA@!"b$GnWXGsWX?öA@GoWXGqWXGqWXGqWXGoWXGlWX%&h(GoWXGoWXGkWXGnWXG¡WXGeWXSf?¸A@CITY OF GRANTCITY OF LAKE ELMOCITY OF PINE SPRINGSCITY OF MAHTOMEDICITY OF STILLWATERCITY OF OAK PARK HEIGHTSBAYTOWN TOWNSHIPWEST LAKELAND TOWNSHIPCITY OF AFTONCITY OF WOODBURYCITY OF OAKDALEHorseshoe LakeJane LakeLake ElmoBearLakeLakeBielenberg DrSettlers Ridge PkwyTower DrTamarack RdRadioDrValleyCreek RdWoodbu r y D r
WeirDr75thStN50th St N62nd St NInterlachenPkwyHadleyAveNHudson AveWoodl a n e D rHudsonRdSaint Johns DrHelmoAveNHudsonBlvdStillwater Rd4th St NCtlyRdM a n n in g A v e N
LakeElmoAveNMahtom30th St N34th St NGreenwayAve7th St N15th St NCounty Rd 71BoutwellRdN
43rd St N50th St N80th St N
O l s o n L a keTrN 20th St NKeatsAveNCommerceDrWildwoodRdIdealAveN39thStNManningAveS47th St NDemontreville TrN40thStNJamaManningTrNNeal Ave SStillwaterBlvdNHiltonTrStillwater WayPotPotPoentenialiaTrrailailCrCrCossosssingi PAcrAcrAcossssossRaRaRailroadoadPotPententialialTrTrailailiitiPialTrtentiPottUnUlUnnerderepaspass dendUnil nUnddererRaiRaRlroraUndUndRRailRradadaddoaPotPotentenillheaed LLdLocaoctioon nttialTrraiaittialialTrTailnntialTrTodyaat at at tSchSchoomoCo Co CityityHaallloolool/La/Lakkmml/LakeeElmElmoat SchoPotPotPententntialialalTrTrailailaheaheaadddd TlotentialoPoilheadLocLocatiaonot at aHigHigh ShSchochoololt cah pototentententilialaReRRstPoPotReReRestsStopppPotPentialleReRest st t StoStoppppPoPoententtialiaiaReReRessStoStppPotententteest sSStalConConConecnecnt tt to PoroprooseosedddBriBrBrdgedgeOvver erMNMN3636Existing Public Trails (6-10’ wide)Existing Private Trails (6-10’ wide )Existing County Soft Surface Trials (6’ wide)Existing County/Regional Trails (8-10’ wide)Gateway State Trail (10’ wide)County ParksCity ParksPublic DestinationsSchoolRailroad CrossingRegional Trail (on new trail)Regional Trail (on existing trail)Regional Trail Railroad Crossing AlternateInterim Regional Trail (on existing local trail)Interim Regional Trail (on future local trail)Intersection TypeFour-Way StopSignalized0 0.25 0.5 miNORTHPotPentiaaialalGrradeadeadSlGalGGradel SeeSepapapateated d araaaatrade SagggCroCrssiisng ngngto to toHigHigHh hhg h ShSchohoololchhchhigh SiCentral Greenway Regional Trail Master Plan:Lake Elmo SegmentOctober 30, 2018PREFERRED REGIONAL TRAIL ALIGNMENT
Section II: Demand Forecast
12 Central Greenway Regional Trail Master Plan:Lake Elmo Segment \\ Draft December 10, 2018
Figure 10: Trail Primary Service Area Map
CITY OF LAKE ELMO
LAKE ELMO
PARK RESERVE
White Bear Lake
Lake
Elmo St. Croix RiverCITY OF GRANT CITY OF STILLWATER
CITY OF
MAHTOMEDI
CITY OF OAK
PARK HEIGHTS
BAYTOWN
TOWNSHIP
WEST LAKELAND
TOWNSHIP
3 MILES
CITY OF WOODBURY
CITY OF
AFTON
CITY OF
OAKDALE
BROWNS CREEK STATE TR A I L
GATEW AY STATE TRA ILGiWX
?ÇA@
!"b$
GnWX
GsWX
GsWX
?öA@
?öA@
?A@
GqWX
GqWX
GlWX
GlWX
%&h(GoWX
GoWX
GkWX
GnWX
GeWX
?¸A@
96
GoWX
Central Greenway Regional Trail
Lake Elmo Segment Service Area
Regional Parks
City Parks
Existing Regional Trail
Regional Trail Search Corridor
Central Greenway Regional Trail
Lake Elmo Segment Existing Trail
Lake Elmo Segment Proposed Trail
00.51 miNORTH
3880 Laverne Avenue North • Lake Elmo • Minnesota 55042
Phone: (651) 747-3900 • Fax: (651) 747-3901 • www.lakeelmo.org
January 8, 2019
Metropolitan Council Chair and Parks and Open Space Commission
390 North Robert Street
Saint Paul, MN 55101
RE: Central Greenway Regional Trail – Lake Elmo Segment
Chair Tchourumoff and Commission Members,
The Lake Elmo City Council is excited to provide a letter of support for the Lake Elmo segment of the
Washington County Central Greenway Regional Trail. The representatives of Lake Elmo strongly
believe the proposed trail will play an important part of the City’s and Washington County’s trail system.
The trail will fill an existing gap in the pedestrian and bicycle network both regionally and locally. The
City is especially pleased with the idea of providing a road separated tail system for users to travel from
the south end of the City to the north end without the worry of traveling on a roadway. The opportunity
also hits one of the objectives of the City, which is to provide connectivity throughout. Though,
connectivity without safety is not beneficial. An important aspect to this trail is safety, the City strives to
build trails that provide safe connectivity for recreational users and school aged children, this trail has the
ability to do.
Locally, this trail alignment will strengthen multimodal transportation for our community and allow users
to safely access Lake Elmo Park Reserve, local businesses and schools. Regionally the City agrees that
the Central Greenway Regional Trail will be a benefit by creating connectivity to other neighboring
Cities. Connectivity has been a perused initiative for quite some time and the City will finally be able to
provide a strong greenway to connect existing trails and build new trails into. Ultimately, the full build-
out of this trail will provide a needed link in the regional trail system. Because of this and other listed
reasons, the City is pleased to provide support for the Central Greenway Trail initiative.
Thank you for the opportunity to send our support. We look forward to working with all agency partners
involved with the Central Greenway Regional Trail.
Sincerely,
Mike Pearson, City of Lake Elmo Mayor