HomeMy WebLinkAbout#08 - Pay Req. 2 for Test Well 5 STAFF REPORT DATE: October 10, 2019 CONSENT AGENDA ITEM: Test Well No. 5 – Pay Request No. 2 (Final) SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 2 (Final) for Test Well #5? BACKGROUND: Traut Companies was awarded a construction contract on July 2, 2019 to complete Test Well No. 5. Construction of the well has been completed pending test results for test pumping and water quality. Restoration of the project area is also complete. PROPOSAL DETAILS/ANALYSIS: Traut Companies has submitted Partial Pay Request No. 2 (Final) in the amount of $3,488.90. The request has been reviewed and payment is recommended in the amount requested. FISCAL IMPACT: The final total project cost is $58,378, 11% above the contract amount of $52,588. Final payment is based on increased project costs due to actual quantities of work performed. Payment has exceeded the contract amount but remains within the authorized scope and budget. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 2 (Final) for Test Well #5. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Pay Request No. 2 (Final) to Traut Companies in the amount of $3,488.90 for the Test Well #5 project”. ATTACHMENTS: 1. Partial Pay Estimate No. 2 (Final). PROJECT PAY FORM PARTIAL PAY ESTIMATE NO. PERIOD OF ESTIMATE TO PROJECT OWNER: CONTRACTOR: 1. Original Contract Amount 2. Net Change Order Sum 3. Revised Contract (1+2) 4. *Work Completed 5. *Stored Materials 6. Subtotal (4+5) 7. Retainage* 8. Previous Payments 9. Amount Due (6-7-8) *Detailed Breakdown Attached START DATE:ON SCHEDULE SUBSTANTIAL COMPLETION:X FINAL COMPLETION: ENGINEER'S CERTIFICATION: FOCUS Engineering, inc. DATE CONTRACTOR'S CERTIFICATION: CONTRACTOR DATE APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA DATE DATE No.Approval Date Amount $52,168.00 Additions Deductions $420.00 2 10/1/2019 $600.00 $58,378.00 1 8/7/2019 $180.00 $52,588.00 $58,378.00 $0.00 $54,889.10 $0.000.0% CONTRACT TIME TOTALS $600.00 $180.00 $3,488.90 NET CHANGE $420.00 CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY 2 (FINAL) 9/10/20199/1/2019FROM TEST WELL NO. 5 PROJECT NO. 2019.114 CITY OF LAKE ELMO 3800 LAVERNE AVENUE NORTH LAKE ELMO, MN 55042 ATTN: JACK GRIFFIN, CITY ENGINEER TRAUT COMPANIES 141 28TH AVE SOUTH WAITE PARK, MN 56387 ATTN: DAVID TRAUT 8/1/2019 9/10/2019 REVISED DAYS REMAINING 40 0 0 ORIGINAL DAYS BY BY YES NO The undersigned Contractor certifies that to the best of their knowledge, information and belief the work covered by this payment estimate has been completed in accordance with the contract documents, that all amounts have been paid by the contractor for work for which previous payment estimates was issued and payments received from the owner, and that current payment shown herein is now due. The undersigned certifies that the work has been reviewed and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. ENGINEER BY 10/15/2019 FOCUS Engineering, inc.PROJECT PAYMENT FORM PARTIAL PAY ESTIMATE NO. 2 (FINAL) TEST WELL NO. 5 CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2019.114 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 LS 1 $6,850.00 $6,850.00 0.00 $0.00 1.00 $6,850.00 2 LF 85 $80.00 $6,800.00 0.00 $0.00 140.00 $11,200.00 3 LF 125 $40.00 $5,000.00 0.00 $0.00 55.00 $2,200.00 4 LF 207 $35.00 $7,245.00 0.00 $0.00 204.00 $7,140.00 5 LF 80 $40.00 $3,200.00 0.00 $0.00 95.00 $3,800.00 6 LS 1 $615.00 $615.00 0.00 $0.00 1.00 $615.00 7 CY 5 $595.00 $2,975.00 0.00 $0.00 12.00 $7,140.00 8 LS 1 $1,180.00 $1,180.00 0.00 $0.00 1.00 $1,180.00 9 HRS 10 $295.00 $2,950.00 0.00 $0.00 14.00 $4,130.00 10 LS 1 $950.00 $950.00 0.00 $0.00 1.00 $950.00 11 LS 1 $1,500.00 $1,500.00 0.00 $0.00 1.00 $1,500.00 12 LS 1 $1,400.00 $1,400.00 0.00 $0.00 1.00 $1,400.00 13 LS 1 $1,400.00 $1,400.00 0.00 $0.00 0.00 $0.00 SUBTOTAL - BASE BID - 6-INCH TEST WELL $42,065.00 $0.00 $48,105.00 1 LS 1 $1,250.00 $1,250.00 0.00 $0.00 1.00 $1,250.00 2 LS 1 $1,250.00 $1,250.00 0.00 $0.00 1.00 $1,250.00 3 HR. 24 $145.00 $3,480.00 0.00 $0.00 24.00 $3,480.00 4 EA 1 $275.00 $275.00 0.00 $0.00 1.00 $275.00 5 LF 300 $2.00 $600.00 0.00 $0.00 700.00 $1,400.00 6 DAY 4 $350.00 $1,400.00 0.00 $0.00 1.00 $350.00 7 LS 1 $1,848.00 $1,848.00 0.00 $0.00 1.00 $1,848.00 $10,103.00 $0.00 $9,853.00 TOTALS - BASE CONTRACT $52,168.00 $0.00 $57,958.00 CO1-1 LS 1 $460.00 $460.00 0.00 $0.00 1.00 $460.00 CO1-2 LS 1 -$640.00 -$640.00 0.00 $0.00 1.00 -$640.00 -$180.00 $0.00 -$180.00 CO2-1 SF 2,000 $0.30 $600.00 2,000.00 $600.00 2,000.00 $600.00 $600.00 $600.00 $600.00 TOTALS - REVISED CONTRACT $52,588.00 $600.00 $58,378.00 SUBTOTAL - CHANGE ORDER NO. 1 CHANGE ORDER NO. 2 SEEDING SUBTOTAL - CHANGE ORDER NO. 2 ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE BASE BID - 6-INCH TEST WELL MOBILIZATION AND DEMOBILIZATION CONTAINERIZED DUMPSTER FOR CUTTINGS GAMMA LOGGING HAUL OFF DRILL CUTTINGS DRILL AND DRIVE 10" CASING DRILL 10" OPEN HOLE THROUGH LIMESTONE FURNISH AND INSTALL 6" STEEL CASING 10" OPEN HOLE THROUGH JORDAN UNIT 10 BY 6 FOOT GROUT PACKER GROUT FURNISH, INSTALL, AND REMOVE WELL DEVELOPMENT EQUIPMENT TEST PUMPING DATA LOGGER FURNISH, INSTALL, AND REMOVE WATER METER AND DISCHARGE HOSE WELL DEVELOPMENT CHANGE ORDER NO. 1 VIDEO TAPING BASE BID - 24 HOUR TEST PUMPING AND WATER QUALITY TESTING MOBILIZATION AND DEMOBILIZATION FURNISH, INSTALL, AND REMOVE TEST PUMP 300-400 GPM PUMP TREE CLEARING PER DIEM WATER QUALITY PFAS 537 / VOCs 524.2 SUBTOTAL - BASE BID - TESTING OMIT PFAS 537 TESTING