Loading...
HomeMy WebLinkAbout#09 - 2019 Mill & Overlay STAFF REPORT DATE: October 15, 2019 CONSENT AGENDA ITEM: 2019 Mill and Overlay Project – Pay Request No. 3 SUBMITTED BY: Jack Griffin, Engineer REVIEWED BY: Kristina Handt, City Administrator Chad Isakson, Assistant City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 3 for the 2019 Mill and Overlay Project? BACKGROUND: T.A. Schifsky & Sons, Inc. was awarded a construction contract on April 16, 2019 to complete the 2019 Mill and Overlay Project. The original scope of work has been fully completed, however the additional work requested by the City through Change Order No. 1 (Keats Avenue street patch repairs) still remains to be completed. PROPOSAL DETAILS/ANALYSIS: T.A. Schifsky & Sons, Inc. has submitted Partial Pay Request No. 3 in the amount of $35,871.67. The submittal has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of the total work completed. The amount retained is $31,966.22. FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project. Payment remains within the authorized scope and budget. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 3 for the 2019 Mill and Overlay Project. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Pay Request No. 3 to T.A. Schifsky & Sons, Inc. in the amount of $35,871.67 for the 2019 Mill and Overlay Project”. ATTACHMENTS: 1. Partial Pay Estimate No. 3 PROJECT PAY FORM PARTIAL PAY ESTIMATE NO. PERIOD OF ESTIMATE TO PROJECT OWNER:CONTRACTOR: 1. Original Contract Amount 2. Net Change Order Sum 3. Revised Contract (1+2) 4. *Work Completed 5. *Stored Materials 6. Subtotal (4+5) 7. Retainage* 8. Previous Payments 9. Amount Due (6-7-8) *Detailed Breakdown Attached START DATE:ON SCHEDULE SUBSTANTIAL COMPLETION: FINAL COMPLETION:X ENGINEER'S CERTIFICATION: FOCUS Engineering, inc. DATE CONTRACTOR'S CERTIFICATION:CONTRACTOR DATE APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA DATE DATE BY BY YES NO The undersigned Contractor certifies that to the best of their knowledge, information and belief the work covered by this payment estimate has been completed in accordance with the contract documents, that all amounts have been paid by the contractor for work for which previous payment estimates was issued and payments received from the owner, and that current payment shown herein is now due. The undersigned certifies that the work has been reviewed and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. ENGINEER BY 6/17/2019 9/13/2019 REVISED DAYS REMAINING 88 0 -17 8/16/2019 ORIGINAL DAYS CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY 3 9/30/20198/1/2019FROM 2019 MILL AND OVERLAY PROJECT PROJECT NO. 2018.132 CITY OF LAKE ELMO 3880 LAVERNE AVENUE NORTH, SUITE 100 LAKE ELMO, MN 55042 ATTN: JACK GRIFFIN, CITY ENGINEER T.A. Schifsky & Sons, Inc. 2370 E Hwy 36 North St. Paul, MN 55109 ATTN: Rob Stangler CONTRACT TIME TOTALS $8,140.00 $0.00 $35,871.67 NET CHANGE $8,140.00 $31,966.225.0% $571,486.55 $0.00 $639,324.44 CO-1 8/7/2019 $8,140.00 $673,433.05 $639,324.44 No.Approval Date Amount $665,293.05 Additions Deductions $8,140.00 FOCUS Engineering, inc.PROJECT PAYMENT FORM 10/08/19 PARTIAL PAY ESTIMATE NO. 3 2019 MILL AND OVERLAY PROJECT CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2018.132 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 LS 1.00 $24,000.00 $24,000.00 0.00 $0.00 1.00 $24,000.00 2 LS 1.00 $9,000.00 $9,000.00 0.05 $450.00 1.00 $9,000.00 3 EA 19.00 $100.00 $1,900.00 8.00 $800.00 16.00 $1,600.00 4 EA 21.00 $100.00 $2,100.00 2.50 $250.00 5.00 $500.00 5 LF 84.00 $4.00 $336.00 0.00 $0.00 816.00 $3,264.00 6 SY 27,070.00 $1.25 $33,837.50 0.00 $0.00 28,670.00 $35,837.50 7 SY 10,000.00 $1.35 $13,500.00 0.00 $0.00 10,000.00 $13,500.00 8 SY 440.00 $7.00 $3,080.00 0.00 $0.00 44.63 $312.41 9 SY 2,090.00 $9.00 $18,810.00 0.00 $0.00 3,389.00 $30,501.00 10 LF 55.00 $12.00 $660.00 0.00 $0.00 55.00 $660.00 11 EA 1.00 $3,350.00 $3,350.00 0.00 $0.00 1.00 $3,350.00 12 LF 1,575.00 $6.50 $10,237.50 0.00 $0.00 1,669.00 $10,848.50 13 TN 10.00 $39.00 $390.00 0.00 $0.00 36.31 $1,416.09 14 TN 1,060.00 $8.50 $9,010.00 0.00 $0.00 865.11 $7,353.44 15 TN 330.00 $75.00 $24,750.00 0.00 $0.00 345.35 $25,901.25 16 TN 4,450.00 $64.89 $288,760.50 0.00 $0.00 3,960.28 $256,982.57 17 GAL 2,780.00 $0.01 $27.80 0.00 $0.00 2,620.00 $26.20 18 SY 440.00 $22.50 $9,900.00 0.00 $0.00 101.39 $2,281.28 19 LS 1.00 $5,000.00 $5,000.00 0.00 $0.00 1.14 $5,700.00 20 EA 24.00 $775.00 $18,600.00 0.00 $0.00 26.00 $20,150.00 21 EA 13.00 $325.00 $4,225.00 0.00 $0.00 11.00 $3,575.00 22 LF 2,310.00 $28.00 $64,680.00 0.00 $0.00 2,292.00 $64,176.00 23 LF 120.00 $40.00 $4,800.00 0.00 $0.00 126.00 $5,040.00 24 LF 1,400.00 $21.00 $29,400.00 0.00 $0.00 1,400.00 $29,400.00 25 EA 6.00 $660.00 $3,960.00 0.00 $0.00 4.00 $2,640.00 26 EA 10.00 $414.75 $4,147.50 0.00 $0.00 8.00 $3,318.00 27 EA 2.00 $3,034.50 $6,069.00 0.00 $0.00 2.00 $6,069.00 28 EA 2.00 $3,533.00 $7,066.00 0.00 $0.00 2.00 $7,066.00 29 LF 10.00 $530.00 $5,300.00 0.00 $0.00 10.00 $5,300.00 30 LF 55.00 $55.00 $3,025.00 0.00 $0.00 40.00 $2,200.00 31 EA 2.00 $1,848.00 $3,696.00 0.00 $0.00 2.00 $3,696.00 32 CY 26.00 $94.50 $2,457.00 0.00 $0.00 29.17 $2,756.57 33 LF 50.00 $20.00 $1,000.00 50.00 $1,000.00 50.00 $1,000.00 34 CY 390.00 $25.00 $9,750.00 62.56 $1,564.00 121.44 $3,036.00 35 SY 2,860.00 $3.00 $8,580.00 3,192.00 $9,576.00 3,192.00 $9,576.00 36 SY 1,040.00 $11.00 $11,440.00 277.00 $3,047.00 277.00 $3,047.00 37 LF 5,025.00 $0.35 $1,758.75 29,432.00 $10,301.20 29,432.00 $10,301.20 38 LF 10,050.00 $0.35 $3,517.50 18,947.00 $6,631.45 18,947.00 $6,631.45 $652,121.05 $33,619.65 $622,012.44 1 EA 1.00 $4,452.00 $4,452.00 0.00 $0.00 1.00 $4,452.00 2 LF 20.00 $61.00 $1,220.00 0.00 $0.00 20.00 $1,220.00 3 EA 1.00 $7,500.00 $7,500.00 0.00 $0.00 1.00 $7,500.00 $13,172.00 $0.00 $13,172.00 CO1-1 LS 1.00 $2,640.00 $2,640.00 0.00 $0.00 1.00 $2,640.00 CO1-2 LS 1.00 $3,500.00 $3,500.00 0.00 $0.00 0.00 $0.00 CO1-3 EA 4.00 $500.00 $2,000.00 0.00 $0.00 3.00 $1,500.00 $8,140.00 $0.00 $4,140.00 TOTALS $673,433.05 $33,619.65 $639,324.44 DRAINTILE CLEANOUT 2'X3' CATCH BASIN WITH CASTING 48" STORM SEWER MANHOLE CATCH BASIN 18" RCP STORM SEWER PIPE 15" RCP STORM SEWER PIPE ADJUST VALVE BOX CONCRETE CURB AND GUTTER (ALL TYPES EXCEPT VALLEY GUTTER) CONCRETE VALLEY GUTTER 4" PVC SCH 40 PERF EDGE DRAIN W/BACKFILL AND WRAP CONNECT TO EXISTING STORM STRUCTURE TRAFFIC CONTROL INLET PROTECTION BIOROLL DITCH CHECK SAWCUT PAVEMENT (ALL TYPES) MILL 1.5" EXIST. BITUMINOUS PAVEMENT MILL 2" EXIST. BITUMINOUS PAVEMENT REMOVE AND DISPOSE OF EXISTING BITUMINOUS PAVEMENT (DRIVEWAY) REMOVE AND DISPOSE OF EXISTING BITUMINOUS PAVEMENT SCHEDULE B - WATERMAIN 6" WET TAP 6" WATERMAIN DIP - CL 52 (POLY ENCASED) SUBTOTAL - SCHEDULE A DITCH GRADING SUBTOTAL - SCHEDULE B BASE BID MOBILIZATION HYDRANT REMOVE AND DISPOSE OF EXISTING STORM SEWER REMOVE AND REINSTALL STORM FES WITH TIES REMOVE AND DISPOSE OF CONCRETE CURB (ALL TYPES) CLASS 6 AGGREGATE BASE REMOVE AND REPLACE CLASS 6 AGGREGATE BASE TYPE SP 12.5 BITUMINOUS NON WEARING COURSE MIXTURE (2,B) [SPNWB230B] TYPE SP 9.5 BITUMINOUS WEARING COURSE MIXTURE (2,B) [SPWEA230B] BITUMINOUS MATERIAL FOR TACK COAT 2360 BITUMINOUS WEAR COURSE, DRIVEWAYS SHOULDERING WITH STOCKPILED MILLINGS ADJUST MANHOLE CASTING SEEDING, FERTILIZER, AND WOOD FIBER BLANKET SODDING ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE 15" FLARED END SECTION CLASS 3 RIP RAP WITH FABRIC STRIPING - 4" YELLOW STRIPING (STYLE VARIES) STRIPING - 4" WHITE STRIPING IMPORT AND PLACE TOPSOIL BORROW (LV) CHANGE ORDER NO. 1 WATER SERVICE TO PEBBLE PARK KEATS AVE PAVEMENT PATCHING ADJUST CATCH BASIN CASTING WITH NEW RINGS AND INFI-SHIELD TOTAL - CHANGE ORDER NO. 1