HomeMy WebLinkAbout#17 - Feasibility Report for 31st St-Stillwater Blvd Watermain STAFF REPORT
DATE: November 19, 2019
CONSENT
AGENDA ITEM: Authorize Preparation of a Feasibility Report for the 31st Street and
Stillwater Blvd Watermain Improvements
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator
Chad Isakson, Assistant City Engineer
Marty Powers, Public Works Director
ISSUE BEFORE COUNCIL: Should the City Council authorize the preparation of a feasibility report
for the 31st Street and Stillwater Blvd Watermain Improvements?
BACKGROUND: The City of Lake Elmo is extending watermain to 6 homes located just east of 31st
Street North and south of Stillwater Boulevard in Lake Elmo as shown on the attached Location Map. The
properties reside in an area affected by PFAS contamination and well advisories have been issued. The City
approved a grant agreement with the MPCA at the October 1, 2019 council meeting regarding these
improvements and approved final design services at the October 15, 2019 council meeting in order the jump
start the topographic survey work.
The project extends the public watermain south across Stillwater Boulevard (CSAH 14) from the north side,
approximately 800 feet east of the intersection at 31st Street North. On the south side of CSAH 14,
watermain will be extended approximately 780 feet further south along a shared private driveway.
Individual water service stubs will be installed for each of the 6 residential properties. The project will
include grant funding and administrative processes for ensuring each property completes the private service
connection from the right-of-way to each home, including water meter installation, sealing of the private
well, and all permitting and connection fees.
PROPOSAL DETAILS/ANALYSIS: Staff is recommending that a Feasibility Report be prepared for this
project in accordance with the statutory process for public improvements that are specially assessed. The
feasibility report will advise on the scope of recommended improvements; provide estimated project costs;
identify easement and right-of-way, permits and other requirements of other local agencies needed to
implement the improvements; recommend whether the improvements should be best made as proposed or
in connection with some other improvement; and advise if the improvements are necessary, cost effective,
and feasible. The report will also provide a proposed preliminary assessment roll for each of the benefitting
properties based upon the City’s Special Assessment Policy for Local Improvements. Consistent with the
City Assessment Policy and past practices, the watermain improvements will be 100% assessed to the
benefitting properties. Assessments will be waived once the property connects to City water and
successfully abandons their private well.
A project schedule for the 31st Street and Stillwater Blvd Watermain Improvements is attached and outlines
the implementation timeframe necessary to ready the improvements for construction in 2020. The proposed
schedule provides necessary time to address public involvement, acquire project related easements, acquire
field survey before heavy snowfall, and to receive contractor bids early in 2020 to promote a competitive
bid environment.
FISCAL IMPACT: $4,800. The engineering fees will be funded through the MPCA Grant Agreement
approved at the October 1, 2019 City council meeting.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the consent
agenda, a Resolution Ordering Preparation of a Feasibility Report for the 31st Street and Stillwater Blvd
Watermain Improvements. If removed from the consent agenda, the recommended motion for this action
is as follows:
“Move to approve Resolution No. 2019-088, Ordering preparation of a Feasibility Report for the 31st
Street and Stillwater Blvd Watermain Improvements to be completed by FOCUS Engineering, Inc. in
the not to exceed amount of $4,800.”
ATTACHMENTS:
1. Resolution Ordering Preparation of a Feasibility Report.
2. 31st Street and Stillwater Blvd Watermain Improvements – Location Map.
3. 31st Street and Stillwater Blvd Watermain Improvements – Project Schedule.
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2019-088
A RESOLUTION ORDERING THE PREPARATION OF A FEASIBILITY REPORT
FOR THE 31ST STREET AND STILLWATER BOULEVARD WATERMAIN
IMPROVEMENTS
WHEREAS, the city has been awarded grant funds through the 2018 3M Settlement Expedited
Project Grant Program to extend clean drinking water to 6 homes located along a private driveway near 31st
Street North and Stillwater Boulevard and to reimburse property owners for the costs associated with
connecting to city water and sealing their well.; and
WHEREAS, the city executed an Agreement with the Minnesota Pollution Control Agency dated
October 2, 2019 stating the conditions and terms of the grant funds including the requirement for each
property to connect to city water and abandon all private wells, unless identified as a monitoring well by
MPCA; and
WHEREAS, staff recommends that the city assess properties that do not hook up to city water in the
allotted time in order to recoup those project costs that may not be covered by the grant due to non-
compliance; and
WHEREAS, it is proposed to assess the benefiting properties for all or a portion of the cost of
the improvement, pursuant to the city’s Special Assessment Policy and Minnesota Statues, Chapter 429.
NOW, THEREFORE, BE IT RESOLVED,
That the proposed improvement, called 31st Street and Stillwater Blvd Watermain Improvements, be
referred to the City Engineer and FOCUS Engineering, to complete a feasibility report in accordance with
Minnesota Statues, Chapter 429 for the proposed improvements, and to report to the council with all
convenient speed advising the council in a preliminary way as to whether the proposed improvement is
necessary, cost-effective, and feasible; whether it should be best made as proposed or in connection with
some other improvement; the estimated cost of the improvement as recommended; and a description of
the methodology used to calculate individual assessments for affected parcels.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE SEVENTEETH DAY OF
NOVEMBER, 2019.
CITY OF LAKE ELMO
By: __________________________
(Seal) Mike Pearson
ATTEST: Mayor
________________________________
Julie Johnson
City Clerk
LOCATION MAP
FIGURE NO. 1
CITY OF
LAKE ELMO
PRIVATE DRIVE
LEGEND
31ST ST N
CSAH 14
JO
N
Q
U
I
L
A
V
E
N
UPRR RAILROAD ROW
PROPERTIES SERVED
JONQUIL TRL N
PROJECT NO. 2019.124
31ST STREET
WATERMAIN
IMPROVEMENTS
PROJECT SCHEDULE
CITY OF LAKE ELMO
31ST STREET AND STILLWATER BLD WATERMAIN IMPROVEMENTS
PROJECT NO. 2019.124
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
OCTOBER 1, 2019 Council Approves MPCA Grant Agreement for Stonegate Watermain Project.
OCTOBER 15, 2019 Council Authorizes Topographic Survey and Final Design Services.
NOVEMBER 19, 2019 Council orders preparation of Feasibility Report.
JANUARY 21, 2020 Presentation of Feasibility Report. Council accepts Report and calls for
Improvement Hearing.
FEBRUARY 18, 2019 Public Improvement Hearing. Council Orders the Improvement (4/5th Vote)
and preparation of Plans and Specifications.
MARCH 3, 2020 Council approves Plans and Specifications and orders Advertisement for Bids.
APRIL 2, 2020 Project Bid Date: Receive contractor bids.
APRIL 21, 2020 Council accepts Bids and awards Contract.
MAY 19, 2020 Conduct Pre‐Construction Meeting and issue Notice to Proceed.
SEPTEMEBER 25, 2020 Substantial Completion.
NOVEMBER 13, 2020 Final Completion.
SEPTEMBER 7, 2021 Declares Costs to be Assessed and Calls for Hearing on Assessment.
OCTOBER 5, 2021 Final Assessment Hearing. Council adopts the Final Assessment Roll.