HomeMy WebLinkAbout#16 - CSAH 19 & Hudson Blvd Change Order 3 STAFF REPORT DATE: December 17, 2019 CONSENT AGENDA ITEM: CSAH 19 and Hudson Boulevard Intersection Improvements – Change Order No. 3 SUBMITTED BY: Chad Isakson, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 3 for the CSAH 19 and Hudson Boulevard Intersection Improvements? BACKGROUND: Max Steininger, Inc. was awarded a construction contract on June 4, 2019 to complete the CSAH 19 and Hudson Boulevard Intersection Improvements. The project construction is substantially completed and pending final close-out. PROPOSAL DETAILS/ANALYSIS: Max Steininger, Inc. has submitted a change order to address additional work completed on the CSAH 19 and Hudson Boulevard Intersection Improvements as requested by the City and Washington County as described below. 1. Repair Sanitary Sewer Manhole – Sections of the existing sanitary sewer manhole required replacement to repair and adjust it to match the final grade along the roadway. 2. Additional Mobilization for Aggregate Shouldering – The city requested additional shouldering to be completed from Station 22+00 to 26+00. This work was not included in the original plans and required equipment to be remobilized to the site to complete the work. 3. Furnish New Chain Link Fence – A section of chain link fence around the MnDOT pond was removed for purposes of installing the storm sewer. The contract was to salvage and replace the existing fence. This was not possible because the existing fence was in poor condition requiring new fence to be furnished by the contractor. 4. Additional Mobilization for Crosswalk Striping – Washington County directed the crosswalk striping to be delayed until signals were operational. This required the striping contractor to remobilize to the site at a later date. This cost will be deducted from the steel supplier for not meeting their delivery deadline. 5. Bituminous Incentives – Bituminous incentives for exceeding compaction requirements were achieved on base course pavement. This payment is in accordance with MnDOT incentive charts. The total cost of the above items increases the contract by $4,680.49. FISCAL IMPACT: This change order will increase the contract in the amount of $4,680.49 bringing the revised construction contract to $1,802,075.51. With this change order, the project remains within the authorized project budget and contingencies. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 3 for the CSAH 19 and Hudson Boulevard Intersection Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 3 for the CSAH 19 and Hudson Boulevard Intersection Improvement Project, thereby increasing the contract amount by $4,680.49”. ATTACHMENTS: 1. Change Order No. 3.