HomeMy WebLinkAbout#11 - Geotechnical Investigation Proposal STAFF REPORT
DATE: December 3, 2019
CONSENT
AGENDA ITEM: Approve Geotechnical Investigation Proposal for 2020 Construction
Projects.
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve a contract to complete geotechnical
investigation work for the scheduled 2020 construction projects?
PROPOSAL DETAILS/ANALYSIS: Staff received proposals from two geotechnical firms (AET and
Braun Intertec) to complete an analysis, prepare a report of findings, and provide construction
recommendations based on soil conditions found in construction projects planned for 2020. These projects
consist of:
1. Heritage Farms Street and Utility Improvements
2. Stonegate Addition Street and Utility Improvements
3. 31st Street and Stillwater Boulevard Watermain Extension
4. Pumphouse No. 5
5. Well No. 5 Connecting Watermain Improvements
Both companies provided a scope of services with an understanding of the work. AET’s proposal includes
a fee of $29,700 with the fieldwork to be completed in a period of 2-3 weeks after authorization to complete
the work. Braun Intertec’s proposal includes a fee of $28,931 with the fieldwork to be completed in a period
of 5-7 weeks after authorization to complete the work. The City Engineer is recommending a contract be
awarded to AET due to the accelerated schedule of completion of work proposed in comparison to Braun.
FISCAL IMPACT: $29,700. This fee is a part of the overall project costs presented to the Council for
each of the 5 infrastructure projects listed above. The appropriate costs will be assigned to each project.
RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda,
approve a geotechnical services contract for the 2020 construction projects to AET in the not to exceed
amount of $29,700. If removed from the consent agenda, the recommended motion for the action is as
follows:
“Move to approve a geotechnical services contract for the 2020 construction projects to AET in the not
to exceed amount of $29,700”.
ATTACHMENTS:
1. AET Proposal for Lake Elmo 2020 Geotechnical Services.
550 Cleveland Avenue North | Saint Paul, MN 55114
Phone (651) 659-9001 | (800) 972-6364 | Fax (651) 659-1379 | www.amengtest.com | AA/EEO
This document shall not be reproduced, except in full, without written approval from American Engineering Testing, Inc.
November 18, 2019
Chad Isakson, PE
City of Lake Elmo
3880 Laverne Avenue North
Lake Elmo, MN 55042
Re: Proposal for Geotechnical Services
AET Proposal No. 01-20691
Lake Elmo 2020 Infrastructure Improvements
Dear Mr. Isakson:
American Engineering Testing, Inc. (AET) is pleased to submit this proposal to conduct
the scope of services listed below:
Scope of Services:
Field Exploration
Heritage Farms Street and Utility Improvement
•Drill and sample twelve (12) standard penetration test (SPT) borings to depths ranging
from 10 to 35 feet.
Stonegate Addition Street and Utility Improvement
•Drill and sample seventeen (17) SPT borings to a depth of 10 feet.
31st Street & Stillwater Boulevard Watermain Extension
•Drill and sample four (4) SPT borings to a depth of 10 feet.
Production Well No. 5 Pumphouse
•Drill and sample three (3) SPT borings to depths of 10 and 20 feet.
Well No. 5 Connecting Watermain Improvement
•Drill and sample four (4) SPT borings to a depth of 10 feet.
For all the projects listed above, our field services also include:
•Stake the soil borings in the field using provided diagrams or GPS coordinates.
•Clear underground public utilities through the Gopher State One Call system.
•Backfill borings per Minnesota Department of Health requirements.
•Measure and document the boring locations and surface elevations by using a GPS.
Laboratory
•Visually-manually classify the soils per the Unified Soil Classification System.
CONSULTANTS
·ENVIRONMENTAL
·GEOTECHNICAL
·MATERIALS
·FORENSICS
City of Lake Elmo
Lake Elmo 2020 Infrastructure Improvements
November 18, 2019
Page 2 of 3
American Engineering Testing, Inc.
• Conduct water content tests on cohesive soils retrieved.
Report (to include)
• Logs of the test borings, including soil classifications, N-values, and laboratory results.
• Review of encountered soil and groundwater conditions.
• Foundation recommendations and settlement estimation for the proposed pumphouse.
• General recommendations for directional drilling, utility bedding and backfill, if
applicable.
• Recommendations for pavement subgrade preparation, estimated R-value, pavement
design, and reclamation, if applicable.
AET’s scope of work is intended for geotechnical purposes only, and not to explore for the
presence or extent of environmental contamination at the site. However, we will note
obvious contamination encountered.
Fee:
Our services will be performed on a time-and-material basis per the attached fee schedule.
For the scope described, we will establish $29,700 as a not-to-exceed fee. The budget
breakdowns of each project are attached. We combined the mobilization to projects in
asterisk (*) into one trip.
1. Heritage Farms St. and Utility Improvements $ 11,500
2. Stonegate Addition St. and Utility Improvements $ 8,500
3. 31st St. and Stillwater Blvd Watermain Extension* $ 4,300
4. Production Well No. 5 Pumphouse* $ 2,900
5. Well No. 5 Connecting Watermain Improvements* $ 2,500
Total $ 29,700
Schedule:
Based on our current backlog, we anticipate the fieldwork can begin on about 2 to 3 weeks
after receiving authorization to proceed. Verbal results can be provided shortly after
fieldwork completion. Individual final report should then follow field completion by about
2 to 2½ weeks.
Terms/Conditions:
Our services will be conducted per our executed Contract Agreement between the City of
Lake Elmo and American Engineering Testing, Inc. for Professional Services, dated July
10, 2010.
Acceptance:
Please indicate your acceptance of this proposal by endorsing the enclosed copy and
returning it to us. The original proposal is intended for your records.
2019 GEOTECHNICAL FEE SCHEDULE
01DPM021.15 (1/19) AMERICAN ENGINEERING TESTING, INC.
I. Personnel Hourly Rates
A. Administrative Assistant 70.00/hr.
B. Engr. or Env. Technician I 77.00/hr.
C. Engr. or Env. Technician II 90.00/hr.
D. Drill Technician/Geo Lab Technician 102.00/hr.
E. Engr. or Env. Technician III 110.00/hr.
F. Engineering Assistant 119.00/hr.
G. Engineer I/Geologist I 132.00/hr.
H. Engineer II/Geologist II/Sr. Engr. Assistant 152.00/hr.
I. Senior Engineer/Geologist 169.00/hr.
J. Principal Engineer/Geologist 205.00/hr.
K. Principal of Firm 225.00/hr.
II. Vehicle Mileage
A. Personal Automobile/Truck 0.75/mile
B. Auxiliary Truck Vehicle 1.00/mile
C. Truck with Coring, FWD, or GPR Equipment 1.10/mile
D. Truck with Warning Sign/Crash Trailer 1.20/mile
E. 1-ton Truck with Drill Rig 1.20/mile
F. 1½ to 2½-ton Truck with Drill Rig 1.35/mile
G. CPT Truck Rig (20-ton push capacity) 1.60/mile
H. Tractor/Lowboy Trailer 1.80/mile
III. Equipment Rental
A. Drill Rig Rental
1. Rotary Drill on 1-ton Truck 78.00/hr.
2. Rotary Drill on 1½ to 2½-ton Truck 88.00/hr.
3. Rotary Drill on All-Terrain Vehicle 120.00/hr.
4. Portable, Non-rotary Rig 88.00/hr.
B. Auxiliary/Specialty Vehicle Rental
1. Auxiliary Truck Vehicle 19.50/hr.
2. Truck with Warning Sign/Crash Trailer 43.00/hr.
3. Truck with Coring Equipment 59.00/hr.
C. Cone (CPT) Rig/Equipment Rental
1. CPT Rig (Truck or ATV) 155.00/hr.
2. Electronic Cone w/Computer 48.00/hr.
3. Soil Sampler 7.00/hr.
4. Water Sampler 22.00/hr.
D. Miscellaneous Equipment Rental
1. Field Vane Shear 335.00/day
2. Field Electrical Resistivity 260.00/day
3. Field Seismic Shear Wave (ReMi) 435.00/day
4. Inclinometer Reading Equipment 340.00/day
5. Electronic Transducer Reading 180.00/day
6. Bore Hole Permeability
a. Open End Casing Method 140.00/day
b. HQ Wireline Packer 350.00/day
7. Borehole Pressuremeter 75.00/hr.
8. Iowa Borehole Shear Tester 335.00/day
9. Double Ring Infiltrometer 275.00/day
10. GPS Mapping System 16.00/hr.
11. Pile Driving Analyzer (PDA) 750.00/day
12. Calibrated SPT Rod 230.00/day
13. Pile Integrity Test (PIT) 360.00/day
E. Geotechnical Software Rental
1. Geo Studio Finite Element 75.00/hr.
2. CAPWAP 40.00/hr.
3. AutoCAD or Microstation 35.00/hr.
4. Wave Equation (WEAP) 25.00/hr.
5. LPILE or GROUP 25.00/hr.
6. Slope Stability (ReSSA) 25.00/hr.
7. Stabilized Earth Slopes & Walls 25.00/hr.
8. Settlement (FoSSA) 25.00/hr.
F. Bit Wear- Rock Coring
1. Diamond Bit - Sedimentary Rock
a) B, NQ 12.00/foot
b) HQ 14.00/foot
2. Diamond Bit - Metamorphic & Igneous
a) B, NQ 20.00/foot
b) HQ 23.00/foot
IV. Laboratory Tests of Soil
A. Water Content hourly
B. Dry Density (includes water content) 60.00/test
C. Atterberg Limits (ASTM:D4318)
1. Plasticity Index 118.00/test
2. Liquid Limit or Plastic Limit Separately 103.00/test
D. Sieve Analysis (includes -#200) 110.00/test
E. Hydrometer Analysis (sieve included) 208.00/test
F. Thermal Resistivity w/Proctor (ASTM:D5334)
1. As Received and Oven Dried (2 pts) 1000.00/test
2. Dry Out Curve (4 pts) 1245.00/test
G. Electrical Resistivity (ASTM:G57-Soil Box) 102.00/test
H. Corrosion/Concrete Attack Series* price upon request
I. Consolidation (up to 32 tsf)
1. With P-e curves only 480.00/test
2. With P-e curves, time curves 610.00/test
J. Unconfined Compression (incl. wc/density) 103.00/test
K. Hand Penetrometer 10.00/test
L. Organic Content of Soil 70.00/test
M. Topsoil Borrow Test (Mn/DOT 3877) 298.00/test
N. R-value (Hveem Stabilometer) 400.00/test
O. California Bearing Ratio
1. Granular 640.00/test
2. Cohesive 730.00/test
P. Proctor Tests (Methods A or B)
1. Standard 140.00/test
2. Modified 150.00/test
*includes pH, chloride ion, soluble sulfates, sulfides,
redox potential (resistivity not included).
V. Expenses
A. Direct Project Expenses: includes out-of- Cost + 15%
town per diem; plowing & towing; special
materials & supplies; special travel,
transportation & freight; subcontracted
services, and miscellaneous costs
B. Equipment Replacement (when abandonment Cost
is more feasible than recovery)
C. Equipment Recovery (when required by Cost + 15%
regulatory agencies or project specifications)
The rates presented are portal-to-portal with vehicle mileage, expenses
and equipment rentals being additional.
Overtime for personnel charged at above cost plus 25% for over 8 hours
per day or Saturday; and at above cost plus 50% for Sundays or Holidays.
Hazardous work charged at an additional 25%. Night time shift work will
include a premium charge of $30.00 per person per shift.
Hourly Breakdown:
Rate Total
Principal Engineer 1 hours $205.00 $205.00
Engineer II 6.5 hours $152.00 $988.00
Engineering Assistant 2 hours $119.00 $238.00
Senior Engr Tech III 0 hours $110.00 $0.00
Drill/Lab Technician 47 hours $102.00 $4,794.00
Word Processing Specialist 2.5 hours $70.00 $175.00
Total:$6,400.00
Equipment Rental/Mileage:
Rate Total
Personal Auto/Truck Mileage 0 miles $0.75 $0.00
Auxiliary Drill Truck Mileage 120 miles $1.00 $120.00
1.5-2.5 Ton Truck Drill Rig Mileage 90 miles $1.35 $121.50
CPT Truck Rig Mileage 0 miles $1.60 $0.00
Tractor/Lowboy Trailer Mileage 0 miles $1.80 $0.00
Auxiliary Drill Truck Rental 45 hours $23.50 $1,057.50
1.5-2.5 Ton Truck Drill Rig Rental 42 hours $88.00 $3,696.00
All-Terrain Drill Rig Rental 0 hours $120.00 $0.00
CPT Truck Rig Rental 0 hours $143.00 $0.00
Piezocone w/computer Rental 0 hours $41.00 $0.00
GPS Equipment 3.5 hours $15.25 $53.38
Total:$5,048.38
Lab Test Rates
Rate Total
Sieve Analysis, without hydrometer 0 tests $110.00 $0.00
Sieve Analysis, with hydrometer 0 tests $208.00 $0.00
Atterberg Limits 0 tests $118.00 $0.00
Unconfined Compression, w/wc, dens 0 tests $103.00 $0.00
Organic Content 0 tests $70.00 $0.00
Total:$0.00
Expenses
Rate Total
MDH Temp Well Notification 1 x cost $75.00 $75.00
Warning Sign Rental Costs 0 x cost $0.00 $0.00
Total:$75.00
Overall Total:$11,523.38
Unit
Unit
Unit
Unit
Table A - Budget Details: Heritage Farms St. & Utility Improvements
Page 1 of 5
Hourly Breakdown:
Rate Total
Principal Engineer 1 hours $205.00 $205.00
Engineer II 8.5 hours $152.00 $1,292.00
Engineering Assistant 1 hours $119.00 $119.00
Senior Engr Tech III 0 hours $110.00 $0.00
Drill/Lab Technician 33 hours $102.00 $3,366.00
Word Processing Specialist 2 hours $70.00 $140.00
Total:$5,122.00
Equipment Rental/Mileage:
Rate Total
Personal Auto/Truck Mileage 0 miles $0.75 $0.00
Auxiliary Drill Truck Mileage 90 miles $1.00 $90.00
1.5-2.5 Ton Truck Drill Rig Mileage 60 miles $1.35 $81.00
CPT Truck Rig Mileage 0 miles $1.60 $0.00
Tractor/Lowboy Trailer Mileage 0 miles $1.80 $0.00
Auxiliary Drill Truck Rental 31 hours $23.50 $728.50
1.5-2.5 Ton Truck Drill Rig Rental 28 hours $88.00 $2,464.00
All-Terrain Drill Rig Rental 0 hours $120.00 $0.00
CPT Truck Rig Rental 0 hours $143.00 $0.00
Piezocone w/computer Rental 0 hours $41.00 $0.00
GPS Equipment 3 hours $15.25 $45.75
Total:$3,409.25
Lab Test Rates
Rate Total
Sieve Analysis, without hydrometer 0 tests $110.00 $0.00
Sieve Analysis, with hydrometer 0 tests $208.00 $0.00
Atterberg Limits 0 tests $118.00 $0.00
Unconfined Compression, w/wc, dens 0 tests $103.00 $0.00
Organic Content 0 tests $70.00 $0.00
Total:$0.00
Expenses
Rate Total
MDH Temp Well Notification 0 x cost $75.00 $0.00
Warning Sign Rental Costs 0 x cost $0.00 $0.00
Total:$0.00
Overall Total:$8,531.25
Unit
Unit
Unit
Unit
Table B - Budget Details: Stonegate Addition St. & Utility Improvements
Page 2 of 5
Hourly Breakdown:
Rate Total
Principal Engineer 0.5 hours $205.00 $102.50
Engineer II 5.5 hours $152.00 $836.00
Engineering Assistant 1 hours $119.00 $119.00
Senior Engr Tech III 0 hours $110.00 $0.00
Drill/Lab Technician 21 hours $102.00 $2,142.00
Word Processing Specialist 1 hours $70.00 $70.00
Total:$3,269.50
Equipment Rental/Mileage:
Rate Total
Personal Auto/Truck Mileage 0 miles $0.75 $0.00
Auxiliary Drill Truck Mileage 120 miles $1.00 $120.00
1.5-2.5 Ton Truck Drill Rig Mileage 60 miles $1.35 $81.00
CPT Truck Rig Mileage 0 miles $1.60 $0.00
Tractor/Lowboy Trailer Mileage 0 miles $1.80 $0.00
Auxiliary Drill Truck Rental 11 hours $23.50 $258.50
1.5-2.5 Ton Truck Drill Rig Rental 6 hours $88.00 $528.00
All-Terrain Drill Rig Rental 0 hours $120.00 $0.00
CPT Truck Rig Rental 0 hours $143.00 $0.00
Piezocone w/computer Rental 0 hours $41.00 $0.00
GPS Equipment 3 hours $15.25 $45.75
Total:$1,033.25
Lab Test Rates
Rate Total
Sieve Analysis, without hydrometer 0 tests $110.00 $0.00
Sieve Analysis, with hydrometer 0 tests $208.00 $0.00
Atterberg Limits 0 tests $118.00 $0.00
Unconfined Compression, w/wc, dens 0 tests $103.00 $0.00
Organic Content 0 tests $70.00 $0.00
Total:$0.00
Expenses
Rate Total
MDH Temp Well Notification 0 x cost $75.00 $0.00
Warning Sign Rental Costs 0 x cost $0.00 $0.00
Total:$0.00
Overall Total:$4,302.75
Unit
Unit
Unit
Unit
Table C - Budget Details: 31st St. & Stillwater Blvd Watermain Ext.
Page 3 of 5
Hourly Breakdown:
Rate Total
Principal Engineer 0.5 hours $205.00 $102.50
Engineer II 7.5 hours $152.00 $1,140.00
Engineering Assistant 1 hours $119.00 $119.00
Senior Engr Tech III 0 hours $110.00 $0.00
Drill/Lab Technician 9 hours $102.00 $918.00
Word Processing Specialist 1.5 hours $70.00 $105.00
Total:$2,384.50
Equipment Rental/Mileage:
Rate Total
Personal Auto/Truck Mileage 0 miles $0.75 $0.00
Auxiliary Drill Truck Mileage 0 miles $1.00 $0.00
1.5-2.5 Ton Truck Drill Rig Mileage 0 miles $1.35 $0.00
CPT Truck Rig Mileage 0 miles $1.60 $0.00
Tractor/Lowboy Trailer Mileage 0 miles $1.80 $0.00
Auxiliary Drill Truck Rental 4 hours $23.50 $94.00
1.5-2.5 Ton Truck Drill Rig Rental 4 hours $88.00 $352.00
All-Terrain Drill Rig Rental 0 hours $120.00 $0.00
CPT Truck Rig Rental 0 hours $143.00 $0.00
Piezocone w/computer Rental 0 hours $41.00 $0.00
GPS Equipment 0 hours $15.25 $0.00
Total:$446.00
Lab Test Rates
Rate Total
Sieve Analysis, without hydrometer 0 tests $110.00 $0.00
Sieve Analysis, with hydrometer 0 tests $208.00 $0.00
Atterberg Limits 0 tests $118.00 $0.00
Unconfined Compression, w/wc, dens 0 tests $103.00 $0.00
Organic Content 0 tests $70.00 $0.00
Total:$0.00
Expenses
Rate Total
MDH Temp Well Notification 1 x cost $75.00 $75.00
Warning Sign Rental Costs 0 x cost $0.00 $0.00
Total:$75.00
Overall Total:$2,905.50
Table D - Budget Details: Production Well No. 5 Pumphouse
Unit
Unit
Unit
Unit
Page 4 of 5
Hourly Breakdown:
Rate Total
Principal Engineer 0.5 hours $205.00 $102.50
Engineer II 5 hours $152.00 $760.00
Engineering Assistant 1 hours $119.00 $119.00
Senior Engr Tech III 0 hours $110.00 $0.00
Drill/Lab Technician 9 hours $102.00 $918.00
Word Processing Specialist 1.5 hours $70.00 $105.00
Total:$2,004.50
Equipment Rental/Mileage:
Rate Total
Personal Auto/Truck Mileage 0 miles $0.75 $0.00
Auxiliary Drill Truck Mileage 0 miles $1.00 $0.00
1.5-2.5 Ton Truck Drill Rig Mileage 0 miles $1.35 $0.00
CPT Truck Rig Mileage 0 miles $1.60 $0.00
Tractor/Lowboy Trailer Mileage 0 miles $1.80 $0.00
Auxiliary Drill Truck Rental 4 hours $23.50 $94.00
1.5-2.5 Ton Truck Drill Rig Rental 4 hours $88.00 $352.00
All-Terrain Drill Rig Rental 0 hours $120.00 $0.00
CPT Truck Rig Rental 0 hours $143.00 $0.00
Piezocone w/computer Rental 0 hours $41.00 $0.00
GPS Equipment 0 hours $15.25 $0.00
Total:$446.00
Lab Test Rates
Rate Total
Sieve Analysis, without hydrometer 0 tests $110.00 $0.00
Sieve Analysis, with hydrometer 0 tests $208.00 $0.00
Atterberg Limits 0 tests $118.00 $0.00
Unconfined Compression, w/wc, dens 0 tests $103.00 $0.00
Organic Content 0 tests $70.00 $0.00
Total:$0.00
Expenses
Rate Total
MDH Temp Well Notification 1 x cost $75.00 $75.00
Warning Sign Rental Costs 0 x cost $0.00 $0.00
Total:$75.00
Overall Total:$2,525.50
Table E - Budget Details: Well No. 5 Connecting Watermain Improvements
Unit
Unit
Unit
Unit