HomeMy WebLinkAbout#05- Lake Elmo Inn CUP Extension1
STAFF REPORT
DATE: 4/02/2019
CONSENT
TO: City Council
FROM: Ken Roberts, Planning Director
AGENDA ITEM: Time Extension - Lake Elmo Inn Parking Lot Conditional Use Permit
REVIEWED BY: Sarah Sonsalla, City Attorney
INTRODUCTION:
The City has received a request from Lake Elmo Inn, Inc. for a time extension for its conditional use
permit (CUP). The City Council approved a CUP for a parking facility as a principal use for the property
located at 3504 Lake Elmo Avenue North on February 20, 2018. (Please see Lake Elmo Inn’s attached
letter).
ISSUE BEFORE THE CITY COUNCIL:
Should the City Council grant a time extension for the CUP for the start of the construction of a new parking
lot for the Lake Elmo Inn?
BACKGROUND:
Existing Vacant Lot
Land Use:
Existing Zoning: VMX – Village Mixed Use
Surrounding Single family homes to the North (VMX – Village Mixed Use) and West (RS –
Use/Zoning: Rural Single Family); Commercial (VMX – Village Mixed Use) to the South and
West.
Comprehensive VMX – Village Mixed Use
Plan:
History: The site has long been a vacant lot and is currently being used for parking for the
Lake Elmo Inn restaurant. There is no parking lot currently at the site, however.
Deadline Application Complete – 2-1-2019
for Action: Extension Letter Sent – 3-26-2019
60 Day Deadline – 4-1-2019
Applicable §154.500 VMX – Village Center District
Regulations: § 154.106 – Conditional Use Permits
§ 154.210 – Off-street Parking
2
The City Council approved the CUP for a parking facility as a principal use on the property located at 3504
Lake Elmo Avenue North on February 20, 2018. Section 154.106 (K) of the City Code states “If substantial
construction has not taken place within 12 months of the date on which the conditional use permit was
granted, the permit is void except that, on application, the Council after receiving recommendation from
the Planning Commission, may extend the permit for such additional period as it deems appropriate.” In
this case, the Applicant has not yet started construction of the approved parking lot and it has requested
City Council approval of a time extension for the CUP.
The Planning Commission reviewed this request for a time extension on March 11, 2019. The Planning
Commission recommended approval of the request, subject to the conditions listed in the staff report.
2018 PROPOSAL DETAILS/ANALYSIS:
Purpose for Parking Facility. Lake Elmo Inn has expressed the need for more parking for its restaurant.
The applicant stated Washington County Old Village of Lake Elmo: Street and Utility Improvement Project
(Phase 2) had brought about some on-street parking challenges. The Applicant has also stated that the Lake
Elmo Inn has been using the subject property located at 3504 Lake Elmo Avenue North, which is not paved
for a parking lot, for a number of years now for parking. This is not allowed per City ordinance, however,
as the City’s off-street parking requirements mandate that in all residential, commercial and mixed use
districts, all areas intended to be utilized for parking space for five or more vehicles and associated
driveways shall be paved with a durable surface including, but not limited to, hot asphalt, bituminous, or
concrete. In addition to parking on the subject property, the Inn has also used parking within the right-of-
way for valet parking.
Current Available Parking for the Lake Elmo Inn. The City’s off-street parking requirements mandate
that a standard restaurant provide at least one space per 3 customer seats or each 100 square feet of interior
space. The Lake Elmo Inn is currently served with approximately 9 parking spaces on the parcel on which
the restaurant is located. Additionally, the Inn appears to utilize a parcel to the north for some parking,
which appears to provide approximately 12 spaces. The Inn also works with a property owner to the east
who provides shared parking. Parking standards for a standard restaurant require one space per 100 square
feet or one space per three customers. The Inn’s site plan indicates 2609 square feet, and so the parking that
would be required if the site plan for the restaurant were being reviewed today would be 26 spaces.
3
2 handicap
2 regular
5 in back
Lake Elmo Inn
Approximately 12 spaces
Parcel to the north of Lake
Elmo Inn
4
Conditional Use Permit Required for Parking Facility in VMX District. The property is located within
the VMX zoning district, and a conditional use permit for a parking facility in the VMX District is required.
Parking Lot Design.
• Access. The applicant is proposing access off of 34th Street North via a driveway.
• Number. The applicant is proposing a total of 54 spaces for the parking lot.
• Proposed Paving in the Right-of-Way. These 54 spaces, however, include proposed pavement in
the right-of-way. This is not allowed. All improvements must be contained within the site. This
will result in at least 11 spaces from the proposed plan needing to be removed.
• Size. The drawing that the applicant has provided is not scalable, and therefore Staff does not know
if the proposed size of the stalls is adequate. The stalls will need to be at least 9 feet in width, 8’6”
in depth, and aisles will need to be at least 22 feet wide in order to allow two-way access.
• Accessibility Parking. At least one accessible parking space will be required if the site has 1 to 25
parking spaces, and 26 to 50 parking spaces will require an additional accessible parking space. At
least one of the accessible parking spaces must be van-accessible.
• Required Setback from Residential Properties. The City’s requirements mandate that off-street
parking containing more than four parking spaces shall be located a minimum of twenty (20) feet
from the boundary of any adjacent lot zoned or used for residential purposes. The property to the
north is used for residential purposes, and the property to the west is zoned for residential purposes,
and therefore the parking lot must be setback 20 feet from these properties.
• Marking of Parking Spaces. The proposed site plan shows that parking spaces will be marked.
Marking of spaces with painted lines at least four inches in width is a requirement for parking lots
with five or more spaces.
• Curbing. The City’s off-street parking facilities require that open off-street parking areas designed
to have head-in parking along the property line shall provide a bumper curb not less than five (5)
feet from the side property line or a barrier of normal bumper height not less than three (3) feet
from the side property line.
• Landscaping. The applicant has not submitted a landscaping plan for the parking lot. The parking
lot application will need to include a landscape plan that includes the following:
o Interior Parking Lot Landscaping. At least 5% of the interior area of parking lots with
more than 30 spaces is to be devoted to landscaping planning areas in islands or corner
beds. Because the proposed number of spaces is over 30, this will be a requirement.
Additionally, at least one tree per ten spaces or fraction thereof must be provided.
o Perimeter Parking Lot Landscaping. A landscaped frontage strip at least five feet wide
needs to be provided between parking areas and public streets, sidewalks or paths and
include screening consisting of either a masonry wall, fence, berm, or hedge or
combination that forms a screen 3.5-4 feet in height. Additionally, screening 4-6 feet in
height along the north and west sides of the parcel (sides abutting residential properties)
shall be provided along with at least one deciduous or coniferous tree every forty feet (this
Shared Parking
5
will require at least 4 along the northern property line and at least two along the western
property line).
Engineering Review. The Applicant has not submitted construction plans for the parking lot. The
Applicant will be required to submit a parking lot permit application approved by the City Engineer.
Valley Branch Watershed District. Because the proposed increase of impervious surface on the site will
be more than 6,000 square feet, the Applicant will be required to obtain a Valley Branch Watershed District
permit.
2018 Planning Commission Review. The Planning Commission held a public hearing and considered the
request for a parking facility for the property located at 3504 Lake Elmo Avenue North on February 12,
2018. One comment from the public was received before the meeting expressing desire that the property be
used for a public parking facility rather than solely for the restaurant and that it be paved. One neighbor had
concern about lighting. Another resident expressed excitement about the parking lot, reiterating the need
for additional parking for the restaurant.
In 2018, the Planning Commission discussed the following in regards to the proposed parking facility:
• Lighting. There was discussion about parking lot lighting timers to prevent light pollution on
adjacent residential properties during hours that the restaurant is closed.
• Landscaping. As mentioned in this report, the Planning Commission had concern that the
screening requirements along the public street would inhibit visibility and pose safety risks. They
recommended amending the condition by removing the requirement that such landscaping be
installed.
The parking lot must adhere to all screening and landscaping requirements as outlined
in the Staff Report to the Planning Commission dated 2/12/2018 except for the
requirement that landscape screening be required along Lake Elmo Avenue and 34th
Street North.
• Crosswalk at Intersection of 34th Street North and Lake Elmo Avenue. The Commission
also made comment on the removal of the crosswalk across Lake Elmo Avenue at the
intersection of 34th Street North and Lake Elmo Avenue. The Commission sees a need for
that crosswalk to be replaced, as they have seen some safety issues with its removal. This has
no bearing on the subject request, but the Planning Commission would like this
communicated to Council and to the County.
2018 Findings. Resolution 2018-018 approving the conditional use permit has the following findings:
1. The proposed use will not be detrimental to or endanger the public health, safety, comfort,
convenience or general welfare of the neighborhood or the city. The proposed use will pave
an area that has already been used as parking for a significant period of time, bringing
the property in to compliance with City Code.
2. The use or development conforms to the City of Lake Elmo Comprehensive Plan. The area
is guided for VMX – Village Mixed Use in the Land Use Guide of the Comprehensive
Plan. Parking facility is a conditional use in this district.
3. The use or development is compatible with the existing neighborhood. A parking facility
will alleviate parking needs for the Lake Elmo Inn.
4. The proposed use meets all specific development standards for such use listed in Article 7 of
this Chapter. There are no specific development standards for a parking facility in
Article 7.
5. If the proposed use is in a flood plain management or shoreland area, the proposed use meets
all the specific standards for such use listed in Chapter 150, §150.250 through 150.257
6
(Shoreland Regulations) and Chapter 152 (Flood Plain Management). The property is
located outside the 0.2% annual chance floodplain and is not within the shoreland area.
6. The proposed use will be designed, constructed, operated and maintained so as to be
compatible in appearance with the existing or intended character of the general vicinity and
will not change the essential character of that area. The property is already used for
parking. Paving a parking lot will not drastically change the existing or intended
character of the general vicinity or alter the essential character.
7. The proposed use will not be hazardous or create a nuisance as defined under this Chapter to
existing or future neighboring structures. The proposed parking lot will potentially slightly
increase the number of cars that are able to park on the property than had been
parking there previously when the parking area was not paved, but paving the parking
lot will bring the property in to compliance with City standards.
8. The proposed use will be served adequately by essential public facilities and services,
including streets, police and fire protection, drainage structures, refuse disposal, water and
sewer systems and schools or will be served adequately by such facilities and services
provided by the persons or agencies responsible for the establishment of the proposed use.
The proposed use will be adequately served by the aforementioned, provided a parking
lot application is submitted and approved, meeting City standards.
9. The proposed use will not create excessive additional requirements at public cost for public
facilities and services and will not be detrimental to the economic welfare of the community.
The proposed use will not create additional requirements or cost.
10. The proposed use will not involve uses, activities, processes, materials, equipment and
conditions of operation that will be detrimental to any persons, property or the general
welfare because of excessive production of traffic, noise, smoke, fumes, glare or odors. The
use will not involve anything that would be detrimental.
11. Vehicular approaches to the property, where present, will not create traffic congestion or
interfere with traffic on surrounding public thoroughfares. The use will create little more
traffic congestion than already exists at the site.
12. The proposed use will not result in the destruction, loss or damage of a natural or scenic
feature of major importance. N/A
2018 Conditions of Approval. Resolution 2018-018 approving the conditional use permit has the
following conditions:
1. The Applicant shall submit and have approved a parking lot permit meeting all zoning,
engineering, and other applicable requirements.
2. The parking lot must adhere to all screening and landscaping requirements as outlined in the Staff
Report to the Planning Commission dated 2/12/2018 except for the requirement that landscape
screening be required along Lake Elmo Avenue and 34th Street North.
3. The applicant must obtain a permit from the Valley Branch Watershed District prior to the
issuance of a permit for construction, provide a copy of the permit to the City, and adhere to all
conditions of approval.
4. Lighting will need to comply with Section 150.035: Lighting, Glare Control, and Exterior
Lighting Standards of the City Code.
5. The parking lot shall not extend beyond property lines.
6. The applicant shall not barricade public right-of-way for the use of valet parking or any other
purposes without issuance of a right-of-way obstruction permit by the City.
2019 Time Extension Request. As I noted above, the Applicant has not yet started construction of the
approved parking lot and is asking the City for a time extension to start construction of the approved parking
facility. Staff does not have any major concerns with the time extension request. It is in the best interest
7
of the City and the nearby property owners, however, to not have the CUP approval go on indefinitely with
no action or progress toward implementation. As neighbors, City Code standards and businesses in the
area change, the standards and expectations for an approved CUP may change as well.
Based on the Applicant’s request and the construction season, staff and the Planning Commission are
recommending that the City Council extend the time limit in the conditional use permit for substantial
construction of the parking lot until October 1, 2019. If the Applicant does not start construction of the
parking lot by then, it will need to request another time extension and make a case to the City as to why the
City should further extend the time period. If no substantial construction on the parking lot has occurred
by October 1, 2019, the City Council could by resolution make the determination that the CUP is void and
no longer valid.
Findings. Staff and the Planning Commission recommend that the Council make the following findings:
1. That the procedures for obtaining a time extension for a Conditional Use Permit are found in
the Lake Elmo Zoning Ordinance, Section 154.106.
2. That all submission requirements of said Section 154.106 have been met by the Applicant.
Conditions of Approval. Staff and the Planning Commission recommend the following conditions of
approval:
1. The Applicant shall submit and have approved a parking lot permit meeting all zoning,
engineering, and other applicable requirements.
2. The parking lot must adhere to all screening and landscaping requirements as outlined in the Staff
Report to the Planning Commission dated 2/12/2018 except for the requirement that landscape
screening be required along Lake Elmo Avenue and 34th Street North.
3. The Applicant must obtain a permit from the Valley Branch Watershed District prior to the
issuance of a permit for construction, provide a copy of the permit to the City, and adhere to all
conditions of approval.
4. Lighting will need to comply with Section 150.035: Lighting, Glare Control, and Exterior
Lighting Standards of the City Code.
5. The parking lot shall not extend beyond property lines.
6. The Applicant shall not barricade public right-of-way for the use of valet parking or any other
purposes without issuance of a right-of-way obstruction permit by the City.
7. The Applicant must start substantial construction of the approved parking facility no later than
October 1, 2019 unless the City Council grants another time extension for the conditional use
permit. If the applicant has not started substantial construction of the parking facility by October
1, 2019, and a time extension is not applied for, the CUP will be declared void by the City
Council.
8. All other terms and conditions of Resolution No. 2018-018 shall remain in effect and unchanged.
FISCAL IMPACT:
Staff does not foresee any fiscal impact.
OPTIONS:
The City Council may:
• Adopt Resolution 2019-023 approving the requested Conditional Use Permit time extension with
recommended conditions.
8
• Amend the recommended conditions of approval and adopt Resolution 2019-023 approving the
requested Conditional Use Permit time extension with conditions as amended.
• Direct Staff to prepare a Resolution denying the time extension request for the Conditional Use
Permit.
RECOMMENDATION:
Staff and the Planning Commission are recommending approval of the request from the Lake Elmo Inn for
a time extension to start construction of the city-approved parking facility no later than October 1, 2019 on
the property located at 3504 Lake Elmo Avenue North.
“Move to adopt Resolution 2019 – 023 approving the request of the Lake Elmo Inn for a time
extension to its conditional use permit to start substantial construction of a City-approved parking
facility on the property located at 3504 Lake Elmo Avenue North no later than October 1, 2019.”
ATTACHMENTS:
• Application Letter
• City Maps
• Resolution 2019 –023 approving the conditional use permit with the time extension
1
561387v1 SJS LA515-1
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION 2019-023
A RESOLUTION APPROVING THE REQUEST OF THE LAKE ELMO INN FOR A TIME
EXTENSION TO ITS CONDITIONAL USE PERMIT TO START SUBSTANTIAL
CONSTRUCTION OF A CITY-APPROVED PARKING FACILITY ON THE PROPERTY
LOCATED AT 3504 LAKE ELMO AVENUE NORTH NO LATER THAN OCTOBER 1, 2019
WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing
under the laws of the State of Minnesota; and
WHEREAS, Lake Elmo Inn, Inc., PO Box 182, Lake Elmo, MN 55042, (the “Applicant”)
submitted an application in 2018 to the City of Lake Elmo (the “City”) for a conditional use permit
to allow a parking facility at the property located at 3504 Lake Elmo Avenue North (the
“Property”); and
WHEREAS, the Lake Elmo Planning Commission held a public hearing on the proposed
conditional use permit on February 12, 2018; and
WHEREAS, the Lake Elmo Planning Commission submitted its report dated February 20,
2018 to the City Council and recommended approval of the conditional use permit; and
WHEREAS, the City Council approved the conditional use permit for the parking facility
at its February 20, 2018 meeting by adopting Resolution No. 2018-018 (the “CUP Resolution”);
and
WHEREAS, the CUP Resolution and Section 154.106 (K) of the City Code required the
Applicant to begin substantial construction of the parking facility no later than February 20, 2019
(12 months from the date the conditional use permit was approved by the City Council); and
WHEREAS, the Applicant has not yet commenced construction of the parking facility on
the Property; and
WHEREAS, Section 154.106 (K) of the City Code states that “upon application, the
Council after receiving recommendation from the Planning Commission, may extend the permit
for such additional period as it deems appropriate”; and
WHEREAS, on February 1, 2019, the Applicant submitted an application requesting City
Council approval of a time extension to begin substantial construction of the approved parking
facility on the Property; and
WHEREAS, the Lake Elmo Planning Commission reviewed the Applicant’s time
extension request on March 11, 2019 and recommended approval, subject to conditions; and
2
561387v1 SJS LA515-1
WHEREAS, the City notified the Applicant in writing of its decision to extend the
deadline for review of the Applicant’s time extension application for an additional 60 days
pursuant to Minnesota Statutes Section 15.99, subdivision 3 (f) on March 26, 2019; and
WHEREAS, the City Council considered the Applicant’s time extension request on April
2, 2019; and
NOW, THEREFORE, based on the testimony elicited and information received, the City
Council makes the following:
FINDINGS
1) That the procedures for obtaining a time extension for a Conditional Use Permit are found
in the Lake Elmo Zoning Ordinance, Section 154.106.
2) That all the submission requirements of said Section 154.106 have been met by the
Applicant.
CONCLUSIONS AND DECISION
Based on the foregoing, the Applicant’s request for a time extension to start substantial
construction of a City-approved parking facility on the Property to October 1, 2019 is granted and
the Applicant’s conditional use permit is hereby amended accordingly, subject to the following
conditions:
1) The Applicant shall submit and have approved a parking lot permit meeting all zoning,
engineering, and other applicable requirements.
2) The parking lot must adhere to all screening and landscaping requirements as outlined in the Staff
Report to the Planning Commission dated 2/12/2018 except for the requirement that landscape
screening be required along Lake Elmo Avenue and 34th Street North.
3) The Applicant must obtain a permit from the Valley Branch Watershed District prior to the
issuance of a permit for construction, provide a copy of the permit to the City, and adhere to all
conditions of approval.
4) Lighting will need to comply with Section 150.035: Lighting, Glare Control, and Exterior
Lighting Standards of the City Code.
5) The parking lot shall not extend beyond property lines.
6) The Applicant shall not barricade public right-of-way for the use of valet parking or any other
purposes without issuance of a right-of-way obstruction permit by the City.
7) The Applicant must start substantial construction of the approved parking facility no later than
October 1, 2019 unless the City Council grants another time extension for the conditional use
3
561387v1 SJS LA515-1
permit. If the Applicant has not started substantial construction of the parking facility by October
1, 2019 and a time extension is not applied for, the CUP will be declared void by the City
Council.
8) All other terms and conditions of Resolution No. 2018-018 shall remain in effect and unchanged.
Passed and duly adopted this 2nd day of April, 2019 by the City Council of the City of Lake Elmo,
Minnesota.
__________________________________
Mike Pearson, Mayor
ATTEST:
________________________________
Julie Johnson, City Clerk