HomeMy WebLinkAbout#06 - 2019 Seal Coat - Accept Bids STAFF REPORT
DATE: May 21, 2019
CONSENT
AGENDA ITEM: 2019 Seal Coat Project – Accept Bids and Award Contract
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director
Amanda Groh, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept bids and award a contract for the 2019
Seal Coat Project?
PROPOSAL DETAILS/ANALYSIS: Bids were received, publicly opened, and read aloud at City Hall
on Thursday, May 9, 2019. FOCUS Engineering, Inc. has prepared and attached the Tabulation of Bids
and a Letter of Recommendation for the award of the contract. The City received three (3) bids for this
project, with Pearson Bros, Inc. providing the lowest bid. Staff is recommending that Pearson Bros, Inc.
be awarded the contract in the amount of $119,616.60 which includes the amount of $56,224.08 for the
City of Lake Elmo and the amount of $63,392.52 for West Lakeland Township.
The project will be completed jointly with West Lakeland Township with the Township reimbursing Lake
Elmo their portion of the construction cost in the bid award amount of $63,392.52 (53%). West Lakeland
Township will also pay Lake Elmo $3,000 for engineering and administration fees once the Lake Elmo
City Council accepts the bids and awards the construction contract. Construction observation services
will be contracted directly by each jurisdiction for the work performed on their streets.
FISCAL IMPACT: $56,224.08.
The post-bid construction estimate for Lake Elmo is $56,224.08 (47%). The total engineering design,
bidding and construction services is estimated to be $9,000 less $3,000 to be reimbursed by West
Lakeland Township. The Lake Elmo total post-bid project cost is therefore estimated to be $62,224.08 to
be paid through the General Fund (Fund No. 101-430-3120-42250).
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the consent
agenda, a resolution accepting the bids and awarding a contract to Pearson Bros, Inc. If removed from
consent agenda, the recommended motion for this action is as follows:
“Move to approve Resolution No. 2019-040 Accepting the Bids and Awarding a Contract to Pearson
Bros, Inc. in the Bid amount of $119,616.60 for the 2019 Seal Coat Project; which includes $56,224.08
for the City of Lake Elmo and $63,392.52 for West Lakeland Township.”
ATTACHMENTS:
1. Resolution Accepting Bids and Awarding Contract for the 2019 Seal Coat Project.
2. Engineer’s Letter of Award Recommendation and Tabulation of Bids.
3. Project Schedule.
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2019-040
A RESOLUTION ACCEPTING THE BIDS AND AWARDING A
CONTRACT FOR THE 2019 SEAL COAT PROJECT
WHEREAS, pursuant to an advertisement for bids for the 2019 Seal Coat Project, bids were
received, opened, and tabulated according to law, and bids were received complying with the
advertisement; and
WHEREAS, bids were tabulated, checked and summarized to verify that all requirements of the
submittals were met; and
WHEREAS, the project engineer reviewed the bids and has provided a letter recommending the
award of the contract to the lowest responsible bidder, Pearson Bros, Inc. in the amount of
$119,616.60.
NOW, THEREFORE, IT IS HEREBY RESOLVED,
1. That the Mayor and City Clerk are hereby authorized and directed to enter into a Contract
in the accordance with the above ordered Project, in the amount of the Contractor’s lowest
responsible bid, and according to the plans and specifications thereof approved by the City
Council.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids, except that the deposits of the successful bidder and the next
two lowest bidders shall be retained until a contract has been signed.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE TWENTY-FIRST DAY OF
MAY 2019.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
Mayor
(Seal)
ATTEST:
________________________________
Julie Johnson
City Clerk
May 14, 2016
Honorable Mayor and City Council
City of Lake Elmo, Minnesota
2019 Seal Coat Project
City of Lake Elmo, Minnesota
FOCUS Project No. 2019.109
Dear Mayor and City Council:
Bids for the 2019 Seal Coat Project were received on May 9, 2019, at 3:00 PM with the following results:
Contractor Base Bid
Pearson Bros, Inc.
City of Lake Elmo $56,224.08
West Lakeland Township $63,392.52
TOTAL: $119,616.60
Allied Blacktop Company
City of Lake Elmo $59,398.02
West Lakeland Township $66,971.13
TOTAL: $126,369.15
Asphalt Surface Technologies
City of Lake Elmo $70,280.10
West Lakeland Township $79,240.65
TOTAL: $149,520.75
A complete Tabulation of Bids is enclosed for your information. We recommend that you award the Contract
to the lowest responsible bidder, Pearson Brows, Inc. in the total amount of $119,616.60.
Please contact me with any questions you may have.
Sincerely,
Amanda E. Groh, P.E.
Project Engineer
Enclosure
cc: Jack Griffin, City Engineer
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
TABULATION OF BIDS2019 SEAL COAT PROJECTLAKE ELMO, MNPROJECT NO. 2019.109BIDS OPENED: May 9, 2019 3:00PMITEMNO. ITEMUNIT QUANTITYUnit Price Total Amount Unit Price Total Unit Price Total Unit Price TotalCity of Lake Elmo ‐ Bituminous Seal Coat1BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK AND CRS 2P EMULSIFIED ASPHALTSY45,342 1.25$ 56,677.50$ 1.31$ 59,398.02$ 1.24$ 56,224.08$ 1.55$ 70,280.10$ West Lakeland Township ‐ Bituminous Seal Coat2BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK AND CRS 2P EMULSIFIED ASPHALTSY51,123 1.25$ 63,903.75$ 1.31$ 66,971.13$ 1.24$ 63,392.52$ 1.55$ 79,240.65$ TOTAL BASE BID120,581.25$ 126,369.15$ 119,616.60$ 149,520.75$ Asphalt Surface TechnologiesEngineer's Estimate Allied Blacktop Company Pearson Bros., Inc.
PROJECT SCHEDULE
CITY OF LAKE ELMO
2019 SEAL COAT PROJECT
PROJECT NO. 2019.109
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
APRIL 11, 2019 Placement of Advertisement for Bids.
– Oakdale-Lake Elmo Review. Publication on April 18
– Quest CDN. Publication on April 18
MAY 9, 2019 Receive Contractor bids.
MAY 21, 2019 Council accepts bids and awards Contract. Approve JSA with WLT
JUNE 19, 2019 Conduct Pre-construction meeting and Issue Notice to Proceed.
JUNE 24, 2019 Contractor begins Work.
AUGUST 5, 2019 Substantial Completion of Work; including sweeping of excess aggregate.
SEPTEMBER 6, 2019 Final Completion of Work; including punchlist and final documentation.