HomeMy WebLinkAbout#08 - 2019 Mill and Overlay STAFF REPORT DATE: August 7, 2019 CONSENT AGENDA ITEM: 2019 Mill and Overlay – Change Order No. 1 SUBMITTED BY: Amanda Groh, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 1 for the 2019 Mill and Overlay project? BACKGROUND: T.A. Schifsky & Sons, Inc. was awarded a construction contract on April 16, 2019 to complete the 2019 Mill and Overlay project. Construction is ongoing. PROPOSAL DETAILS/ANALYSIS: T.A. Schifsky & Sons, Inc. has submitted a change order to address the additional work requested by the City to provide a water service stub to Pebble Park; complete pavement patching along Keats Ave at the intersection with 59th St Ct N, 57th St N, and near 51st St N; and to replace existing concrete rings on catch basins in Wild Flower Shores adjacent to damaged curb that needs replacement. FISCAL IMPACT: This change order will increase the contract in the amount of $8,140.00, $2,640.00 from the watermain fund and $5,500.00 out of the 2019 street maintenance budget, bringing the revised construction contract to $673,433.05. With this change order, the project remains within the authorized project budget and contingencies. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 1 for the 2019 Mill and Overlay project. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 1 for the 2019 Mill and Overlay project, thereby increasing the contract amount by $8,140.00”. ATTACHMENTS: 1. Change Order No. 1. CHANGE ORDER NO.1 2019 MILL AND OVERLAY CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2018.132 QUANTITY UNIT PRICE AMOUNT CO1-1 LS 1.0 $2,640.00 $2,640.00 CO1-2 LS 1.0 $3,500.00 $3,500.00 CO1-3 EA 4.0 $500.00 $2,000.00 TOTALS - CHANGE ORDER NO. 1 $8,140.00 DESCRIPTION / JUSTIFICATIONITEM DESCRIPTION OF PAY ITEM UNIT CHANGE ORDER WATER SERVICE TO PEBBLE PARK KEATS AVE PAVEMENT PATCHING ADJUST CATCH BASIN CASTING WITH NEW RINGS AND INFI-SHIELD This item was added as a request by Public Works to be able to provide water service to the drinking fountain in Pebble Park. This item was added to repair settlement/patching concerns raised by Public Works. This item was added to replace existing concrete rings while repairing damaged curb adjacent to catch basins in the Wild Flower Shores neighborhood.