HomeMy WebLinkAbout#08 - CSAH 19 & Hudson Change Order 2 STAFF REPORT DATE: September 17, 2019 CONSENT AGENDA ITEM: CSAH 19 and Hudson Boulevard Intersection Improvements – Change Order No. 2 SUBMITTED BY: Chad Isakson, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 2 for the CSAH 19 and Hudson Boulevard Intersection Improvements? BACKGROUND: Max Steininger, Inc. was awarded a construction contract on June 4, 2019 to complete the CSAH 19 and Hudson Boulevard Intersection Improvements. The project construction is in progress. PROPOSAL DETAILS/ANALYSIS: Max Steininger, Inc. has submitted a change order to address additional work completed on the CSAH 19 and Hudson Boulevard Intersection Improvements as requested by the City and as identified below. 1. Reconstruct Catch Basin Manhole 5050: Remove casting, rings, infi-shield and install a 1-foot barrel section, rings, infi-shield, and casting in order to match the graded side slopes. The location of the manhole is in the corner of two slopes graded at 3:1, making surface elevations difficult to match. The final grading in the field requires the manhole to be raised 1-foot higher than its planned elevation. The total cost of the above items increases the contract by $1,373.28. FISCAL IMPACT: This change order will increase the contract in the amount of $1,373.28 bringing the revised construction contract to $1,797,395.02. With this change order, the project remains within the authorized project budget and contingencies. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 2 for the CSAH 19 and Hudson Boulevard Intersection Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 2 for the CSAH 19 and Hudson Boulevard Intersection Improvement Project, thereby increasing the contract amount by $1,373.28”. ATTACHMENTS: 1. Change Order No. 2. CONTRACT CHANGE ORDER FORM CHANGE ORDER NO. DATE: TO: UNIT Amount of Original Contract $ Sum of Additions/Deductions approved to date (CO No. 1 ) $ Contract Amount to date $ Amount of this Change Order (ADD) (DEDUCT) (NO CHANGE)$ Revised Contract Amount $ The Contract Period for Completion will be (UNCHANGED) (INCREASED) (DECREASED)days APPROVED BY ENGINEER: FOCUS Engineering, inc. APPROVED BY CONTRACTOR DATE DATE APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA DATE DATE 0 This Document will become a supplement to the Contract and all provisions will apply hereto. The Contract Documents are modified as follows upon execution of this Change Order. BYENGINEER 1,790,088.96 5,932.78 1,796,021.74 1,373.28 1,797,395.02 INCREASE/(DECREASE) MAX STEININGER, INC, 3080 LEXINGTON AVE SO, EAGAN, MN 55121 CSAH 19 AT HUDSON BLVD INTERSECTION IMPR. PROJECT NO. 2017.154 2 September 17, 2019 ITEM $1,373.28 NET CONTRACT CHANGE $1,373.28 CITY OF LAKE ELMO, MINNESOTA BYBY CHANGE ORDER DESCRIPTION / JUSTIFICATION: This change order addresses construction changes not included in the base contract as requested by the City: 1) Reconstruct Catch Basin Manhole 5050: Remove casting, rings, infishield and install a 1-foot barrel section, rings, infishield, and casting in order to match the graded side slopes. The location of the manhole is in the corner of two slopes graded at a 3:1. Final grading exposed a need to raise the manhole 1-foot higher than the planned elevation. Attachments (list documents supporting change):Itemization Summary DESCRIPTION OF PAY ITEM QTY UNIT PRICE **See attached itemization 9/6/2019 FOCUS Engineering, inc.CHANGE ORDER FORM CHANGE ORDER NO. 2 CSAH 19 AT HUDSON BLVD INTERSECTION IMPR. CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2017.154 CITY FUNDS SAP 206-120-001 COUNTY FUNDS SAP 082-619-028 CO 2-1 2506.503 EA 1.00 1.0 $1,373.28 $1,373.28 TOTALS - CHANGE ORDER NO. 2 $1,373.28 ITEM DESCRIPTION OF PAY ITEM UNIT CHANGE ORDER Reconstruct Drainage Structure QUANTITY TOTAL ESTIMATED QUANTITY UNIT PRICE AMOUNT DESCRIPTION / JUSTIFICATIONMN/DOT ITEM Remove casting, rings and infishield. Install 1-foot concrete manhole section, install rings, infishield, and casting.