HomeMy WebLinkAbout#07 Improvements and Security Reduction for the Savona 1st, 2nd and 3rd Additions STAFF REPORT
DATE: September 3, 2019
CONSENT
AGENDA ITEM: Accept Improvements and Approve Security Reduction for the Savona 1st,
2nd and 3rd Additions.
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Ken Roberts, Planning Director
Marty Powers, Public Works Director
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept the improvements and approve security
reductions for the Savona 1st, 2nd and 3rd Additions?
PROPOSAL DETAILS/ANALYSIS: Staff has received and processed requests to accept the
improvements and to reduce the development security for the Savona 1st, 2nd and 3rd Additions. This
request has been reviewed and the following reduction is being recommended:
Current Security Amount Proposed Security Amount
1. Savona 1st Addition $ 666,495 $ 547,612
2. Savona 2nd Addition $ 970,756 $ 549,773
3. Savona 3rd Addition $ 1,003,159 $ 898,985
The Savona 1st, 2nd and 3rd Addition street, sidewalk, trail and storm sewer improvements, and storm
water ponding and infiltration basins have been completed and are recommended for acceptance by the
City. The Certificates of Completion are attached. The warranty period for the improvements, except
utilities, will start on September 3, 2019 with the acceptance of the improvements, and the 1-year warranty
will end on September 3, 2020. Twenty-five percent (25%) of the original security amounts for these
categories will be retained until the warranty period has expired. All other security amounts (except
landscaping) are being recommended for release. In addition, the 2-year warranty period for the Savona 1st
and 2nd Additions has expired and the developer has made all warranty corrections that were identified by
City staff. Therefore, the twenty-five percent (25%) warranty security for these utilities are recommended
for release.
FISCAL IMPACT: It is the City’s goal to retain at all times during the subdivision improvements a
security amount that is adequate to ensure completion of all elements of the improvements as protection to
the City tax payers against the potential of developer default.
RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda,
accept the improvements and approve the security reductions for the Savona 1st, 2nd and 3rd Additions as
detailed in the respective worksheets. If removed from the consent agenda, the recommended motion for
the action is as follows:
“Move to accept the improvements and approve security reduction for the Savona 1st, 2nd and 3rd
Additions as detailed in the attached Security Reduction Worksheets”.
ATTACHMENTS:
1. Certificate of Completion – Savona 1st Addition.
2. Certificate of Completion – Savona 2nd Addition.
3. Certificate of Completion – Savona 3rd Addition.
4. Security Reduction Worksheet – Savona 1st Addition.
5. Security Reduction Worksheet – Savona 2nd Addition.
6. Security Reduction Worksheet – Savona 3rd Addition.
CERTIFICATE OF COMPLETION
DATE OF ISSUANCE: September 3, 2019
OWNER: CITY OF LAKE ELMO, MN
DEVELOPER: U.S. HOME CORPORATION, D/B/A LENNAR
SUBDIVISION
NAME:
SAVONA 1ST ADDITION
PROJECT NO.: 2012.130
This Certification of Completion applies to all work under the Development Agreement
This Certification of Completion applies to the following specified parts of the Development
Agreement
Section 33.A – Public sewer and watermain
Section 33.B – Public improvements including street construction, concrete curb and gutter,
storm sewer facilities, sidewalks, trails, materials and equipment.
I do hereby certify that the work to which this Certificate applies has been constructed in accordance
with the Development Agreement dated July 1, 2014. The above-mentioned improvement is hereby
declared to be complete and acceptance of this work is recommended.
DATE OF COMPLETION: September 3, 2019
Ryan Stempski Reg. No. 45395
FOCUS Engineering, inc.
Section 33.A Warranty Period Begins December 20, 2016 and ends December 20, 2018
Section 33.B Warranty Period Begins
September 3, 2019
and ends
September 3, 2020
CERTIFICATE OF COMPLETION
DATE OF ISSUANCE: September 3, 2019
OWNER: CITY OF LAKE ELMO, MN
DEVELOPER: U.S. HOME CORPORATION, D/B/A LENNAR
SUBDIVISION
NAME:
SAVONA 2ND ADDITION
PROJECT NO.: 2014.138
This Certification of Completion applies to all work under the Development Agreement
This Certification of Completion applies to the following specified parts of the Development
Agreement
Section 33.A – Public sewer and watermain
Section 33.B – Public improvements including street construction, concrete curb and gutter,
storm sewer facilities, sidewalks, trails, materials and equipment.
I do hereby certify that the work to which this Certificate applies has been constructed in accordance
with the Development Agreement dated October 22, 2014. The above-mentioned improvement is
hereby declared to be complete and acceptance of this work is recommended.
DATE OF COMPLETION: September 3, 2019
Ryan Stempski Reg. No. 45395
FOCUS Engineering, inc.
Section 33.A Warranty Period Begins December 20, 2016 and ends December 20, 2018
Section 33.B Warranty Period Begins
September 3, 2019
and ends
September 3, 2020
CERTIFICATE OF COMPLETION
DATE OF ISSUANCE: September 3, 2019
OWNER: CITY OF LAKE ELMO, MN
DEVELOPER: U.S. HOME CORPORATION, D/B/A LENNAR
SUBDIVISION
NAME:
SAVONA 3RD ADDITION
PROJECT NO.: 2015.124
This Certification of Completion applies to all work under the Development Agreement
This Certification of Completion applies to the following specified parts of the Development
Agreement
Section 34.A – Public sewer and watermain
Section 34.B – Public improvements including street construction, concrete curb and gutter,
storm sewer facilities, sidewalks, trails, materials and equipment.
I do hereby certify that the work to which this Certificate applies has been constructed in accordance
with the Development Agreement dated October 22, 2015. The above-mentioned improvement is
hereby declared to be complete and acceptance of this work is recommended.
DATE OF COMPLETION: September 3, 2019
Ryan Stempski Reg. No. 45395
FOCUS Engineering, inc.
Section 34.A Warranty Period Begins January 16, 2018 and ends January 16, 2020
Section 34.B Warranty Period Begins
September 3, 2019
and ends
September 3, 2020
SAVONA 1ST ADDITION Time of Performance: October 31, 2015
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading $650,000 $812,500 100%$812,500
Sanitary Sewer $138,099 $172,624 100%$86,312 $43,156 $43,156
Watermain $155,927 $194,909 100%$97,454 $48,727 $48,727
Streets $763,387 $954,234 75%$477,117 $238,558
Surface Water Facilities $493,703 $617,129 75%$308,564 $154,282
Erosion Control $52,533 $65,666 75%$32,833 $16,417
Sidewalks/Trails $119,642 $149,553 75%$112,164
Street Lighting NA NA By Xcel Energy
Street Signs and Traffic Control Signs $11,600 $14,500 75%$7,250 $3,625
Landscaping $97,236 $121,545 75%
Tree Preservation and Restoration NA NA
Wetland Mitigation and Buffers NA NA LOC Through VBWD
Monuments $6,450 $8,063 75%$6,047
Miscellaneous Facilities NA NA
Record Drawings $2,500 $3,125 75%$2,344
TOTALS $2,491,077 $3,113,846 RELEASED AMOUNTS:$969,448 $1,295,189 $182,714 $91,883
$575,337 CUMMULATIVE AMOUNTS:$969,448 $2,264,637 $2,447,351 $2,539,234
SECURITY AMOUNT REMAINING:$2,144,399 $849,210 $666,495 $574,612
DATE: 3/2/2016 12/20/2016 2/5/2019 9/3/2019
REDUCTIONS
SAVONA 2ND ADDITION Time of Performance: October 31, 2015
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading NA NA NA
Sanitary Sewer $314,594 $393,243 100%$196,621 $98,311 $98,311
Watermain $485,172 $606,464 100%$303,232 $151,616 $151,616
Streets $614,836 $768,545 75%$384,272 $192,136
Surface Water Facilities $471,332 $589,165 75%$294,583 $147,291
Erosion Control $51,146 $63,933 75%$31,966 $15,983
Sidewalks/Trails Included in Streets Included in Streets
Street Lighting NA NA By Xcel Energy
Street Signs and Traffic Control Signs Included in Streets Included in Streets
Landscaping $153,415 $191,769 75%
Tree Preservation and Restoration NA NA
Wetland Mitigation and Buffers NA NA LOC Through VBWD
Monuments $5,800 $7,250 75%$5,438
Miscellaneous Facilities NA NA
Record Drawings $2,500 $3,125 75%$2,344
TOTALS $2,098,795 $2,623,494 RELEASED AMOUNTS:$1,178,709 $474,029 $420,982
$655,873 CUMMULATIVE AMOUNTS:$1,178,709 $1,652,738 $2,073,720
SECURITY AMOUNT REMAINING:$1,444,785 $970,756 $549,773
DATE: 3/2/2016 12/20/2016 9/3/2019
REDUCTIONS
SAVONA 3RD ADDITION Time of Performance: October 31, 2016
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading (Separate Grading Agreement) $127,000 $127,000
Sanitary Sewer $345,301 $431,626 75%$215,813 $107,907
Watermain $503,113 $628,891 75%$314,446 $157,223
Streets $1,168,007 $1,460,009 75%$730,004 $365,002
Surface Water Facilities $333,140 $416,425 50%$208,213 $104,106
Erosion Control $133,732 $167,165 75%$125,374
Sidewalks/Trails Included in Streets Included in Streets
Street Lighting NA NA By Xcel Energy
Street Signs and Traffic Control Signs Included in Streets Included in Streets
Landscaping $95,218 $119,023 0%
Tree Preservation and Restoration NA NA
Wetland Mitigation and Buffers NA NA LOC Through VBWD
Monuments $6,000 $7,500 75%$5,625
Miscellaneous Facilities NA NA
Record Drawings $6,500 $8,125 75%$6,094
TOTALS $2,591,011 $3,365,764 RELEASED AMOUNTS:$1,468,476 $392,129 $502,095 $104,106
$809,691 CUMMULATIVE AMOUNTS:$1,468,476 $1,860,605 $2,362,700 $2,466,806
SECURITY AMOUNT REMAINING:$1,897,288 $1,505,159 $1,003,064 $898,958
DATE: 12/20/2016 1/16/2018 2/5/2019 9/3/2019
REDUCTIONS