DATE: October 13, 2020
DISCUSSION
AGENDA ITEM: Manning Phase 3 Update
SUBMITTED BY: Kristina Handt, City Administrator
BACKGROUND:
Manning Phase 3 (Manning from the reconstruct of Manning/Stillwater Blvd to north of 10th St) has been
in the city and county’s Capital Improvement Plan (CIP) for a few years. As shown on the project
summary sheet included in your packet it had been tentatively planned for 2023. Earlier this year the
County held an online open house to gather feedback from residents (accessible at
https://spark.adobe.com/page/4mPMHp6EtxLrF/ ). A copy of the feedback is also included in your
packet. The link to the interactive map showing the location of where feedback came from is
https://wcmn.maps.arcgis.com/apps/CrowdsourceReporter/index.html?appid=ced3416d33fd4853a23a287
068b8ceea
ISSUE BEFORE COUNCIL:
What feedback does the Council have regarding Manning Phase 3?
PROPOSAL DETAILS/ANALYSIS:
While staff had been planning to bring this information to council to share the public feedback and get input
from council regarding that feedback (trails, Easton Village Access, etc), the county recently informed us
that they no longer have funding to move forward with the project as planned in 2023. The two sources of
funding they had identified (bonding and increased sales tax) are no longer approved funding sources for
them. Instead the county will be changing their focus to traffic management improvements. While nothing
specific has been identified, city staff has emphasized the need for a stop light at Manning and 30th St in
the near future. The county may also decide to break the project up into smaller sections depending upon
their funding availability.
FISCAL IMPACT:
As shown in the city’s CIP, the funding source for the city contribution was planned to be debt service and
possibly assessments. The city has also included $250,000 for the stoplight at Manning and 30th St. in the
CIP with the funding source being Municipal State Aid (MSA) funds. With the recent 12% cut in those
funds from the state, the city will have to re-evaluate which projects are slated for this funding source.
ATTACHMENT:
• Survey Results
• CIP Summary Sheet
Survey Comments
Trails desired along entire route 37
Speed 19
Roundabouts preferred 13
Noise 11
30th Street Intersection (Signal or Roundabout)9
Maintain Easton Village Access off Manning 7
Intersection Improvements 6
Landscaping 5
24th Street Improvements 4
Maintain Snowmobile Trail 3
Improve Neighborhood Access 3
Do not like U-Turn access 2
Increased Police Presense for Speeding 2
Safety Crossing Manning for Pedestrians 2
Do not want trails 2
Do not add stoplights 1
Property Value Concerns 1
Minimize traffic impacts, efficent traffic flow 1
Concerned with Limited Access to Manning 1
Remove Snowmobile Trail 1
Vibrations from traffic 1
Do not want median 1
Remove intersection at Manning Trail and Avenue 1
Improvements needed sooner 1
Environmental Concerns 1
Railroad Crossing Improvements 1
Airport Access Improvements 1
Wide shoulders for Farm Equiptment 1
Bike Lane 1
3 Lane Section 1
Map Comment Summary
Trails desired along entire route 26
Roundabouts preferred 22
Do not want trails 12
Maintain Easton Village Access off Manning 11
30th Street Intersection (Signal or Roundabout)9
Speed 8
Noise 4
Landscaping 3
Maintain Snowmobile Trail 3
24th Street Improvements 3
Trail on one side of Manning 3
Intersection Improvements 2
Remove intersection at Manning Trail and Avenue 2
Safety Crossing Manning for Pedestrians 1
Vibrations from traffic 1
Do not want median 1
Railroad Crossing Improvements 1
Higher Speeds 1
Do not add stoplights 1
Capital Improvement Plan - 2021 - 2025
City of Lake Elmo, Minnesota Contact Engineer
2021 2025thru Department Public Works Department
Description
CSAH 15 from CSAH 14 to CSAH 10
Per Washington County includes:
Expansion to four lane divided highway
Access management
Intersection control
Separate multi-use trail
Landscaping and Aesthetics
Project #PW-057
Priority 3 Important
Justification
Need determined by Washington County
Budget Impact/Other
30% assessment to residential properties
Trail could come from park dedication funds
County could delay project if not inlcuded as part of their BOND-2022
Useful Life 25 years
Project Name Manning Ave Phase 3 Category Street Reconstruction
Type Improvement
Total Project Cost:$1,650,000
Status Active
Total20212022202320242025Expenditures
1,650,0001,650,000Construction/Maintenance
1,650,000 1,650,000Total
Total20212022202320242025Funding Sources
1,650,0001,650,000Debt Service
1,650,000 1,650,000Total