HomeMy WebLinkAbout#13 - Stonegate Street & Utility Project Change Order STAFF REPORT DATE: October 6, 2020 CONSENT AGENDA ITEM: Approve Change Order No. 3 for the Stonegate Addition Street & Utility Improvements SUBMITTED BY: Mark Scholle, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 3 for the Stonegate Addition Street and Utility Improvements? BACKGROUND: A-1 Excavating, Inc. was awarded a construction contract on May 5, 2020 to complete the Stonegate Addition Street & Utility Improvements. Work remains in progress with a substantial completion date of September 25, 2020 and final completion date of November 13, 2020. PROPOSAL DETAILS/ANALYSIS: A-1 Excavating, Inc. has requested an extension to the contract times to meet substantial completion for the improvements. Staff has reviewed this request and is recommending that the request be approved to extend the contract times for substantial completion by an additional 8 days; 3 days for rain delays when work was unable to proceed, and 5 days due to delays in the shipment of materials due to COVID 19. Staff has subsequently prepared Change Order No. 3 to revise the substantial completion date from September 25, 2020 to October 3, 2020. The final completion date will remain unchanged. FISCAL IMPACT: There is change in the contract amount as part of this change order. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 3 for the Stonegate Addition Street & Utility Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 3 for the Stonegate Addition Street & Utility Improvements, thereby revising the substantial completion date from September 25, 2020 to October 3, 2020”. ATTACHMENTS: 1. Change Order No. 3 9/21/2020