HomeMy WebLinkAbout#15 - Hamlet on Sunfish Lake Geotechnical Services STAFF REPORT
DATE: October 6, 2020
CONSENT
AGENDA ITEM: Approve Geotechnical Services Contract for the Hamlet on Sunfish Lake Street
and Utility Improvements
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator
Marty Powers, Public Works Director
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve a Geotechnical Services Contract with
AET, Inc. for the Hamlet on Sunfish Lake Street and Utility Improvements?
BACKGROUND: At the July 21, 2020 council meeting the City Council authorized the preparation of
plans and specifications for the Hamlet on Sunfish Lake Street and Utility Improvements. The project will
extend municipal water into the neighborhood to provide clean drinking water to each of the 41 homes. The
private HOA Sanitary sewer collection system will be repaired and replaced as necessary to ready the
system for city ownership and maintenance. Following the utility work, the public streets will be
reconstructed together with the installation of drain tile and concrete curb and gutter.
PROPOSAL DETAILS/ANALYSIS: As part of the detailed design services for the street and utility
improvements, a geotechnical investigation needs to be completed. The services include taking soil borings,
analysis of soil properties, and preparation of a report including recommendations for pipe bedding, street
pavement sections, and other recommendations for constructing the proposed improvements. Proposals
were solicited from two firms in the city consulting engineering pool, including Braun Intertec Inc, and
American Engineering Testing (AET), Inc. The City Engineer is recommending a contract be awarded to
American Engineering Testing (AET), Inc.
FISCAL IMPACT: $11,700. The work scope and fees are within the previously council authorized budget
for the Project. Total estimated project cost of $3,970,600.
RECOMMENDATION: Staff is recommending that the City Council consider, as part of the consent
agenda, awarding a Geotechnical Services Contract for the Hamlet on Sunfish Lake Street and Utility
Improvements. Staff is recommending AET, Inc. be awarded the contract in a not to exceed amount of
$11,700. If removed from the consent agenda, the recommended motion for this action is as follows:
“Move to approve a Geotechnical Services Contract to AET, Inc in the not to exceed amount of
$11,700 for the Hamlet on Sunfish Lake Street and Utility Improvements.”
ATTACHMENTS:
1. American Engineering Testing (AET), Inc. Geotechnical Services Proposal.
550 Cleveland Avenue North | Saint Paul, MN 55114
Phone (651) 659-9001 | (800) 972-6364 | Fax (651) 659-1379 | www.amengtest.com | AA/EEO
This document shall not be reproduced, except in full, without written approval from American Engineering Testing, Inc.
September 8, 2020
City of Lake Elmo
3880 Laverne Avenue North
Lake Elmo, MN 55042
Attn: Chad Isakson, PE
Re: Proposal for Geotechnical Services
AET Proposal No. 01-20971
Hamlet on Sunfish Lake Street and Utility Improvements
Dear Mr. Isakson:
American Engineering Testing, Inc. (AET) is pleased to submit this proposal to conduct
the scope of services listed below:
Scope of Services:
Field Exploration
• Drill and sample sixteen (16) standard penetration test (SPT) borings to depths of 11
and 14½ feet, totaling of 218 feet of soil drilling.
• Stake the soil borings in the field using provided diagrams or GPS coordinates.
• Clear underground public utilities through the Gopher State One Call system.
• Backfill borings per Minnesota Department of Health requirements.
• Measure and document the boring locations and surface elevations by using a GPS.
Laboratory
• Visually-manually classify the soils per the Unified Soil Classification System.
• Conduct water content tests on cohesive soils retrieved.
• Perform sieve analysis testing (P200) to aid in infiltration rate assessments.
Report (to include)
• Logs of the test borings, including soil classifications, N-values, and laboratory results.
• Review of encountered soil and groundwater conditions.
• Foundation, bedding, and backfilling recommendations for the proposed watermain
lines. Comments on constructability of trenchless installation methods.
• Estimation of infiltration rates for the proposed basin based on MSM guidelines.
• Recommendation for pavement subgrade preparation, estimated R-value, and
pavement design.
AET’s scope of work is intended for geotechnical purposes only, and not to explore for the
presence or extent of environmental contamination at the site. However, we will note
obvious contamination encountered.
CONSULTANTS
· ENVIRONMENTAL
· GEOTECHNICAL
· MATERIALS
· FORENSICS
City of Lake Elmo
Sunfish Lake Street and Utility Improvements
September 8, 2020
Page 2 of 2
American Engineering Testing, Inc.
Fee:
Our services will be performed on a time-and-material basis per the attached fee schedule.
For the scope described, we will establish $11,700 as a not-to-exceed fee. The units and
unit rates to arrive at this budget are shown in attached Table A.
Schedule:
Based on our current backlog, we anticipate the fieldwork can begin in about 3 weeks after
receiving authorization to proceed. Verbal results can be provided shortly after fieldwork
completion. The final report should then follow field completion by about 2 to 2½ weeks.
Terms/Conditions:
Our services will be conducted per our executed Contract Agreement between the City of
Lake Elmo and American Engineering Testing, Inc. for Professional Services, dated July
10, 2010.
Acceptance:
Please indicate your acceptance of this proposal by endorsing the enclosed copy and
returning it to us. The original proposal is intended for your records.
Sincerely,
American Engineering Testing, Inc.
Liang Chern Chow, PE Jeffery K. Voyen, PE
Geotechnical Engineer Vice President/Principal Engineer
Phone: 612-685-4313 Phone: 651-659-1305
Email: lchow@amengtest.com Email: jvoyen@amengtest.com
AET PROPOSAL No.: 01-20971 ACCEPTANCE AND AUTHORIZATION
Signature ______________________________________ Date _______________________
Printed Name _________________________________________________________________
Title ________________________________________________________________________
Representing__________________________________________________________________
Attachment: 2020 Geotechnical Fee Schedule
Table A – Budget Details
2020 GEOTECHNICAL FEE SCHEDULE
01DPM021.15 (1/20) AMERICAN ENGINEERING TESTING, INC.
I. Personnel Hourly Rates
A. Administrative Assistant 71.00/hr.
B. Engr. or Env. Technician I 78.00/hr.
C. Engr. or Env. Technician II 91.00/hr.
D. Drill Technician/Geo Lab Technician 104.00/hr.
E. Engr. or Env. Technician III 112.00/hr.
F. Engineering Assistant 121.00/hr.
G. Engineer I/Geologist I 134.00/hr.
H. Engineer II/Geologist II/Sr. Engr. Assistant 154.00/hr.
I. Senior Engineer/Geologist 176.00/hr.
J. Principal Engineer/Geologist 215.00/hr.
K. Principal of Firm 235.00/hr.
II. Vehicle Mileage
A. Personal Automobile/Truck 0.75/mile
B. Auxiliary Truck Vehicle 1.00/mile
C. Truck with Coring, FWD, or GPR Equipment 1.10/mile
D. Truck with Warning Sign/Crash Trailer 1.20/mile
E. 1-ton Truck with Drill Rig 1.20/mile
F. 1½ to 2½-ton Truck with Drill Rig 1.35/mile
G. CPT Truck Rig (20-ton push capacity) 1.60/mile
H. Tractor/Lowboy Trailer 1.80/mile
III. Equipment Rental
A. Drill Rig Rental
1. Rotary Drill on 1-ton Truck 80.00/hr.
2. Rotary Drill on 1½ to 2½-ton Truck 90.00/hr.
3. Rotary Drill on All-Terrain Vehicle 123.00/hr.
4. Portable, Non-rotary Rig 90.00/hr.
B. Auxiliary/Specialty Vehicle Rental
1. Auxiliary Truck Vehicle 20.00/hr.
2. Truck with Warning Sign/Crash Trailer 44.00/hr.
3. Truck with Coring Equipment 61.00/hr.
C. Cone (CPT) Rig/Equipment Rental
1. CPT Rig (Truck or ATV) 159.00/hr.
2. Electronic Cone w/Computer 49.00/hr.
3. Soil Sampler 8.00/hr.
4. Water Sampler 22.00/hr.
D. Miscellaneous Equipment Rental
1. Field Vane Shear 335.00/day
2. Field Electrical Resistivity 265.00/day
3. Field Seismic Shear Wave (ReMi) 435.00/day
4. Inclinometer Reading Equipment 350.00/day
5. Electronic Transducer Reading 180.00/day
6. Bore Hole Permeability
a. Open End Casing Method 140.00/day
b. HQ Wireline Packer 350.00/day
7. Borehole Pressuremeter 75.00/hr.
8. Iowa Borehole Shear Tester 335.00/day
9. Double Ring Infiltrometer 275.00/day
10. GPS Mapping System 17.00/hr.
11. Pile Driving Analyzer (PDA) 750.00/day
12. Calibrated SPT Rod 230.00/day
13. Pile Integrity Test (PIT) 360.00/day
E. Geotechnical Software Rental
1. Geo Studio Finite Element 85.00/hr.
2. CAPWAP 50.00/hr.
3. AutoCAD or Microstation 40.00/hr.
4. Wave Equation (WEAP) 30.00/hr.
5. LPILE or GROUP 30.00/hr.
6. Slope Stability (ReSSA) 30.00/hr.
7. Stabilized Earth Slopes & Walls 30.00/hr.
8. Settlement (FoSSA) 30.00/hr.
F. Bit Wear- Rock Coring
1. Diamond Bit - Sedimentary Rock
a) B, NQ 13.00/foot
b) HQ 15.00/foot
2. Diamond Bit - Metamorphic & Igneous
a) B, NQ 21.00/foot
b) HQ 24.00/foot
IV. Laboratory Tests of Soil
A. Water Content hourly
B. Dry Density (includes water content) 60.00/test
C. Atterberg Limits (ASTM:D4318)
1. Plasticity Index 120.00/test
2. Liquid Limit or Plastic Limit Separately 105.00/test
D. Sieve Analysis (includes -#200) 112.00/test
E. Hydrometer Analysis (sieve included) 210.00/test
F. Thermal Resistivity w/Proctor (ASTM:D5334)
1. As Received and Oven Dried (2 pts) 1000.00/test
2. Dry Out Curve (4 pts) 1245.00/test
G. Electrical Resistivity (ASTM:G57-Soil Box) 107.00/test
H. Corrosion/Concrete Attack Series* price upon request
I. Consolidation (up to 32 tsf)
1. With P-e curves only 500.00/test
2. With P-e curves, time curves 620.00/test
J. Unconfined Compression (incl. wc/density) 105.00/test
K. Hand Penetrometer 15.00/test
L. Organic Content of Soil 75.00/test
M. Topsoil Borrow Test (Mn/DOT 3877) 300.00/test
N. R-value (Hveem Stabilometer) 400.00/test
O. California Bearing Ratio
1. Granular 640.00/test
2. Cohesive 730.00/test
P. Proctor Tests (Methods A or B)
1. Standard 145.00/test
2. Modified 155.00/test
*includes pH, chloride ion, soluble sulfates, sulfides,
redox potential (resistivity not included).
V. Expenses
A. Direct Project Expenses: includes out-of- Cost + 15%
town per diem; plowing & towing; special
materials & supplies; special travel,
transportation & freight; subcontracted
services, and miscellaneous costs
B. Equipment Replacement (when abandonment Cost
is more feasible than recovery)
C. Equipment Recovery (when required by Cost + 15%
regulatory agencies or project specifications)
The rates presented are portal-to-portal with vehicle mileage, expenses
and equipment rentals being additional.
Overtime for personnel charged at above cost plus 25% for over 8 hours
per day or Saturday; and at above cost plus 50% for Sundays or Holidays.
Hazardous work charged at an additional 25%. Night time shift work will
include a premium charge of $30.00 per person per shift.
Hourly Breakdown:
Rate Total
Principal Engineer 1 hours $215.00 $215.00
Engineer II 11 hours $154.00 $1,694.00
Engineering Assistant 2 hours $121.00 $242.00
Senior Engr Tech III 2 hours $112.00 $224.00
Drill/Lab Technician 51.5 hours $104.00 $5,356.00
Word Processing Specialist 2 hours $71.00 $142.00
Total: $7,873.00
Equipment Rental/Mileage:
Rate Total
Auxiliary Drill Truck Mileage 200 miles $1.00 $200.00
1.5-2.5 Ton Truck Drill Rig Mileage 80 miles $1.35 $108.00
Tractor/Lowboy Trailer Mileage 40 miles $1.80 $72.00
Auxiliary Drill Truck Rental 29 hours $20.00 $580.00
1.5-2.5 Ton Truck Drill Rig Rental 14 hours $90.00 $1,260.00
All-Terrain Drill Rig Rental 10 hours $123.00 $1,230.00
GPS Equipment 2 hours $17.00 $34.00
Total: $3,484.00
Lab Test Rates
Rate Total
Sieve Analysis, P200 only 6 tests $50.00 $300.00
Total: $300.00
Overall Total: $11,657.00
Unit
Unit
Unit
Table A - Budget Details