DATE: November 17, 2020
CONSENT
AGENDA ITEM: Accept Improvements and Approve Security Reduction for the Hammes Estates
3rd Addition.
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Ken Roberts, Planning Director
Marty Powers, Public Works Director
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept the improvements and approve a security
reduction for the Hammes Estates 3rd Addition?
PROPOSAL DETAILS/ANALYSIS: Staff has received and processed a request to accept the
improvements and to reduce the development security for the Hammes Estates 3rd Addition. This request
has been reviewed and the following reduction is being recommended:
Current Security Amount Proposed Security Amount
1. Hammes Estates 3rd Add. $1,277,288 $861,170
The Hammes Estates 3rd Addition street and drainage improvements are now in the warranty period per
the attached Certificate of Completion. Twenty-five percent (25%) of the original security amount will be
retained until the warranty period expires on November 17, 2021 for street and drainage improvements.
This release of security is conditioned on the developer bringing their escrow accounts into compliance.
FISCAL IMPACT: It is the City’s goal to retain at all times during the subdivision improvements a
security amount that is adequate to ensure completion of all elements of the improvements as protection to
the City tax payers against the potential of developer default.
RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda,
accept the improvements and approve the security reduction for the Hammes Estates 3rd Addition as
detailed in the attached worksheet contingent upon the escrow accounts being brought into compliance. If
removed from the consent agenda, the recommended motion for the action is as follows:
“Move to accept improvements and approve the security reduction for the Hammes Estates 3rd
Addition as detailed in the attached Security Reduction Worksheet, contingent upon the escrow
accounts being brought into compliance”.
ATTACHMENTS:
1. Certificate of Completion – Hammes Estates 3rd Addition.
2. Security Reduction Worksheet – Hammes Estates 3rd Addition.
HAMMES 3RD ADDITION Time of Performance: October 31, 2018DEVELOPMENT AGREEMENT AMOUNTSCATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6Grading NA NAIncluded in Phase 1Sanitary Sewer $384,246 $480,307 $360,230Watermain $503,893 $629,866 $472,399Storm Sewer (w/pond structures) $360,855 $451,068 $225,534 $112,767Streets + Sidewalks $500,959 $626,199 $313,099 $156,550Bituminous Trails $48,972 $61,215 $45,911Surface Water Facilities NA NAStreet Lighting $48,000 $60,000 $45,000Street Signs and Traffic Control Signs $3,100 $3,875 $2,906Private Utilities (electricity, natural gas, telephone, and cable)Landscaping $212,300 $265,375Tree Preservation and Restoration NA NAWetland Mitigation and Buffers NA NAMonuments $6,900 $8,625 $6,469Erosion Control $44,616 $55,770 $41,828Miscellaneous Facilities NA NARecord Drawings $5,000 $6,250 $4,688TOTALS $2,118,840 $2,648,551RELEASED AMOUNTS:$1,371,263 $416,118 $0 $0 $0 $0CUMMULATIVE AMOUNTS:$1,371,263 $1,787,382SECURITY AMOUNT REMAINING:$1,277,288 $861,170DATE:3/17/2020 11/17/2020REDUCTIONS