Loading...
HomeMy WebLinkAbout#04 - 2020 Mill and Overlay Change Order 2 STAFF REPORT DATE: November 3, 2020 CONSENT AGENDA ITEM: Approve Change Order No. 2 for the 2020 Mill and Overlay Project SUBMITTED BY: Cara Geheren, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 2 for the 2020 Mill and Overlay project? BACKGROUND: Minnesota Paving and Materials was awarded a construction contract on June 2, 2020 to complete the 2020 Mill and Overlay Project. The work is substantially completed with the exception of minor punch list items. The project had a substantial completion date of August 28, 2020 and final completion date of September 18, 2020. PROPOSAL DETAILS/ANALYSIS: Minnesota Paving and Materials has submitted a change order to address additional work required to complete various aspects of the project as follows: • The project bid included a line item to adjust existing valve boxes to the final pavement height. During construction, it was discovered that three valve boxes could not be adjusted as their existing valve boxes were broken or damaged before the project began. Additional work and materials were required by the contractor to replace the broken valve box sections. • Additional work and materials were required by the contractor to replace a section of roadway where the underlaying base material failed. The aggregate base section was removed and replaced with new material and the area was repaved. • Additional shoulder grading work was required by the contractor to grade the shoulder for positive drainage. Following the paving of the wear course pavement, areas of the shoulder were higher than the drive lane, prohibiting runoff from leaving the roadway. FISCAL IMPACT: This change order will increase the contract in the amount of $10,542.00 bringing the revised construction contract to $343,602.18. With this change order the project remains within the planned budget. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 2 for the 2020 Mill and Overlay Project. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 2 for the Mill and Overlay Project, thereby increasing the contract amount by $10,542.00”. ATTACHMENTS: 1. Change Order No. 2. 10.27.2020 CHANGE ORDER NO.2 2020 MILL AND OVERLAY PROJECT CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2020.110 QUANTITY UNIT PRICE AMOUNT CO2-1 LS 1.0 $2,330.00 $2,330.00 CO2-2 LS 1.0 $2,180.00 $2,180.00 CO2-3 LF 1,856.0 $3.25 $6,032.00 TOTALS - CHANGE ORDER NO. 2 $10,542.00 During construction, three existing gate valve boxes were found to have top sections in need of repair. This line item covers time and materials to remove pavement at the valve boxes, to excavate and remove broken valve box sections, to install new valve box sections and lids as necessary, and to pave new shoulder patches After paving, a section of the shoulder exhibited base failure near 3812 Jamaca Ave N. This line item covers time and materials to remove pavement, to excavate the unsuitable shoulder base material, to replace with new base material, and to pave a new shoulder patch After paving, sections of the existing shoulder were higher than the edge of pavement. This line item covers removal of excess material and grading of the shoulder to drain away from the road. DESCRIPTION / JUSTIFICATIONITEM DESCRIPTION OF PAY ITEM UNIT CHANGE ORDER REMOVE AND REPLACE VALVE BOXES PATCH FAILED SHOULDER GRADE SHOULDER TO DRAIN