Loading...
HomeMy WebLinkAbout#18 - Change Order for Well 5 WM STAFF REPORT DATE: December 15, 2020 CONSENT AGENDA ITEM: Approve Compensating Change Order No. 2 for the Well No. 5 Connecting Watermain Improvements SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Chad Isakson, Project Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Compensating Change Order No. 2 for the Well No. 5 Connecting Watermain Improvements? BACKGROUND: Miller Excavating, Inc. was awarded a construction contract on July 16, 2020 to complete the Well No. 5 Connecting Watermain Improvements project. The contractor has completed the work in accordance with the contract, plans, and specifications. PROPOSAL DETAILS/ANALYSIS: Miller Excavating, Inc. has submitted a compensating change order to reconcile the estimated and actual quantities installed on the project. With approval of this change order the contract amount will be adjusted to reflect the actual quantities installed as a part of the project. FISCAL IMPACT: $16,921.77 increase to the final construction contract amount. This compensating change order will increase the final construction contract amount to $519,469.60. The original construction contract amount at the time of award was $500,000.33. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Compensating Change Order No. 2 for the Well No. 5 Connecting Watermain Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Compensating Change Order No. 2 for the Well No. 5 Connecting Watermain Improvements, thereby increasing the contract amount by $16,921.77”. ATTACHMENTS: 1. Compensating Change Order No. 2.