HomeMy WebLinkAbout#27 - Tamarack Farm Estates Street Improvements STAFF REPORT DATE: December 15, 2020 REGULAR AGENDA ITEM: Approve Resolution Receiving Feasibility Report and Calling Hearing on Improvement for the Tamarack Farm Estates Street Improvements SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Cara Geheren, Project Engineer ISSUE BEFORE COUNCIL: Should the City Council accept the Feasibility Report and call a public hearing for the Tamarack Farm Estates Street Improvements to be held at the January 19, 2021 Council meeting? BACKGROUND: On October 6, 2020, the City Council authorized the preparation of a feasibility report for the Tamarack Farm Estates Street Improvements. Linden Trail North, within the Tamarack Farm Estates subdivision, is identified for improvement in 2021 in accordance with the City’s Street Capital Improvement Program which provides for the long-term planning and management of street and transportation infrastructure throughout the City. PROPOSAL DETAILS/ANALYSIS: This Feasibility Report has been prepared to address street and drainage improvements programmed for construction in 2021. The report serves to identify the necessary improvements, the estimated project costs, and to consider the assessment of a portion of the project costs to properties adjacent to and benefitting from the improvements. The proposed project includes the reconstruction of Linden Trail North, within the Tamarack Farm Estates subdivision, including the one-way loop street at the northwest end of the subdivision, consisting of approximately 2,100 feet of roadway. The proposed improvements include a fully reconstructed street with new granular subbase drainage layer, new Class 6 aggregate base and new bituminous pavement. The existing bituminous curb will be replaced with new concrete curb and gutter to improve drainage, improve the construction quality, and provide edge control to protect and extend the service life of the new bituminous surface. Roadway widening is proposed along the one-way loop to increase the street width and turning radius to better accommodate maintenance and emergency vehicle access. The timing of these street improvements was determined by the City’s pavement management program. Upon review of the necessary street improvements, staff also reviews the street drainage systems and existing public utilities. In addition to the street improvements, the scope of this Report includes the restoration of the existing street drainage system, including either repair or replacement of existing drainage pipe and structures, and storm sewer casting replacement. Drainage improvements are limited to the necessary improvements to meet watershed rules and to prevent water from standing on or along the new street pavements, and are not intended to resolve pre-existing private property drainage issues. The Tamarack Farm Estates subdivision is a rural open space development consisting of 19 residential lots. The subdivision is served by private water wells and a community wastewater treatment system. The neighborhood resides outside of the City’s Municipal Urban Service Area (MUSA), therefore there are no current plans to extend public sanitary sewer to the neighborhood. However, public watermain currently exits directly adjacent to the subdivision, along 50th Street North. This Report therefore includes a preliminary layout to extend municipal water into the neighborhood to serve each of the 19 properties. An estimated project cost and corresponding unit assessment is reported to allow the City Council and property owners to make an informed decision as to whether connecting to the public water system is a desirable improvement to be completed at the time of the street reconstruction work. The neighborhood is not located in a known area for PFAS contamination or within a Special Well Construction Area. The total estimated street and drainage improvement cost is $645,000. The improvements would be partially assessed against the benefitting properties consistent with the City’s Special Assessment Policy. Street and drainage improvements are assessed at a rate of 30% of the total project costs for residential properties using a unit method. Residential properties are considered to provide an equal demand on street use and are therefore assessed on a per unit basis, including “flag” lots located on private streets. The remaining 70% of the project costs are paid through the City general fund. Residential properties along Linden Trail North with direct access to the street, vacant lots, and lots with direct access from a private street, are included as benefitting properties. Each property is assessed one unit unless the property has the ability to be subdivided using the current underlying land use and zoning regulations. The City planning department reviews larger parcels to determine if a parcel can be subdivided and the number of lots that could be obtained. The total estimated public watermain cost is $312,000. Watermain extension improvements are assessed 100% against the benefitting properties using per residential equivalent unit method. In addition to the watermain improvement assessment, each property will incur a $3,000 Water Availability Charge (WAC), a $1,000 Water Connection Charge, a meter fee and permit fee at the time they make the connection to the public watermain. Assessments for street and drainage improvements will be levied over a 15-year period. If watermain improvements are incorporated into the project, assessments for public watermain will be levied over a 20- year period. All assessments are be charged an interest rate of 1% over the bond rate for the project. In addition to the recommended improvements, the estimated project costs and the proposed assessments, this report addresses the permitting requirements and the easement and right-of-way acquisition needed to implement the improvements. The feasibility report findings and recommendations will be further presented at the meeting. FISCAL IMPACT: The total estimated street and drainage improvement cost is $645,000, with $193,800 paid through special assessments and the remaining $451,200 paid through the general tax levy. If watermain improvements are incorporated into the project, the total estimated public watermain cost is $312,000, with 100% paid through special assessments. RECOMMENDATION: Staff is recommending that the City Council approve a Resolution, receiving the Feasibility Report and calling a public hearing for the Tamarack Farm Estates Street Improvements. The recommended motion for this action is as follows: “Move to approve Resolution No. 2020-104, receiving the Feasibility Report and Calling a Public Hearing for the Tamarack Farm Estates Street Improvements.” ATTACHMENTS: 1. Resolution Receiving Report and Calling for Hearing on Improvements. 2. Notice of Hearing on Improvement. 3. Tamarack Farm Estates Street Improvements – Location Map. 4. Tamarack Farm Estates Street Improvements – Project Schedule. Feasibility Report (available for review at City Hall). CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2020-104 A RESOLUTION RECEIVING A FEASIBILITY REPORT FOR THE TAMARACK FARM ESTATES STREET IMPROVEMENTS AND CALLING HEARING ON IMPROVEMENT WHEREAS, pursuant to City Council authorization, adopted on October 6, 2020, a feasibility report has been prepared by FOCUS Engineering, Inc. for the Tamarack Farm Estates Street Improvements; and WHEREAS, the feasibility report recommends that benefitting properties be assessed all or a portion of the cost of the improvements pursuant to the City’s Special Assessment Policy and Minnesota Statutes, Chapter 429; and WHEREAS, the feasibility report provides information regarding whether the proposed improvement is necessary, cost-effective, and feasible; whether it should best be made as proposed or in connection with some other improvement; the estimated cost of the improvements as recommended; and a description of the methodology used to calculate individual assessments for affected parcels. NOW, THEREFORE, BE IT RESOLVED, 1. That the City Council will consider the improvements in accordance with the report and the assessments of the abutting properties for all or a portion of the cost of the improvements pursuant to Minnesota Statues, Chapter 429 at an estimated total project cost of $$645,000 for the street and drainage improvements, and $312,000 for extending watermain to the neighborhood should public watermain be requested or authorized. 2. A public hearing shall be held on such proposed improvements on the 19th day of January, 2021 and may be conducted in the Council Chambers of City Hall, or conducted by electronic means pursuant to Minnesota Statutes Section 13D.021 because of the COVID-19 pandemic, during a regularly scheduled City Council meeting at or approximately after 7:00 P.M. and the clerk shall give mailed and published notice of such hearing and improvement as required by law. ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE FIFTHTEENTH DAY OF DECEMBER, 2020. CITY OF LAKE ELMO By: __________________________ Mike Pearson (Seal) Mayor ATTEST: ________________________________ Julie Johnson City Clerk CITY OF LAKE ELMO NOTICE OF HEARING ON IMPROVEMENT TAMARACK FARM ESTATES STREET IMPROVEMENTS Notice is hereby given that the City Council of Lake Elmo will conduct a public hearing on Tuesday, January 19, 2021, at or approximately after 7:00 PM to consider the making of the following improvements, pursuant to Minnesota Statutes, Sections 429.011 to 429.111: Street and drainage improvements along Linden Trail North, within the Tamarack Farm Estates subdivision, including a reconstructed street with new granular subbase drainage layer, new Class 6 aggregate base, new bituminous pavement, and new concrete curb and gutter. The improvements will also incorporate the restoration of the existing street drainage system, including either repair or replacement of existing drainage pipe and structures. Due to the ongoing COVID-19 pandemic, members of the City Council will either participate in the meeting by telephone or other electronic means pursuant to Minnesota Statutes, Section 13D.021, or in-person at the City Council’s regular meeting place at Lake Elmo City Hall, 3800 Laverne Avenue North, Lake Elmo, Minnesota. The City will provide an update on the meeting method/type for the hearing on the City’s website at http://www.lakeelmo.org/ as the meeting gets closer and those details can be finalized with certainty. Additionally, questions or comments related to the public hearing may be emailed to Julie Johnson, City Clerk at jjohnson@lakeelmo.org, made by phone at 651.747.3914, or mailed to 3880 Laverne Avenue North, Suite 100, Lake Elmo, MN 55042. Comments submitted through these methods must be received by Tuesday, January 19, 2021 at 12:00 p.m. in order to be considered during the hearing. Please note that any emails, letters and attachments you send to the City are likely considered public information and the City staff may use them in staff reports that go to the City Council and/or the general public. The area proposed to be assessed for these improvements include properties abutting the above referenced streets or properties that gain direct driveway access from the above referenced streets. The estimated total cost for the project is $645,000 for the street and drainage improvements, and $312,000 for extending watermain to the neighborhood should public watermain be requested or authorized. A reasonable estimate of the impact of the assessment will be available at the hearing. Such persons as desiring to be heard with reference to the proposed improvements will be heard during this meeting. DATED: December 15, 2020 BY ORDER OF THE LAKE ELMO CITY COUNCIL Mike Pearson, Mayor (Published in the Stillwater Gazette on December 18, 2020 and December 25, 2020) LOCATION MAP FIGURE NO. 1 TAMARACK FARM ESTATES NEIGHBORHOOD CITY OF LAKE ELMO TAMARACK FARM ESTATES LEGEND PROJECT NO. 2020.125 TAMARACK FARM ESTATES STREET IMPROVEMENTS CITY LIMITS PROJECT STREETS LINDEN TRAIL N, FROM 50TH STREET N TO THE CUL-DE-SAC PROJECT SCHEDULE  CITY OF LAKE ELMO    TAMARACK FARM ESTATES STREET IMPROVEMENTS  PROJECT NO. 2020.125  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.   651.300.4261  Jack Griffin, P.E.                651.300.4264  Ryan Stempski, P.E.  651.300.4267  Chad Isakson, P.E.  651.300.4283                  OCTOBER 6, 2020  Council orders preparation of Feasibility Report and Topographic Survey.      DECEMBER 15, 2020  Presentation  of  Feasibility  Report.  Council  accepts  Report  and  calls  for  Improvement Hearing.       JANUARY 19, 2021  Public Improvement Hearing. Council Orders the Improvement (4/5th Vote)  and preparation of Plans and Specfications.    APRIL 6, 2021  Council approves Plans and Specifications and orders Advertisement for Bids.      MAY 6, 2021      Project Bid Date: Receive contractor bids.      MAY 18, 2021  Council accepts Bids and awards Contract.       JUNE 14, 2021    Conduct Pre‐Construction Meeting and issue Notice to Proceed.   OCTOBER 1, 2021    Substantial Completion.   NOVEMBER 19, 2021    Final Completion.                               *Final Assessment Hearing Schedule TBD